Wickland v. Snyder

565 P.2d 976, 39 Colo. App. 403
CourtColorado Court of Appeals
DecidedJune 9, 1977
Docket76-484
StatusPublished
Cited by18 cases

This text of 565 P.2d 976 (Wickland v. Snyder) is published on Counsel Stack Legal Research, covering Colorado Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickland v. Snyder, 565 P.2d 976, 39 Colo. App. 403 (Colo. Ct. App. 1977).

Opinion

565 P.2d 976 (1977)

G. L. WICKLAND, Plaintiff-Appellee and Cross-Appellant,
Buffalo Oil Corporation, Plaintiff,
v.
Jim SNYDER, d/b/a Jim Snyder Drilling Company, Defendant and Third-Party Plaintiff-Appellant and Cross-Appellee,
v.
Cecil J. OSBORNE, Third-Party Defendant.

No. 76-484.

Colorado Court of Appeals, Div. II.

June 9, 1977.

*977 Welborn, Dufford, Cook & Brown, Philip J. Dufford, Beverly J. Quail, Denver, for plaintiff-appellee and cross-appellant.

Davis, Graham & Stubbs, Donald E. Phillipson, Brian T. Dolan, Denver, for defendant and third-party plaintiff-appellant and cross-appellee.

ENOCH, Judge.

Defendant, Jim Snyder, appeals a judgment of $75,000 for breach of contract entered against him and in favor of plaintiff G. L. Wickland. We affirm.

The action arose as a result of the mislocation of two oil and gas wells which defendant contracted to drill for plaintiff. Plaintiff had an oil and gas lease covering several contiguous 40-acre tracts in Weld County where the wells were to have been drilled.

Well No. 1 was completed in January 1974 at a contract price of $27,240. This well produced both oil and gas, but was completed as a shut-in gas well primarily because of a lack of pipeline facilities. Well No. 2 was completed in June 1974, at a contract price of $27,180. This well was a dry hole.

In September 1974 another leaseowner in the area informed plaintiff that well No. 1 might be in the wrong location. A resurvey by defendant's surveyor completed in October 1974 revealed that the wells were apparently mislocated, and plaintiff's own survey, completed in March 1975, confirmed that both wells were several hundred feet west of their intended location. Well No. 1 was in fact on an adjacent lessee's acreage, and well No. 2, while still on plaintiff's lease, was on a different 40-acre tract than that designated in the contract. Plaintiff was able to secure rights to the production of well No. 1, by granting the lessee of that acreage a 12½ overriding royalty.

A summary judgment as to liability was entered in plaintiff's favor and the issue of damages was tried to the court.

Defendant agrees that the trial court was correct in measuring the damages by the cost of drilling the wells in the proper location, see Landauer v. Huey, 143 Colo. 76, 352 P.2d 302, less the value of benefits received by plaintiff as a result of the holes drilled in the wrong locations. See Wells Aircraft Parts Co. v. Allan J. Kayser Co., 118 Colo. 197, 194 P.2d 326. Defendant contends on appeal, however, that the court used the wrong time period in determining the cost of drilling and incorrectly determined the value of the benefits received by plaintiff.

Defendant asserts that in ascertaining damages the trial court should have used the cost of drilling each well at the time performance was due or at the time the breach was discoverable, so that plaintiff could have obtained substitute performance.

We conclude that defendant has failed to preserve this issue for appeal. As to the issue of the cost of drilling, the only relevant grounds asserted at trial by defendant's then counsel was a general statement that the damages were excessive and contrary to the law and evidence. No memorandum brief specifically addressing the cost of drilling accompanied the motion for new trial. The case was tried by both sides as if costs of drilling were to be measured as of the time of trial. The only suggestion that a different time should be used was a brief comment by defendant's trial attorney and by the third-party defendant's (surveyor's) attorney during closing arguments that the costs should be the approximately $27,000 paid for the wells at the time they were drilled, rather than the cost at trial, which was found to be $40,000 per well.

A matter which has not been raised or considered in the trial court will not be *978 ruled upon on review even if it may be applicable. Denver v. Miller, 151 Colo. 444, 379 P.2d 169. A change in the theory as to the measure of damages is one of the matters to which this rule applies. See Lexington Colorado Auto Co. v. Grigsby, 76 Colo. 328, 231 P. 160.

Also, a judgment will generally not be reversed because the trial judge adopted a wrong reason in reaching a conclusion which might be correct. Fleming v. Wells, 45 Colo. 255, 101 P. 66. See Klipfel v. Neill, 30 Colo.App. 428, 494 P.2d 115. The valuation of drilling costs here would be supportable under the evidence currently in the record, even if the measure of damages now advocated was applied in this case. Therefore, we decline to review this issue further. See Walker v. Casto, 150 Colo. 332, 372 P.2d 438.

Both parties contest the amount of benefits found by the court to have accrued to plaintiff as a result of defendant's drilling in the wrong place. The court estimated these benefits at approximately $8,760.

Defendant contends that plaintiff accepted the benefit of both wells, and that the measure of the benefit received is the reasonable value of the services rendered by defendant, or approximately $27,000 per well. The correct measure of value, however, is the value to the person benefitted, and the contractual rate, while some evidence of the value of the benefit, is not conclusive. Nordin Construction Co. v. City of Nome, 489 P.2d 455 (Alaska). Also making the best of a bad situation does not necessarily signify retention of the benefit. Nordin Construction Co., supra.

Rather than being an attempt to acquire a costless bargain, see Leoffler v. Wilcox, 132 Colo. 449, 289 P.2d 902, the lease procured by plaintiff from the true lessee for well No. 1 was a reasonable effort to mitigate damages. Plaintiff had spent almost $57,000 above the cost of drilling to complete the well after it was drilled and before learning of the error in location. In order to protect this expenditure, plaintiff had to grant the 12½ overriding royalty to the original lessee. Even if this well should eventually be productive, plaintiff will receive substantially less total revenue than from a comparable well on his original lease.

Although we recognize that it is not presently known whether a well in the proper location would have been superior or inferior to the well actually drilled, still the increased burden of the override was a proper factor for the court to consider in determining the net benefit from well No. 1 accruing to plaintiff. The burden was on defendant to show the value of the benefit, Nordin Construction Co., supra, and there was only minimal evidence by defendant to show the value of well No. 1 as a producing well. Therefore we cannot say that the court erroneously undervalued the benefit received.

Plaintiff received no benefit from well No. 2, except for the geologic information derived therefrom. Since this well was not in the proper location, the contract price again is not conclusive as to the value of the benefit received by plaintiff.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southern Colorado Mri, Ltd. v. Med-Alliance, Inc.
166 F.3d 1094 (Tenth Circuit, 1999)
Frost v. Schroeder & Co., Inc.
876 P.2d 126 (Colorado Court of Appeals, 1994)
Schmidt v. Frankewich
819 P.2d 1074 (Colorado Court of Appeals, 1991)
Goldman v. Union Bank and Trust
765 P.2d 638 (Colorado Court of Appeals, 1988)
Timothy C. Wirt, M.D., P.C. v. Prout
754 P.2d 429 (Colorado Court of Appeals, 1988)
Alzado v. Blinder, Robinson & Co., Inc.
752 P.2d 544 (Supreme Court of Colorado, 1988)
Mohawk Green Apartments v. Kramer
709 P.2d 955 (Colorado Court of Appeals, 1985)
People in Interest of CAJ
709 P.2d 604 (Colorado Court of Appeals, 1985)
Combined Communications Corp. v. Bedford Motors, Inc.
702 P.2d 281 (Colorado Court of Appeals, 1985)
Yoder v. Hooper
695 P.2d 1182 (Colorado Court of Appeals, 1985)
Johns v. Colorado Real Estate Commission
697 P.2d 410 (Colorado Court of Appeals, 1984)
Sisneros v. First National Bank of Denver
689 P.2d 1178 (Colorado Court of Appeals, 1984)
Ruff v. Yuma County Transportation Co.
690 P.2d 1296 (Colorado Court of Appeals, 1984)
New Sheridan Hotel & Bar, Ltd. v. Commercial Leasing Corp.
645 P.2d 868 (Colorado Court of Appeals, 1982)
State Farm Mutual Automobile Insurance Co. v. Meyer
647 P.2d 683 (Colorado Court of Appeals, 1982)
Kudler v. Smith
643 P.2d 783 (Colorado Court of Appeals, 1981)

Cite This Page — Counsel Stack

Bluebook (online)
565 P.2d 976, 39 Colo. App. 403, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickland-v-snyder-coloctapp-1977.