Wilbur Waggoner Equipment Rental & Excavating Co. v. Bumiller

542 S.W.2d 32
CourtMissouri Court of Appeals
DecidedAugust 3, 1976
Docket36548 and 37235
StatusPublished
Cited by6 cases

This text of 542 S.W.2d 32 (Wilbur Waggoner Equipment Rental & Excavating Co. v. Bumiller) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wilbur Waggoner Equipment Rental & Excavating Co. v. Bumiller, 542 S.W.2d 32 (Mo. Ct. App. 1976).

Opinion

RENDLEN, Judge.

Plaintiff Wilbur Waggoner Equipment Rental and Excavating Company, Inc. (hereinafter Waggoner) and Barbara J. Osborne, one of several defendants, separately appeal portions of the judgment in this court-tried case.

On July 17, 1969, defendant Earl Bumil-ler contracted to sell a parcel of land in the City of St. Louis owned by Bumiller and his wife Doris to Tractor-Trailer Supply Company, Inc., agreeing to demolish the existing building and bring the lots to street grade. Three days earlier, in anticipation of the sales agreement, Bumiller entered into a demolition contract with defendant Willard Hart, d/b/a B & B Building Materials and Hart Wrecking Company, 1 (hereinafter Hart) to raze the building for $22,280. This contract bore a signature purporting to be that of Barbara J. Osborne as a contract-. ing party with Hart. On July 9, Hart had obtained a bond with Maryland Casualty Company (hereinafter Maryland) as surety securing performance of the proposed contract and the bond application form also bore the purported signature of Barbara J. Osborne. Later Hart contracted with Wag-goner to furnish men and equipment for the work but in October of that year Hart abandoned the partially finished job and Bumiller who had paid Hart $19,675 (from which Hart had paid Waggoner only $4,000) contracted with Arch Contracting Company to complete the demolition and grading.

The following resumé of the pleadings provides a background for segregating issues and identifying relationships of the *34 parties. The suit was tried on Waggoner’s second amended petition, asserting in Count I its claim for mechanic’s lien against the land of Bumiller and for money judgment of $13,128.40 against all defendants individually and against Hart and Osborne, d/b/a B & B Building Materials and Hart Wrecking Company. 2 The court awarded judgment of $13,128.40 against Hart and Osborne but denied plaintiff’s claims for mechanic’s lien and money judgment as to the Bumillers. Waggoner’s claim under Count II against Maryland (then a third-party defendant) as third-party beneficiary under the “surety bond” was denied.

Bumiller cross-claimed against Osborne and Hart, obtaining judgment for breach of contract against both in the amount of $7,300. Osborne answered, denying the contracts were “signed by this defendant [Osborne] or that it was signed by any other person under her direction, instruction or authority.” The parties stipulated that Barbara J. Osborne did not sign the papers purporting to bear her signature.

By third-party petition Bumiller, seeking indemnification on the performance bond, obtained judgment against Maryland in the amount of $7,300. Maryland answered, admitting suretyship but successfully cross-claimed against Hart and Osborne as principals on the bond, holding them liable in the amount of $7,300 for the judgment on Bu-miller’s third-party claim. Maryland’s cross-claim refers to defendants Hart and Osborne “individually and as partners d/b/a B & B Building Materials.”

Hart’s counter-claim charging Waggoner with negligence in razing the building was denied. 3

. WAGGONER’S APPEAL

In its appeal Waggoner contends the court erred: (1) in finding that plaintiff was not a third-party beneficiary under Hart’s performance bond; and (2) in refusing plaintiff’s claim for mechanic’s lien (a) because contrary to the court’s finding, the evidence showed that the demolition contract was part of an overall plan to erect a new building, and (b) the court erroneously found Doris Bumiller did not authorize Earl Bumiller to act for her when executing the sales and demolition contract.

Considering Waggoner’s contentions of third-party beneficiary status and right of direct action on the bond, we look to the language of the instruments. The bond binds Hart and Maryland to Bumiller in the sum of $22,280. The further operant portion provides:

Whereas, the principal [Hart] has entered into a certain written agreement dated the 7th day of July A.D. 1969, with the owner [Bumiller] . . .for wrecking . which agreement is or may be attached hereto for reference. Now, therefore, the condition 4 of this obligation is such, that if the principal shall well and truly perform and carry out the covenants, terms and conditions of said agreement, this obligation to be void; otherwise to remain in full force and effect.

No express or implied obligation appears requiring Hart or Maryland to pay for labor or materials provided by others. However the demolition contract, 5 incorporated by reference, provides that Hart “wreck” the building, obtain permits, certificates of in *35 surance including workmen’s compensation and a completion bond. Further Bumiller was to advance $2,000 at signing and thereafter make progress payments as the work advanced—

[U]pon the presentation of the parties of the first part [Hart] of their expenses provided that receipts will be furnished for all the monies previously outlayed. (Emphasis added.)

Waggoner contends this quoted portion of the contract constitutes an implied promise to pay all laborers and materialmen, providing it (Waggoner) a direct right of action on the bond under the holding in LaSalle Iron Works, Inc. v. Largen, 410 S.W.2d 87, 92 (Mo. banc 1966). We do not agree.

The bond was executed to Bumiller as sole obligee, conditioned on Hart’s performance of the contract. Before a third party, furnishing labor or material but not named in the bond or contract nor privy to the consideration, may sue thereon, it must be found the bond was entered into for his benefit. The intention to benefit the “third-party” laborer or materialman may be found if, as found in LaSalle, supra at 89, the bond is conditioned “that the contractor shall pay all claims for labor and materials, or that he shall pay laborers and materialmen.” Explaining its holding, the court in LaSalle, supra at 90, citing 77 A.L.R., l.c. 31, stated:

[I]f there is an actual promise by the obligors to pay the third party, either by express words or by reasonable implication, there is no need to speculate for whose benefit the undertaking [bond] was made. Of course, the question of intention to benefit cannot be eliminated altogether in considering the rights of third parties, since in many cases the promise for their benefit is not clearly expressed and the meaning of the instrument is doubtful.

There the bond was conditioned that the principal should reimburse and pay the obli-gee for all outlays and expenses incurred in making good any default of the principal and further that the principal—

[SJhall pay all persons who have contracts directly with the Principal for labor or materials, . . . Supra at 88. (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Haz-Mat Response, Inc. v. Certified Waste Services Ltd.
896 P.2d 393 (Court of Appeals of Kansas, 1995)
Catalina Mortg. Co., Inc. v. Monier
800 P.2d 574 (Arizona Supreme Court, 1990)
Farmers Produce Exchange No. 202 v. Mudd
671 S.W.2d 334 (Missouri Court of Appeals, 1984)
Norman v. Norman (In Re Norman)
32 B.R. 562 (W.D. Missouri, 1983)
Ceco Corp. v. Plaza Point, Inc.
573 S.W.2d 92 (Missouri Court of Appeals, 1978)
J. Louis Crum Corp. v. Alfred Lindgren, Inc.
564 S.W.2d 544 (Missouri Court of Appeals, 1978)

Cite This Page — Counsel Stack

Bluebook (online)
542 S.W.2d 32, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wilbur-waggoner-equipment-rental-excavating-co-v-bumiller-moctapp-1976.