Wilcher v. Amerititle, Inc.

157 P.3d 790, 212 Or. App. 498, 2007 Ore. App. LEXIS 673
CourtCourt of Appeals of Oregon
DecidedMay 9, 2007
Docket0002690CV; A125597
StatusPublished
Cited by4 cases

This text of 157 P.3d 790 (Wilcher v. Amerititle, Inc.) is published on Counsel Stack Legal Research, covering Court of Appeals of Oregon primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilcher v. Amerititle, Inc., 157 P.3d 790, 212 Or. App. 498, 2007 Ore. App. LEXIS 673 (Or. Ct. App. 2007).

Opinion

LANDAU, P. J.

This is a case in which a dispute between contractors about the construction of an $8,000 chimney was transformed into claims against a title company for breach of contract and negligence totaling in excess of $200,000. The trail from the chimney dispute to the action against the title company is a convoluted one and, indeed, its very convolution is at the core of the arguments on appeal. Suffice it to say at this introductory juncture that the case ultimately went to a jury, which found in favor of one of the contractors and awarded damages against the title company for both noneconomic and economic loss. The title company now appeals, arguing that it was entitled to judgment as a matter of law on both the non-economic and economic damage awards on the ground that any such harm that plaintiff suffered was simply not a foreseeable consequence of anything that the title company did. We agree and reverse in part.

I. FACTS

The relevant facts are rather involved. They are for the most part uncontroverted, however. The story begins with the construction of a house. Plaintiff is a contractor who builds “spec” homes. In 1997, he obtained a $160,000 line of credit from C & K Markets, Inc. 401(k) Profit Sharing Plan (C & K), to finance the construction of one such spec home. Plaintiff hired Mark Wendt Homes, Inc. (Wendt), to build a chimney for the home. Plaintiff thought the construction of the chimney would cost around $8,000. Wendt completed construction of the chimney in July 1997. Plaintiff, however, did not pay Wendt for the work; among other things, plaintiff thought that Wendt wanted too much money for the project. On September 12,1997, Wendt filed a construction lien in the amount of $13,610.

In the meantime, C & K had advanced plaintiff approximately $150,000 of the $160,000 line of credit. Plaintiff, however, had not made any interest payments as required under the terms of the loan. Plaintiff ultimately defaulted entirely, and, in March 1998, C & K recorded a trustee’s notice of sale of the property, based on plaintiffs failure to make payments on the loan and on his failure to [501]*501resolve the lien that Wendt had filed. The sale was scheduled for August 5, 1998.

Notwithstanding C & K’s notice, plaintiff listed the property for sale in late spring 1998. Harold and Nancy Soucy offered to purchase the property from plaintiff for $250,000. As part of the deal, the Soucys agreed to pay off the Wendt lien — which, with accumulating interest and attorney fees, had grown to approximately $20,000 — and to pay off plaintiffs obligation to C & K.

This is where defendant enters the story. Defendant is the title company that the Soucys hired to make the escrow arrangements for the sale of plaintiffs property. Plaintiff had no contact with defendant in setting up the escrow arrangements.

The Soucys then met with Wendt to negotiate their own settlement with Wendt. The Soucys brought with them Gary Hart, whose child was married to the Soucy’s child and who also owned a nursery. Under the terms of the settlement with Wendt, the Soucys agreed to pay $3,000 in cash, while Hart agreed to contribute $9,000 worth of nursery stock. The Soucys informed plaintiff of the settlement, and plaintiff approved. Neither the Soucys nor Wendt, however, executed the document that memorialized the settlement.

Defendant, which had no knowledge of those settlement talks, proceeded with the closing. On July 22, 1998, Jean Phillips, one of defendant’s employees, contacted all of plaintiffs creditors to determine the exact amounts necessary to release the liens against the property. She contacted Wendt’s lawyer to obtain the payoff amount to satisfy the construction lien. In the course of that conversation, the lawyer asked Phillips about the sale price for plaintiffs property. Phillips told the lawyer that it was selling for $250,000. The significance of the disclosure of that sale price turns out to be the heart of the dispute between plaintiff and defendant.

Wendt decided not to go forward with the settlement with the Soucys. Wendt testified that he made that decision because an inspection of the nursery stock that Hart had offered revealed that the trees had no real value. Harold Soucy testified that Wendt had told him that he had backed [502]*502out of the settlement because his lawyer, having learned of the $250,000 sale price, advised him not to compromise. In either event, Wendt did not settle. The Soucys meanwhile decided to proceed with the purchase. That meant that plaintiff was entitled to insist that the Soucys pay Wendt the full amount of the construction lien.

Plaintiff, however, elected not to enforce that obligation. Instead, he obtained, for the sum of $816, a release bond on the Wendt lien. The sale to the Soucys closed on July 30, 1998. Nothing was deducted from the sale price to satisfy Wendt’s construction lien. The C & K loan was paid in full, and the Soucys took possession of the property.

At this point, heretofore completely unrelated transactions come into play. Plaintiff had problems with other creditors, including Merland Rice, who had sued plaintiff for $72,997, plus interest. On September 22, 1998, plaintiff allowed a judgment to be taken against him for that amount. At the same time, the Oregon Department of Revenue obtained a judgment against plaintiff for unpaid employment taxes.

All the while, the Wendt construction lien remained unpaid. The matter came to trial in June 2000. The trial court entered judgment in favor of Wendt for a principal amount of $11,600, plus interest and attorney fees, which ultimately totaled something in excess of $60,000. Plaintiff appealed the judgment, but we affirmed. Mark Wendt Homes, Inc. v. Wilcher, 186 Or App 416, 63 P3d 1271 (2003).

In the meantime, since the filing of the Wendt construction lien, plaintiff found it increasingly difficult to borrow money. Because of the filing of the liens, and because of the outstanding judgments against him, plaintiffs credit score decreased, resulting in lenders offering him financing subject to increased interest rates that made borrowing financially unappealing.

Plaintiff sued defendant, which, it will be recalled, was the title company that had handled the escrow for the sale of his property to the Soucys. Plaintiff alleged three claims: breach of implied contract, negligence, and “breach of confidentiality.”

[503]*503According to the allegations of the complaint, defendant breached an implied obligation to maintain confidences when defendant’s employee, Phillips, disclosed the $250,000 sale price to Wendt’s attorney. As a result of that breach, the complaint alleges, plaintiff suffered economic harm in the amount of $816 for the cost of the lien release bond and $101,329.67 in attorney fees that plaintiff was forced to spend litigating the $11,600 Wendt construction lien matter, occasioned by Wendt backing out of the settlement with the Soucys following the disclosure of the sale price.

The negligence claim was based on the same allegations, including the allegations that, as a result of the negligent disclosure of the Soucy transaction sale price, plaintiff was forced to spend the $816 for the bond and the $101,329.67 in attorney fees. In addition, plaintiff alleged that he had suffered $100,000 in noneconomic harm to his reputation for timely paying bills.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pacificorp v. Northwest Pipeline GP
879 F. Supp. 2d 1171 (D. Oregon, 2012)
Stuart v. Pittman
230 P.3d 958 (Court of Appeals of Oregon, 2010)
Wilcher v. Amerititle, Inc.
157 P.3d 790 (Court of Appeals of Oregon, 2007)

Cite This Page — Counsel Stack

Bluebook (online)
157 P.3d 790, 212 Or. App. 498, 2007 Ore. App. LEXIS 673, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilcher-v-amerititle-inc-orctapp-2007.