White v. Rimmer & Garrett, Inc.

360 So. 2d 914
CourtLouisiana Court of Appeal
DecidedJune 28, 1978
Docket6568
StatusPublished
Cited by6 cases

This text of 360 So. 2d 914 (White v. Rimmer & Garrett, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Rimmer & Garrett, Inc., 360 So. 2d 914 (La. Ct. App. 1978).

Opinion

360 So.2d 914 (1978)

John H. WHITE, d/b/a White Construction and Equipment Rental Company, Plaintiff-Appellant,
v.
RIMMER & GARRETT, INC., Defendant-Appellee.

No. 6568.

Court of Appeal of Louisiana, Third Circuit.

June 28, 1978.

*915 Camp, Carmouche, Palmer, Carwile & Barsh, Karl E. Boellert, Lake Charles, for plaintiff-appellant.

Aaron, Aaron & Chambers, Noble M. Chambers, Jr., Crowley, for defendant-appellee.

Before DOMENGEAUX, WATSON and GUIDRY, JJ.

GUIDRY, Judge.

This case is before us on appeal after remand by the Louisiana Supreme Court for the introduction of evidence relative to the assessment of damages due plaintiff as a result of defendant's breach of a construction subcontract. This appeal is limited solely to the issue of quantum.

The facts giving rise to this suit as well as the history of previous litigation may be summarized as follows:

On October 9, 1971, John H. White d/b/a White Construction & Equipment Rental Company (White), as subcontractor, and Rimmer & Garrett, Inc. (R & G), as contractor, entered into a written subcontract agreement whereby White undertook to perform certain excavation and dirt hauling work in accordance with a primary contract previously entered into between R & G and the Louisiana Department of Highways for the construction of a portion of the I-210 bypass in Lake Charles, Louisiana. The portion of the primary contract that was to be performed by White was designated as Item 203(5) and was further described as "Cubic Yards Special Borrow Excavation'". The approximate quantity of material required was listed as 1,738,540 cubic yards. Article 2 of the subcontract provided that White was to furnish all labor, materials and equipment and to perform all work for Item 203(5). White's principal duties involved the excavation of dirt from a "borrow pit" and the transportation of this material to the highway construction site. The unit price for the work was set forth on a declining scale according to the quantity of special borrow excavation.

On October 14, 1971, the parties signed a supplemental agreement which further delineated White's obligations under the terms of the contract. Among other things, this agreement specifically excluded any special borrow located north of Interstate 10 from the terms of the contract, and provided that White's responsibilities under Item 203(5) would include loading, hauling and spot dumping on the project. The agreement further contained a provision which stated "The minimum special borrow quantity will be 1,000,000 Cubic Yards".

A dispute concerning the configuration of the borrow pits resulted in a second supplemental and amending agreement between the parties dated April 10, 1972. This second agreement consisted of fourteen numbered paragraphs and provided, inter alia, that the shape of the pit was to be as shown on a plat of the Waterloop Subdivision dated January 21, 1972. R & G agreed to pay White at a flat rate of $.915 per yard for all material heretofore and subsequently removed. A handwritten provision which stated "one million cu. yd. Guaranteed" was added and initialed by the parties.

Work on the project was resumed. However, difficulties which arose between the parties eventually culminated in the filing, on March 19, 1973, of a suit by White against R & G seeking specific performance, accounting and/or damages. R & G reconvened seeking damages allegedly incurred as a result of the failure of White to abide by the terms of the contract. At the time that White ceased work, it appeared that White had only hauled 985,650 cubic yards of dirt.[1]

White was claiming that he was entitled under the terms of the contract to excavate and haul all of the dirt required for the completion of Item 203(5) with the exception of the area located north of Interstate 10 and a "scraper" item which, pursuant to an oral agreement, was to be excavated by R & G. On the other hand, R & G took the position that White was only entitled to *916 excavate and haul 1,000,000 cubic yards of material.

The trial court determined that White was entitled to excavate and haul only 1,000,000 cubic yards. Based upon a finding that White had received payment for 985,650 cubic yards of material, the trial court awarded White the contract price of $.915 for the difference, i. e., 14,350 cubic yards, which amounts to the sum of $13,130.25. R & G's reconventional demand was denied.

On appeal, this court held that the subcontract as amended by the two supplements was ambiguous, and that parol evidence was admissible to ascertain the true intent of the parties. White v. Rimmer & Garrett, Inc., 328 So.2d 686 (La.App. 3rd Cir. 1976). After considering the evidence in the record, we affirmed the trial court's determination that White was entitled to haul only 1,000,000 cubic yards of dirt. The trial court's damage award was however amended and reduced by awarding White his average profit over the contract period (13.95¢ per cubic yard) for each additional yard that White was entitled to haul (14,350 cubic yards) which equals the sum of $2,001.83.

Writs were granted by our Supreme Court. After concluding that the contract as amended was not ambiguous and thus parol evidence was not admissible to vary the terms of the contract, the Supreme Court held that White enjoyed the exclusive right, with some exceptions, to excavate and haul all of the dirt required for Item 203(5) and that White was entitled to damages for R & G's usurpation of this right. White v. Rimmer & Garrett, Inc., 340 So.2d 283 (La.1976). These damages were to be assessed according to the amount of loss sustained and the profit of which White had been deprived. Lost profit was to be determined by deducting the cost of labor and materials from the total contract price. The Supreme Court noted that the Court of Appeal was in error in assessing White's lost profit on the proportionate basis of his net income experience on the job, as this figure would also include expenses which were fixed and not variable with the amount of dirt actually hauled. The case was remanded for the purpose of the introduction of evidence relative to the computation of White's lost profits and also for the determination of the amount of cubic yards on which to assess damages.

The Supreme Court set forth the proper formula for the determination of this latter item as follows:

". . . the amount of dirt actually used for Item 203(5) less (1) the dirt White actually hauled and was paid for (985,650); (2) the 86,000 cubic yards of fill hauled by R & G north of I-10 and (3) the amount R & G was responsible for as the `scraper'2 item."

On remand, the court was directed to ascertain the total amount of dirt actually used for Item 203(5) and the amount of the "scraper" item.

On rehearing, the Supreme Court, in a brief per curiam opinion, recognizing that final figures for the yardage actually used in Project Item 203(5) varied substantially from the yardage estimates the parties had initially agreed to use, amended its decree as follows:

"In our original opinion we stated that the case is remanded to ascertain the total amount of dirt used on Item 203(5) and the amount of the `scraper' item. In order to avoid any injustice to either party, on remand the court will not be bound by any figures mentioned in the opinion.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Raphael v. Raphael
929 So. 2d 825 (Louisiana Court of Appeal, 2006)
Adonis Raphael v. Geraldine Elizabeth Rapheal
Louisiana Court of Appeal, 2006
PELTS & SKINS EXPORT v. State
735 So. 2d 116 (Louisiana Court of Appeal, 1999)
Rosbottom v. Office Lounge, Inc.
654 So. 2d 377 (Louisiana Court of Appeal, 1995)
Mini Togs Products, Inc. v. Wallace
513 So. 2d 867 (Louisiana Court of Appeal, 1987)
New Orleans v. United Gas Pipe Line Co.
517 So. 2d 145 (Louisiana Court of Appeal, 1987)
Meeks v. Huntington School, Inc.
489 So. 2d 435 (Louisiana Court of Appeal, 1986)

Cite This Page — Counsel Stack

Bluebook (online)
360 So. 2d 914, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-rimmer-garrett-inc-lactapp-1978.