White v. Rimmer & Garrett, Inc.

328 So. 2d 686
CourtLouisiana Court of Appeal
DecidedJune 2, 1976
Docket5294
StatusPublished
Cited by3 cases

This text of 328 So. 2d 686 (White v. Rimmer & Garrett, Inc.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Rimmer & Garrett, Inc., 328 So. 2d 686 (La. Ct. App. 1976).

Opinion

328 So.2d 686 (1976)

John H. WHITE, d/b/a White Construction and Equipment Rental Company, Plaintiff and Appellee,
v.
RIMMER & GARRETT, INC., Defendant and Appellant.

No. 5294.

Court of Appeal of Louisiana, Third Circuit.

March 10, 1976.
Rehearing Denied April 7, 1976.
Writ Granted June 2, 1976.

*687 Aaron, Aaron & Chambers by Noble M. Chambers, Jr., Crowley, for defendant-appellant.

Camp, Carmouche, Palmer, Carwile & Barsh by Karl E. Boellert, Lake Charles, for plaintiff-appellee.

Before HOOD, CULPEPPER, DOMENGEAUX, GUIDRY and PAVY, JJ.

DOMENGEAUX, Judge.

This is a suit for breach of a construction subcontract. Plaintiff-appellee, the subcontractor will be hereinafter referred to as White, and defendant-appellant contractor will be hereinafter referred to as R & G, Inc.

The subcontract provided for certain excavation work to be performed by White in conformance with a primary contract between R & G, Inc. and the Louisiana Department of Highways. The District Judge concluded that White was entitled to excavate, haul, and deposit 1,000,000 cubic yards of fill and no more. In that White had only excavated and moved 985,650 cubic yards by the time difficulties apexed between the parties, the District Judge awarded White the sum of $13,130.25, based on the difference at $0.915 per cubic yard. R & G, Inc.'s reconventional demand was denied. R & G, Inc. has appealed and White has answered the appeal seeking an increase in the award.

The issues are:

1. Was the subcontract with its two supplements, ambiguous? *688 2. What portion of Item 203(5) in the primary Louisiana Department of Highways contract was White entitled to haul under its subcontract with R & G, Inc.?

3. Did R & G, Inc. interfere with the performance by White of its obligations, duties and responsibilities under its subcontract with R & G, Inc.?
4. Did White breach its subcontract with R & G, Inc. by improperly excavating the slopes of the borrow pits such that accurate measurement of the dirt removed therefrom could not be accomplished?
5. What is the proper measure of damages for the amount White was entitled to haul but was allegedly prevented from hauling?

The suit arises out of a written contract entered into between R & G, Inc. as contractor and White as subcontractor. Prior to entering into that agreement, R & G, Inc. was the successful bidder and entered into a public contract with the Louisiana Department of Highways for the construction of a portion of the 1-210 bypass in Lake Charles, Louisiana. The portion of the primary contract with the Louisiana Department of Highways which is of concern in this suit is that designated as Item 203(5). The description contained in the contract of Item 203(5) was "Cubic Yards—Special Borrow Excavation". The "approximate quantity" was listed as 1,738,540 cubic yards.

Mr. Bob Young, Branch Manager and Salesman for Furlow-Laughlin Company, a heavy equipment dealer, contacted Mr. Tom Garrett, President of R & G, Inc., inquiring whether Mr. Garrett was interested in negotiating with earth moving contractors to move the dirt referred to in the Department of Highways contract. Mr. Garrett indicated that he was interested, and as a consequence Mr. Young introduced the plaintiff John H. White to Mr. Garrett. Young knew White and had previous business dealings with him, having sold equipment to him on prior occasions. Garrett and White began negotiations culminating in the subcontract wherein White was to perform Item 203(5) of the primary agreement with the Louisiana Department of Highways.

Apparently Mr. Young's motivation in securing a contractual agreement between Mr. Garrett and Mr. White was that in the event Mr. White did undertake the contract he would purchase a Cohen 1066 Backhoe from Furlow-Laughlin through Mr. Young. Upon confection of the agreement, Mr. White did in fact purchase the backhoe from Mr. Young and also purchased dump trucks for the job. The total of all of these purchases was some $456,000.

The subcontract dated October 9, 1971, was on a standard AGC Form which Mr. Garrett supplied. That agreement provided:

"The subcontractor shall furnish all labor, materials and equipment and shall perform all the work for [Item No.203(5)]."

The unit price for this work then was provided on a declining sliding scale according to quantity of special borrow excavation. The agreement provided that the subcontract was to be completed within 400 days from its date. The parties also agreed that R & G, Inc. was to spread, compact and shape the dirt. This, however, was only an oral agreement and was not contained within the written document. Within five days of the signing of the contract, however, a supplemental agreement was added to it. That agreement was for the purpose of specifying and clarifying the duties and obligations of the subcontractor, White, under its agreement with R & G, Inc. Particularly, that agreement provided that Mr. White's obligations were only to load, haul and spot dump on the project although it contained other minor provisions. Additionally, the supplement stated "The *689 minimum special borrow quantity will be 1,000,000 cubic yards." It also provided that any special borrow located north of Interstate 10 was not to be included within the terms of the agreement.

The contractor, R & G, Inc., purchased the land on which the excavation was to be performed, and work began in the fall of 1971. The job progressed until early spring of 1972 when disagreement arose over the area which was to be excavated. It seems that at this time R & G, Inc. had decided to alter the original shape of the excavation (borrow) pits for aesthetic reasons. It planned to convert the pits to lakes and develop a subdivision in the area around them. Mr. White objected to this and refused to go outside the original configuration of the pit, saying that he needed some sort of letter or other authorization before changing the original agreement. Mr. White then drew up a list of thirteen demands and presented them to R & G, Inc. As a result of this dispute, a second amending supplement dated April 10, 1972, was added to the contract. That document was prepared, considering the list of thirteen demands presented by Mr. White. The parties agreed that all excavation would be in conformance with a new plat; in fact Supplement Two stated "The excavation area or pit is as shown on the plat of Waterloop Subdivision prepared by Shutts & Son, dated January 21, 1972." Additionally, it was agreed that White Construction Company would be paid a flat rate of "0.915 dollars per cubic yard for all material removed or to be removed, including material removed to date hereof." (This is a significant increase in the graduated scale in the original subcontract, as is shown hereafter.) The agreement, among other things, also provided that R & G, Inc. would provide a "bleeder" ditch and adequate drainage around the excavated area. A handwritten provision was then added by the parties and initialed by them providing "1,000,000 cu. yd. guaranteed". Mr. Young was present at the signing and initialing of the second supplement, and in fact it was he who added the provision for the "1,000,000 cu. yd. guaranteed".

Work once again commenced in conformance with the new agreement as set forth in the second supplement.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Central Progressive Bank v. Bradley
496 So. 2d 525 (Louisiana Court of Appeal, 1986)
White v. Rimmer & Garrett, Inc.
360 So. 2d 914 (Louisiana Court of Appeal, 1978)
White v. Rimmer & Garrett, Inc.
333 So. 2d 235 (Supreme Court of Louisiana, 1976)

Cite This Page — Counsel Stack

Bluebook (online)
328 So. 2d 686, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-rimmer-garrett-inc-lactapp-1976.