White v. United States

48 Ct. Cl. 169, 1913 U.S. Ct. Cl. LEXIS 140, 1912 WL 1183
CourtUnited States Court of Claims
DecidedFebruary 10, 1913
DocketNo. 29618
StatusPublished

This text of 48 Ct. Cl. 169 (White v. United States) is published on Counsel Stack Legal Research, covering United States Court of Claims primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. United States, 48 Ct. Cl. 169, 1913 U.S. Ct. Cl. LEXIS 140, 1912 WL 1183 (cc 1913).

Opinion

BarNet, J.,

delivered the opinion of the court:

This suit arises out of a contract for the performance of certain work in connection with construction of a filtration plant situated in the District of Columbia. The contract was made between the Government and the firm of Cowardin, Bradley, Clay & Co., but shortly after the beginning of the work John D. McClennan was appointed receiver of said firm of contractors, and, as such receiver, completed it. This suit was begun by McClennan, who is now deceased. After his decease the present claimant was appointed receiver in his stead for the purpose of completing its prosecution. For the purpose of avoiding confusion, both the original contracting firm and Mr. McClennan will be referred to as “the contractors.”

The claim in this case is but for one item only, and that is pay for earth deposited upon a certain roadway, it being contended by the plaintiff .that the contractors should be paid for earth thus deposited as “ other fills and embankments shown by the plans or directed to be made by the engineer officer in charge,” mentioned in the contract, and for which pay at a certain rate per cubic yard is provided in the contract. On the other hand, it is contended by the defendants that under the terms of the contract the earth thus deposited is not the “ fills and embankments ” therein provided for, but is mere “ waste ” arising from the excavation work, for payment of which the contract contains no provision.

The first paragraph of the contract provides in general terms for the work to be done under it and the prices therefor to be paid, and makes the following provisions as to payment for fills and embankments, viz: “ for sixty-five thousand four hundred (65,400) cubic yards embankment under filters, for forty-six thousand seven hundred (46,700) cubic yards other embankment, and for one hundred and twenty-three thousand four hundred (123,400) cubic yards filling over filters; ” and this is the only mention or provision in the contract (aside from the specification thereto attached) as to fills and embankments. It will thus be seen that the contract standing alone provides for two kinds of embankment and one kind of filling. The provision for filling is specific in [176]*176character, and under the well-recognized rule unius expressio est alterius exclussio excludes every other kind of filling unless otherwise clearly shown by the specifications. We say clearly shown because of the well-known rule that when there is a conflict between the contract and the specifications the contract must govern. If, however, the deduction from the contract is only by inference and the specifications upon that point are clear and beyond question, a different rule might prevail. Particular attention is called to this feature of the contract for the reason that the plaintiff seeks to recover in this suit for the earth deposited upon the roadway in question as a “ fill,” and it doubtless comes within the definition of that term, though, as we understand, it is contended that, taking the contract and specifications together, it comes within both terms.

One of the kinds of embankment provided for is also specific in character, and under the rule above mentioned this also excludes all other kinds of embankment unless unmistakably provided for in the specifications; but as the plaintiff makes no claim under this item, it need not be further considered. The other item of “ other embankment ” will be considered further on in this opinion.

The plaintiff’s claim, however, rests upon certain provisions of the specifications, and more particularly upon paragraphs 57 and 58, which are as follows:

“ 57. Worh. — The work under this heading includes the filling of low places under filters and other structures, the filling of central courts, the embankments about the filters, and all other fills and embankments shown by the plans or directed to be made by the engineer officer in charge.
“ 58. Classification. — Embankments shall be divided into three classes:
“ 1. Embankment under filters.
“ 2. Embankments about the walls of filters and in courts.
“ 3. Filling over filters.
“ Material placed below the dam, in the roadway and at other low places for the purpose of disposing of it, and material disposed of off the ground shall not be paid for as embankment. When waste embankments come against the walls of the filters or the pure-water reservoir the usual section shall be built and paid for as embankment, and all material outside shall be treated as waste.”

[177]*177It is contended by the plaintiff that the phrase “ and all other fills and embankments shown by the plans ” in the above paragraph applies to the filling up of the roadway in question, because the same was shown upon the plans submitted with the proposals. An examination of the plans submitted with the proposals for the work shows that the roadway was indicated thereon, but contained no detail whatsoever as to exact location or dimensions. They merely mark where a roadway is to be placed. The findings show that when the contractors first began to deposit material upon the roadway the engineer officer in charge gave them the toe lines and slope of the same, and some months after the work was begun and after the contractor had placed considerable material upon this roadway the engineer officer in charge of the work furnished the contractor with a plan showing in detail the location and dimensions of this roadway, and thereafter the contractors deposited earth thereon under the inspection of this engineer officer as to the character of the earth thus placed, its dimensions, etc. This was continued and payments for the same made in the first voucher as “ other fills and embankment,” and thereafter without any separate designation, to the extent of $12,000, when its was concluded by the engineer officer in charge of the work that this filling of the roadway was not to be paid for under the contract, and payment for the same was then stopped and the $12,000 already paid deducted for subsequent sums earned under the contract. It should also here be stated that the findings do not show that the engineer officer in charge of the work ever directed in terms any deposit of waste material to be made upon the roadway.

It will be seen that paragraph 58 above quoted specifically provides for three classes of embankments: (1) Embankment under filters; (2) embankments about the walls of filters and in courts; (3) filling over filters; thus putting “fills” and “ embankments ” in the same class. No mention is made here of any filling to be placed upon roadways. This is a very significant fact militating against the contention of the plaintiff, because he now claims that the filling required for the roadway was nearly as much in amount as that estimated in [178]*178the contract for “ filling over filters,” which was specifically mentioned above.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

District of Columbia v. Gallaher
124 U.S. 505 (Supreme Court, 1888)

Cite This Page — Counsel Stack

Bluebook (online)
48 Ct. Cl. 169, 1913 U.S. Ct. Cl. LEXIS 140, 1912 WL 1183, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-united-states-cc-1913.