Wilcon, Inc., Plaintiff-Counterdefendant-Appellee Cross-Appellant v. The Travelers Indemnity Company, Defendant-Counterclaimant-Appellant Cross

654 F.2d 976, 1981 U.S. App. LEXIS 18351
CourtCourt of Appeals for the Fifth Circuit
DecidedAugust 20, 1981
Docket79-2888
StatusPublished
Cited by10 cases

This text of 654 F.2d 976 (Wilcon, Inc., Plaintiff-Counterdefendant-Appellee Cross-Appellant v. The Travelers Indemnity Company, Defendant-Counterclaimant-Appellant Cross) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fifth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilcon, Inc., Plaintiff-Counterdefendant-Appellee Cross-Appellant v. The Travelers Indemnity Company, Defendant-Counterclaimant-Appellant Cross, 654 F.2d 976, 1981 U.S. App. LEXIS 18351 (5th Cir. 1981).

Opinion

RANDALL, Circuit Judge:

This diversity case involves the construction of a sewage collection system for the City of Waveland, Mississippi. The litigants are Wilcon, Inc., a construction contractor that worked on the project, and The Travelers Indemnity Co., Inc. (Travelers), the surety that bonded the project. Wilcon brought this suit seeking damages from Travelers for “interference with business relations” and “abuse of process,” both of which torts allegedly occurred in connection with the Waveland construction project. Travelers then sought in a counterclaim to recover the cost of completing the project, which it assumed after Wilcon’s default. After a trial conducted by a magistrate, the jury found in favor of Wilcon on a general verdict and awarded $100,000 in compensatory damages and $1,500,000 in punitive damages; the jury also found in favor of Travelers on its counterclaim and awarded $1,000,000 in compensatory damages with respect thereto.

Each party now challenges the sufficiency of the evidence to support the judgment entered against it, and Travelers also challenges the sufficiency of the evidence to support the purportedly inadequate amount awarded on its counterclaim. We find that the evidence is insufficient to support the jury’s verdict in favor of Wilcon, and we therefore reverse that portion of the district court’s judgment entered pursuant thereto. We find that the evidence is sufficient to support the jury’s verdict on Travelers’ counterclaim, both as to liability and as to the amount, and we therefore affirm that portion of the judgment entered pursuant thereto.

I. THE FACTS

Wilcon, a Louisiana corporation, was from 1969 (its formation) to 1974 (the time of the events in question) a contractor specializing in underground construction; during this period Wilcon procured a number of payment and performance bonds (totalling approximately $7,500,000) from Travelers. Wilcon was and still is controlled by R. E. Wilson, its president and chief stockholder.

Howard L. Byrd, Contractor Building Services, Inc. (the Byrd Corporation) is a Mississippi corporation which at the time of these events was a contractor doing substantial underground construction work. The Byrd Corporation was and still is controlled by Howard L. Byrd, its president and chief stockholder.

In early 1972, Wilcon and the Byrd Corporation agreed to bid together on the con *979 struction of a proposed sewage collection system in Waveland, Mississippi. Although the details of their initial decision to consider a joint bid are in dispute, both parties agree that Joe Ashley, the manager of Travelers’ New Orleans office, played some role in the initiation of this relationship.

In July 1972, the City of Waveland awarded the construction job to Wilcon and the Byrd Corporation, whose joint offer was found by the Mayor and Board of Aldermen of Waveland to be the lowest and best bid. In August 1972, Travelers wrote both a payment and a performance bond on this project; each bond was issued to the City of Waveland in the amount of $2,284,041.30— the contract price of the successful bid.

Work began on the project in September 1972, with the Byrd Corporation responsible for construction on the east side of Wave-land and Wilcon responsible for the west side of the town; Wilcon did not itself begin the job, but instead subcontracted its entire portion to Ray Gray Construction Co. (Gray), a sole proprietorship. The Byrd Corporation and Gray worked together until June 1973, when the Byrd Corporation announced that it was financially unable to complete its portion of the project or to pay its outstanding bills. Wilcon thereupon decided to assume the entire project, and hired Gray to complete the Byrd Corporation’s portion as well as its own. Gray continued work until June 1974, at which point he notified Wilcon that he too was financially unable to complete the project or to pay his outstanding bills. Wilcon then commenced construction on its own, but Wilcon itself ceased work in early 1975. In March of that year, the City of Waveland terminated its contract and called upon Travelers to complete the project in accordance with its performance bond. Travelers immediately demanded performance or indemnity from Wilcon, but Wilcon refused. In April 1975 Travelers hired Wallace Industrial Constructors of Mississippi, Inc. to complete the Waveland project; this was done at a cost to Travelers (including attorneys fees and other expenses) of $1,551,-978.86.

Wilcon’s refusal to indemnify Travelers stems in large part from a dispute with Travelers over the form of business organization used by Wilcon and the Byrd Corporation with respect to their work on the Waveland project. Travelers contends that the two original contractors operated as a joint venture. Travelers relies for this assumption on a variety of relevant documents that read in terms of a “joint venture;” on some testimonial evidence that indicates that the parties treated the arrangement as a joint venture; and on the fact that only Wilcon and the Byrd Corporation — not any separate entity formed by the two contractors — complied with state contractor certification requirements. Travelers argues that as a joint venturer Wilcon is liable under a general indemnity agreement signed by Wilcon in 1970; that agreement by its own terms is applicable to all bonds issued on projects contracted by Wilcon as sole principal or as joint venturer. 1

However, Wilcon contends that the contract with the City of Waveland was held not by Wilcon and the Byrd Corporation as joint venturers, but instead by a separate corporation formed on June 1, 1972 for the sole purpose of bidding and completing the Waveland project. This new corporation was given the confusing name of “Howard L. Byrd, Contractor Building Services and *980 Wilcon, Inc.” (hereinafter the “Combined Corporation”). The Combined Corporation was originally owned in equal shares by Byrd and Wilson, but upon his default Byrd tendered all of his shares to Wilson. Wilcon argues that the Combined Corporation held the construction contract with the City of Waveland and subcontracted equal portions of the Waveland project to Wilcon and the Byrd Corporation. In circumstances like this — where contractors form a new corporation to bid and complete a single project, and then subcontract the project to themselves — Travelers ordinarily requires the execution by the “subcontractors” of a special indemnity agreement by which they became directly responsible to Travelers. In this case, however, Travelers failed to require the execution by Wilcon and the Byrd Corporation of. such an agreement; accordingly, Wilcon has argued since its default that it has no indemnity obligation to Travelers on the Waveland project.

Travelers contends that Wilcon is liable for the completion of the Waveland project even if one assumes arguendo the validity of the Combined Corporation and its subcontracts to Wilcon and the Byrd Corporation. This contention rests on two separate theories, each of which rests in turn on disputed facts. First, Travelers argues that the Combined Corporation acted only as agent for its two purported subcontractors; according to this theory, Wilcon is a principal to the contract and therefore liable under the general indemnity agreement just as if the Combined Corporation had never been formed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Tunstall v. Glidewell
S.D. Alabama, 2020
Arntz Contracting Co. v. St. Paul Fire & Marine Insurance
47 Cal. App. 4th 464 (California Court of Appeal, 1996)
Laitram Machinery, Inc. v. Carnitech A/S
884 F. Supp. 1074 (E.D. Louisiana, 1995)
Rebecca Laughlin v. The Prudential Insurance Co.
882 F.2d 187 (Fifth Circuit, 1989)
Albert Neumann v. Henri Vidal
710 F.2d 856 (D.C. Circuit, 1983)
Hayes v. Irwin
541 F. Supp. 397 (N.D. Georgia, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
654 F.2d 976, 1981 U.S. App. LEXIS 18351, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilcon-inc-plaintiff-counterdefendant-appellee-cross-appellant-v-the-ca5-1981.