Ideal Basic Industries, Inc. v. Juniata Farmers Cooperative Ass'n

289 N.W.2d 192, 205 Neb. 611, 1980 Neb. LEXIS 764
CourtNebraska Supreme Court
DecidedFebruary 26, 1980
Docket42607
StatusPublished
Cited by9 cases

This text of 289 N.W.2d 192 (Ideal Basic Industries, Inc. v. Juniata Farmers Cooperative Ass'n) is published on Counsel Stack Legal Research, covering Nebraska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Ideal Basic Industries, Inc. v. Juniata Farmers Cooperative Ass'n, 289 N.W.2d 192, 205 Neb. 611, 1980 Neb. LEXIS 764 (Neb. 1980).

Opinion

White, J.

This is an appeal by the plaintiff, Ideal Basic Industries, Inc. (hereafter Ideal), from an order dismissing an action to foreclose a mechanic’s lien. The parties were Mel Jarvis Construction Company, Inc. (hereafter Jarvis), Larry Lambrecht, doing business as Wood River Concrete Company (hereafter Lambrecht), and The American Insurance Company (hereafter American).

The essential facts are these. Juniata Farmers Cooperative Association entered into a contract with Farmland Industries, Inc. (hereafter Farmland), for the construction of a grain elevator at Hayland, Nebraska. Farmland, as general contractor, agreed to furnish all labor and material for the construction of a concrete grain elevator. Farmland entered into a subcontract with Jarvis. Jarvis agreed to furnish all the labor and materials for the excavation, the lower pits, tunnels, slabs, and to slip form the concrete grain elevator and annex. Jarvis solicited bids for concrete for the elevator project. Lambrecht submitted a bid and Jarvis accepted by issuing a standard purchase order notifying Lambrecht. Between April and July 1976 Lambrecht supplied mixed concrete to Jarvis. All the cement necessary for making the concrete was purchased from Ideal, plaintiff in this action, on an open account.

Initially, the concrete supplied to Jarvis was mixed and transported from Lambrecht’s batching plant in Wood River, Nebraska. Ideal delivered the raw cement to the plant at Wood River where Lambrecht would transport these raw materials in a *613 mixing truck to the Hayland site. Approximately a month after Lambrecht started delivery of concrete to Jarvis, Lambrecht constructed a batching plant at the jobsite in Hayland. Ideal then delivered the cement to the Hayland batching plant. The cement involved in this case was delivered to the Hayland plant. Ideal does not seek recovery for any cement delivered to the Wood River plant.

Evidence was adduced to show Lambrecht supplied Jarvis with concrete from April 4, 1976, to July 1976. After two payments, a dispute arose and Jarvis stopped paying Lambrecht. Ideal contends it delivered $32,130 worth of cement to Lambrecht at the Hayland site for which it has not been paid.

On September 29, 1976, Ideal filed a mechanic’s lien against Juniata Farmers Cooperative Association for $33,229.82, later amended to $32,130. In order to discharge the property from the lien, Jarvis, as principal, and American, as surety, filed a bond in the amount of $38,500 pursuant to section 52-121, R. R. S. 1943. Ideal filed a petition against Juniata Farmers Cooperative, Lambrecht, Jarvis, and American in an attempt to foreclose its lien. Juniata demurred to the plaintiff’s petition and the demurrer was sustained. Jarvis and American denied the allegations of plaintiff’s petition. Lambrecht cross-petitioned against Juniata, Jarvis, and American, claiming a lien upon the bond filed by Jarvis for the balance due from Jarvis for the sum of $41,316.17. Upon its own motion, the court consolidated the case of Ideal Basic Industries, Inc. v. Juniata Farmers Cooperative Association et al., with that of Larry Lambrecht, doing business as Wood River Concrete Company v. Mel Jarvis Construction Company, Inc., et al. By pretrial order and pursuant to the stipulation of the parties, the court ordered that the case of “Ideal Basic Industries, Inc. vs. Mel Jarvis Construction Company, Inc.” be tried first. It is that suit which is now be *614 fore the court.

Ideal assigns as error the court’s finding that Ideal was not entitled to the protection of the mechanic’s lien statutes; that the failure of Lambrecht to tag or designate his payments to plaintiff on open account barred plaintiff from enforcing its mechanic’s lien; and that the trial court erred in holding Ideal was required to prove the value of cement actually incorporated into the elevator and in failing to find that Ideal proved the value of the cement incorporated into the elevator building. We shall discuss only the first assignment of error.

The controlling question for decision is whether the supplier of a supplier of materials to be used for the construction of a grain elevator is entitled to a claim of a lien under section 52-101, R. R. S. 1943. This section defines who is entitled to a mechanic’s lien and for what a lien may be claimed. Durkee v. Koehler, 73 Neb. 833, 103 N. W. 767. We have said that one claiming a lien must clearly bring himself within the terms of the statute allowing a lien on real estate. Krotter & Sailors v. Pease, 161 Neb. 774, 74 N. W. 2d 538. The section reads in relevant part: “Any person who shall perform any labor or furnish any material, machinery, or fixtures, including gas and electric apparatus and lighting fixtures, whether detachable or undetachable, (1) for the construction, erection, improvement, repair, or removal of any house, mill, well, cistern, manufactory, building, or appurtenance * * * by virtue of an open running account or a contract or agreement, expressed or implied, with the owner thereof or his agents, shall have a lien to secure the payment of the same upon such * * * and the lot of land upon which the same shall stand or the work is performed, and such lien shall include the rental value of any equipment furnished.”

In 53 Am. Jur. 2d, Mechanics’ Liens, § 73, p. 585, it is stated: “Persons supplying materials to a ma *615 terialman or a subcontractor must come clearly within the terms of the statute, or they can claim no lien. They are so far removed from the owner that the privilege of a lien is not often extended to them, and the plainest expressions of law must be used to entitle them to this remedy.”

It is our view that section 52-101 et seq., R. R. S. 1943, provide a lien only to materialmen who supply directly to the owner of the realty, the contractor, or a subcontractor. Ideal sold its material directly to Lambrecht, looked to him for payment, and was directed by him as to the quantity of materials to be delivered and where and when such deliveries were to be made. Earl Barngrover, the Ideal sales representative, testified: “Q. Did you call on Mr. Lambrecht as a customer of Ideal? A. Yes, I did. Q. Did you make arrangements with Mr. Lambrecht for the sale of cement for the Hayland elevator job? A. Yes.” The cement which was supplied by Ideal was done at the request of Lambrecht. Lambrecht was not the agent of the owner, or the contractor, or a subcontractor. Ideal argues that Lambrecht was a subcontractor because he was obliged, by contract, to mix all the cement required for the elevator and he performed that mixing on the jobsite. Although our statutes contain no precise definition of “subcontractor” or “materialman,” these terms have been defined as follows: “* * * the essential feature which constitutes one a subcontractor rather than a materialman is that in the course of performance of the prime contract he constructs a definite, substantial part of the work of improvement in accord with the plans and specifications of such contract, not that he enters upon the jobsite and does the construction there.” (Emphasis supplied.) 53 Am. Jur. 2d, Mechanics’ Liens, § 72, p. 583.

It was stated in 57 C. J. S., Mechanics’ Liens, § 89, p. 599, that a materialman is: “* * * a person who does not follow the business of building or contract *616

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Pack 2000, Inc. v. Cushman
Supreme Court of Connecticut, 2014
Preussag International Steel Corp. v. March-Westin Co.
655 S.E.2d 494 (West Virginia Supreme Court, 2007)
Blue Tee Corp. v. CDI Contractors, Inc.
529 N.W.2d 16 (Nebraska Supreme Court, 1995)
Unadilla Silo Co. v. Hess Bros.
586 A.2d 226 (Supreme Court of New Jersey, 1991)
Atlantic Sea-Con, Ltd. v. Robert Dann Co.
582 A.2d 981 (Court of Appeals of Maryland, 1990)
Miller v. State
779 P.2d 87 (Nevada Supreme Court, 1989)
Hulinsky v. Parriott
441 N.W.2d 883 (Nebraska Supreme Court, 1989)
Columbus Federal Savings & Loan Ass'n v. Swails Construction Co.
338 N.W.2d 593 (Nebraska Supreme Court, 1983)
CHICAGO LUMBER CO. OF OMAHA v. Horner
317 N.W.2d 87 (Nebraska Supreme Court, 1982)

Cite This Page — Counsel Stack

Bluebook (online)
289 N.W.2d 192, 205 Neb. 611, 1980 Neb. LEXIS 764, Counsel Stack Legal Research, https://law.counselstack.com/opinion/ideal-basic-industries-inc-v-juniata-farmers-cooperative-assn-neb-1980.