WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4

CourtCalifornia Court of Appeal
DecidedOctober 30, 2020
DocketA157568
StatusUnpublished

This text of WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4 (WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4, (Cal. Ct. App. 2020).

Opinion

Filed 10/30/20 WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4 NOT TO BE PUBLISHED IN OFFICIAL REPORTS California Rules of Court, rule 8.1115(a), prohibits courts and parties from citing or relying on opinions not certified for publication or ordered published, except as specified by rule 8.1115(b). This opinion has not been certified for publication or ordered published for purposes of rule 8.1115.

IN THE COURT OF APPEAL OF THE STATE OF CALIFORNIA

FIRST APPELLATE DISTRICT

DIVISION FOUR

WIFI RAIL, INC., Plaintiff and Appellant, A157568 v. SAN FRANCISCO BAY AREA (Alameda County RAPID TRANSIT DISTRICT, Super. Ct. No. RG16809176) Defendant and Respondent.

Plaintiff WiFi Rail, Inc. (WiFi Rail) entered into a license agreement with defendant San Francisco Bay Area Rapid Transit District (BART) whereby WiFi Rail agreed to install, operate, use, replace, modify and maintain a commercial wireless internet network for the BART system. WiFi Rail contends that BART breached this license agreement by terminating WiFi Rail without proper notice and an opportunity to cure. A jury found that WiFi Rail did not do all, or substantially all, of the significant things that the license agreement required it to do, and, as it was instructed, it answered no further questions on the special verdict form. The trial court entered judgment for BART on the jury’s verdict, and this appeal involves only the denial by operation of law of WiFi Rail’s motion for judgment notwithstanding the verdict (JNOV) on its breach of contract claim. As it did below, WiFi Rail seeks to overturn the judgment for a new judgment

1 entirely in its favor with a new trial for damages only. Because there is a contested issue of fact as to whether BART’s alleged breach caused WiFi Rail harm, WiFi Rail is not entitled to the JNOV that it seeks. We shall affirm the order denying JNOV by operation of law. FACTUAL AND PROCEDURAL BACKGROUND WiFi Rail incorporated in 2006 with the goal of enabling cellular and internet service on public rail transportation. In 2006, the CEO of WiFi Rail, Cooper Lee, contacted BART to see if BART was willing to allow WiFi Rail to test its concept. BART was a particularly attractive target for Lee because BART maintained a live-train test track in Hayward. Chuck Rae, BART’s then Telecommunications Revenue Manager, responded to Lee, and BART allowed WiFi Rail to utilize its test facility to conduct research and development. WiFi Rail conducted its research at BART’s Hayward test track and in BART’s downtown San Francisco stations and track. The License Agreement WiFi Rail and BART entered into a WIFI License Agreement (the Agreement) on December 15, 2008 for WiFi Rail to provide wireless internet (wifi) service in contractually-designated coverage areas, including all BART passenger rail cars operating on the BART right-of-way, all publicly accessible areas inside the fare gates of all above-ground BART stations, and all publicly accessible areas of BART underground stations, whether inside or outside the fare gates, and including platforms, mezzanines and public corridors, but excluding low-traffic areas identified during the BART design review process. BART granted WiFi Rail a license to install, operate, and use equipment and facilities on the BART System. With limited exceptions for use of existing BART structures and equipment set forth in the Agreement, the Agreement required WiFi Rail to supply and install the all components of

2 the “Wifi Infrastructure” at its sole expense, “including but not limited to (i) all fiber optic cable; (ii) all towers, antennas, insertion couplers, electronics, power supplies and other equipment; (iii) all in-car components; (iv) all internet bandwidth and connectivity; and (iv) all utility connections” (the wifi infrastructure). The Agreement contains a schedule for installation of the wifi infrastructure in five phases: Phase 1 (four stations); Phase 2 (nine stations); Phase 3 (thirteen stations); Phase 4 (thirteen stations); and Phase 5 (six stations). WiFi Rail was to provide wifi in BART stations and cars that would commence, with respect to the required coverage areas located in each phase, upon the completion of each phase and that would continue thereafter during the remaining term of the Agreement. WiFi Rail was required to provide wifi service that would “always equal or exceed the performance provided by leading industry service providers.” The Agreement provides that the details of the wifi infrastructure and its installation schedule shall be determined during the BART Design Approval Process. The Agreement does not contain a fixed time for performance, but states that an installation schedule would be established during BART’s design review process. The Agreement provides that the installation schedule would target completion of the entire wifi infrastructure within 24 months after BART’s design review process approval for Phases 1 and 2. The Agreement also states that time was of the essence. WiFi Rail was entitled to recoup its payment for construction costs by selling advertising and charging passengers for wifi service after completion of Phase 2. Upon BART’s certification of substantial completion for Phase 2, WiFi Rail would owe BART a license fee, and the Agreement sets forth a

3 license fee schedule of $40,000 per station starting in 2009, with a 3.5 percent increase per year thereafter starting January 1, 2010. The term of the Agreement was from December 18, 2008 to December 31, 2019. Upon the occurrence of “an event of default,” the Agreement provides that “each party shall have all rights and remedies specified herein or available at law or in equity,” and “[e]ither party shall have the right to terminate this Agreement if an event of default by the other party exists.” As relevant here, the Agreement defined the following as an “Event of Default”: “[I]f WiFi Rail materially fails to perform any other covenant [besides payment of fees set forth in subsections (i) and (ii)] in this Agreement within thirty (30) days after written notice from BART specifying the failure; provided, that if such failure cannot, with due diligence be cured within a period of thirty (30) days, WiFi Rail shall not be deemed to be in default if WiFi Rail begins to cure the failure within such thirty (30) day period and thereafter diligently prosecutes such cure to completion.” Section 20.2, entitled “Notices,” states: “All notices under this Agreement shall be in writing and shall be deemed validly given if sent by courier, overnight mail, facsimile transmission or regular certified mail, return receipt requested, and shall be effective upon receipt.” This section also provides that notices “should be” addressed to the recipients for each party noted therein. The Project BART issued a construction permit to WiFi Rail in January 2009, which, pursuant to the Agreement, evidenced its approval of WiFi Rail’s plans and engineering drawings. Sometime thereafter, the parties entered into an agreement for a separate test project wherein WiFi Rail would install

4 and test a “proof-of-concept” video surveillance network in train cars for the BART police.1 In the second half of 2010, Lee wrote to WiFi Rail shareholders to explain why he had secured proxy votes to replace the Board of Directors. In this letter, he stated that the company had ceased focusing on the project with BART in 2010, and it had all but stopped work on Phase 2. He wrote that senior management had “diluted [WiFi Rail’s] limited resources in pursuit of potential opportunities in other sectors of the transportation industry,” and nearly all of the company’s money had been spent on executive compensation and travel expenses for fundraising and pursuit of other opportunities.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Oasis West Realty v. Goldman
250 P.3d 1115 (California Supreme Court, 2011)
Haley v. Casa Del Rey Homeowners Ass'n
63 Cal. Rptr. 3d 514 (California Court of Appeal, 2007)
Casella v. SouthWest Dealer Services, Inc.
69 Cal. Rptr. 3d 445 (California Court of Appeal, 2007)
Sweatman v. Department of Veterans Affairs
18 P.3d 29 (California Supreme Court, 2001)
Lee v. West Kern Water District
5 Cal. App. 5th 606 (California Court of Appeal, 2016)
Sanchez v. Brooke
204 Cal. App. 4th 126 (California Court of Appeal, 2012)
Brown v. City of Sacramento
249 Cal. Rptr. 3d 801 (California Court of Appeals, 5th District, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
WiFi Rail, Inc. v. S.F. Bay Area Rapid Transit Dist. CA1/4, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wifi-rail-inc-v-sf-bay-area-rapid-transit-dist-ca14-calctapp-2020.