Wickes Corp. v. Frye

273 N.W.2d 663, 202 Neb. 23, 1979 Neb. LEXIS 975
CourtNebraska Supreme Court
DecidedJanuary 3, 1979
Docket41779
StatusPublished
Cited by6 cases

This text of 273 N.W.2d 663 (Wickes Corp. v. Frye) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wickes Corp. v. Frye, 273 N.W.2d 663, 202 Neb. 23, 1979 Neb. LEXIS 975 (Neb. 1979).

Opinion

Spencer, C. J.,

Pro Tem.

This is an action to foreclose a mechanic’s lien. The District Court found in favor of The Wickes Cor *24 poration and entered a decree of foreclosure. The homeowners, Loyd Reisig and Ruth B. Reisig, filed this appeal. Loyd Reisig died November 2, 1978, and his interest is represented on appeal by his wife as the personal representative of his estate. Defendants contend plaintiff did not establish its lien and in any event should be estopped from enforcing it. We affirm the judgment of the District Court.

The mechanic’s lien was filed November 13, 1975, in the amount of $2,003.33. This figure represents the purchase price of sheetrock, casement windows, and a patio door, allegedly incorporated into the house. The materials which are the subject of the lien were ordered from plaintiff’s Fort Collins, Colorado yard by Kenneth A. Frye, the general contractor. Théy were shipped from Fort Collins and delivered on August 22, 1975. Defendants were informed by Frye on November 24, 1975, that plaintiff had filed a lien against their property. Frye did not complete the contract.

As a result of a meeting held on November 24, 1975, between Frye and Loyd Reisig, a mutual release was executed. Part of this release agreement required Reisig to satisfy the mechanic’s lien which had been filed by Wickes. Frye left town in December 1975, without performing any of the obligations contained in the release.

Michael Webb, a contractor associated with Pine Tree Builders, testified his company subcontracted with Frye to do part of the work on the house. Frye was responsible for providing the materials and Webb suggested he purchase the materials from Wickes Lumber Company in Fort Collins, Colorado. Webb was present at a building project in Henry, Nebraska when a truck arrived loaded with shake shingles, sheetrock, and windows. He stated he did not remember who provided the truck although he referred to it once as the Wickes’ truck after plaintiff’s counsel referred to it as such. Two of his em *25 ployees unloaded some of the shake shingles in Henry and then accompanied the truck to the Reisig house. The next day Webb observed shingles, sheet-rock, and windows in the front of the Reisig house. On his next visit to the house the drywall work had been completed.

Webb’s company was not paid for its work on the house and it filed a mechanic’s lien. At the end of November or the first part of December, after the lien had been filed, Webb received a call from Loyd Reisig. Reisig promised to pay the amount owing if Pine Tree Builders would perform some extra work. Webb agreed. Part of the work was to set the windows, which was done shortly after the telephone conversation. Webb did not measure the windows but he knew they were casement windows. He stated, “As far as I know they came off of the Wickes’ truck.” One of the windows was not installed because it was broken. Pine Tree Builders was paid for its work.

Loyd Reisig testified he and his wife contracted with Frye for the construction of their home. The contract called for a 10 percent downpayment with progress payments to be made as follows: 15 percent upon the completion of footing and foundation work; 20 percent upon completion of framing; 20 percent upon completion of drywall work; 15 percent upon completion of all interior and exterior carpenter work; and the balance upon taking possession. The total contract price was $41,000. Reisig made the downpayment and the first two progress payments for a total of $18,450. The last check to Frye was written on August 5, 1975. Reisig testified he considered this last check, in the amount of $8,200, as covering the next purchases to be made by Frye, including the sheetrock and the windows.

Frye stopped work on the project in early September 1975. Reisig testified he had no idea where Frye was purchasing materials during the period of con *26 struction from May to August. He further stated he was not present when any of the materials were delivered to the construction site except for one occasion when the trusses and asbestos shingles were unloaded. Later in his testimony he stated Frye told him before the windows were delivered that they had been ordered from Wickes and he showed him a copy of the invoice. The invoice indicated the transaction was to be C.O.D. Frye told him, “I have to pay for them before they’re unloaded.” Following delivery of the windows, Frye told Reisig they had been paid for and showed him a check stub. Reisig thought he was shown the check stub the day after delivery.

Reisig testified he became aware 2 or 3 weeks after construction started that Frye had not obtained a performance bond as required by the contract. He stated because of this knowledge, “I would check if a truck would come or a driver would come like a C.O.D. that Frye would show me from Wickes on the windows I checked that with him and that is what I used as a sure thing that Frye would have to pay for them was the C.O.D.’s.” He testified he would not have let the windows be unloaded had he known they were not paid for, or else he would have stopped construction until payment was made. He also would have inventoried the materials which were unloaded and those which were removed by Frye to another location.

Reisig testified he learned about the 20th of September that the windows and others items from Wickes had not been paid for, when he called Wickes or Wickes called him concerning the shake shingles which had been delivered, but which were supposed to have been delivered to another house Frye was building. Reisig at this time was told there was an outstanding bill in an amount over $2,000.

Reisig was asked to examine the copies of the invoices attached to the mechanic’s lien filed by *27 Wickes. He testified a patio door and casement windows had been installed in his residence. Two windows which had been delivered were not installed because one was broken and the other was not meant for his house. Sheetrock was also used in the construction of his house. After stating Frye had told him the windows were ordered from Wickes, Reisig was asked whether there were other materials which had come from Wickes. He replied, “I think there was. I think the trucks come from Wickes. I’m not sure.” Reisig testified that several times Frye removed materials which had originally been delivered to his property.

Jimmy Pask, the manager of Wickes Lumber Company in Fort Collins, testified he met Frye in July 1975, when he came in with Mike Webb for material to build a home in Nebraska. To the best of his knowledge, all the materials ordered by Frye were to be used in the construction of a house for a Lee Schwartzkopf. In early September 1975, he learned for the first time that some of the materials had gone to Reisig. This was when Reisig telephoned to complain that one of the windows which had been delivered was broken and another was the wrong size. He checked into the matter and returned Reisig’s call on September 15, 1975. During this conversation he informed Reisig that the sheet-rock, the windows, and the shake shingles delivered to him had not been paid for. Pask told Reisig he would order new windows when the correct sizes were determined.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Larson Concrete Co. v. Stroschein
353 N.W.2d 354 (South Dakota Supreme Court, 1984)
Dukane Corp. v. Sides Construction Co.
302 N.W.2d 721 (Nebraska Supreme Court, 1981)
Waite Lumber Co., Inc. v. Carpenter
290 N.W.2d 655 (Nebraska Supreme Court, 1980)
Ideal Basic Industries, Inc. v. Juniata Farmers Cooperative Ass'n
289 N.W.2d 192 (Nebraska Supreme Court, 1980)
Delp v. Laier
288 N.W.2d 265 (Nebraska Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
273 N.W.2d 663, 202 Neb. 23, 1979 Neb. LEXIS 975, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wickes-corp-v-frye-neb-1979.