White v. Pruiett

39 S.W.3d 857, 2001 Mo. App. LEXIS 484, 2001 WL 265153
CourtMissouri Court of Appeals
DecidedMarch 20, 2001
DocketWD 58509
StatusPublished
Cited by17 cases

This text of 39 S.W.3d 857 (White v. Pruiett) is published on Counsel Stack Legal Research, covering Missouri Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Pruiett, 39 S.W.3d 857, 2001 Mo. App. LEXIS 484, 2001 WL 265153 (Mo. Ct. App. 2001).

Opinion

HOWARD, Judge.

Appellant Doug White, doing business as White’s Construction (hereinafter referred to as “contractor”), sued Respondent Wanda Pruiett (hereinafter “owner”) for breach of contract and unjust enrichment. The trial court entered a directed verdict against contractor on both claims and denied his motion for new trial. He now appeals from the judgment.

We affirm.

Standard of Review

In directing the verdict against contractor on both of his claims, the trial court determined that contractor failed to present the legal and substantial evidence supporting every fact needed to impose liability that was necessary to warrant submitting his claims of owner’s liability to the jury. Seippel-Cress v. Lackamp, 23 S.W.3d 660, 666 (Mo.App. W.D.2000). In other words, the court found that contractor failed to produce substantial evidence which, together with reasonable inferences therefrom, if true, had probative force upon the breach of contract and unjust enrichment issues from which the jury could reasonably decide the case. Id. Whether the evidence was indeed substantial to permit submitting the case to the jury is a question of law. Id.

A directed verdict is a drastic measure. Seippel-Cress, 23 S.W.3d at 666. We review the evidence and permissible inferences therefrom in a light most favorable to contractor and disregard contrary evidence and inferences. Id. Although we will affirm if we find reasonable grounds supporting the directed verdict, a presumption in favor of reversing the trial court’s directed verdict exists. Id. Thus, unless we find the evidence adduced at trial and inferences fairly and reasonably deductible therefrom to be “‘so strongly against plaintiff[ ] as to leave no room for reasonable minds to differ,”’ we will reverse. Id. (quoting Bridgeforth v. Proffitt, 490 S.W.2d 416, 423 (Mo.App.1973)).

Facts

Using this standard, the record reveals the following facts:

In September, 1998, owner’s home suffered water damage from a broken water line. State Farm Insurance, with whom owner had contracted for homeowner’s insurance, initially offered owner $15,218.57 to settle the claim against her policy for the damage. Pursuant to her policy, owner sought independent bids from several remodeling contractors to determine whether State Farm’s offer was sufficient. Contractor received a call from owner requesting that he meet with her concerning the damage to her home.

Over the next five- or six-week period of time, contractor, at owner’s request, met with owner at her home several times in order to discuss and evaluate the extent of the water damage to her home and the cost of repair of the same. Contractor also consulted owner over the telephone on several occasions concerning the damage. The work that he recommended included several items, including but not limited to replacement of subfloors, drywall, insulation and tile, which work had not been included in State Farm’s initial offer to settle owner’s claim.

After State Farm’s adjuster obtained the first bid on owner’s home and owner *861 complained, State Farm prepared another offer to settle owner’s claim for the sum of $28,059. This offer still did not include all of the items that owner wished to have repaired. Owner therefore invited contractor to attend three separate meetings between owner and State Farm representatives. Contractor’s business associate Stan Deal also attended two of the meetings to assist contractor with evaluating the damage to owner’s home. During these meetings with State Farm, contractor explained and pointed out the additional damage not included in State Farm’s estimate, upon which it had based its offer to settle with owner. At these meetings, owner told State Farm representatives, in the presence of contractor and twice in the presence of his business associate Mr. Deal, that she had chosen contractor to repair the water damage to her home.

At the third meeting with State Farm’s representatives, in October, 1998, owner and contractor met with Charles Feather-stone, a State Farm adjuster who had more experience in handling large claims for water damage than the previous adjuster assigned to owner’s claim. The purpose of the meeting was for a “re-inspection.” There were four State Farm representatives present at this meeting, during which contractor again explained why, in his professional judgment and using his experience and expertise, the additional repairs requested by owner were justified and necessary. His explanation included a physical inspection of the damage by tearing out drywall, insulation and other parts of the home that had become black due to the mildew and damaged due to the water. Again, owner stated to the State Farm representatives that she was going to have contractor do the work. Contractor presented two bids for the work to State Farm. His final estimate was for $56,570. At least three other contractors also submitted bids for the work to State Farm in amounts ranging from $18,698 to $43,421. State-Farm ultimately agreed to pay owner $58,517.25 to settle the claim. Mr. Featherstone testified that he did not rely upon the bids in reaching this final offer of settlement made to owner.

At the time owner first called contractor, contractor had been working full time for approximately eight months as a lead subcontractor for MidWestern Builders, one of Kansas City’s largest residential remodeling contractors. He quit this job during the time that he was meeting with owner concerning the damage to her home. When he learned that he would not be the contractor to perform the work on owner’s home, he was unable to go back to his job at MidWestern, but he did perform subcontracting work for other builders.

When contractor learned that owner and her family intended to repair their home on their own, he filed his claim against owner on two counts — Count I for breach of contract and Count II for unjust enrichment. The case was tried to a jury on December 6 and 7, 1999. At the close of contractor’s evidence, owner moved for a directed verdict on both counts. The trial court granted both motions, directing the verdict in favor of owner. This appeal followed.

The issue on appeal is whether contractor made a submissible case on Counts I and II such that the motions for directed verdict should not have been granted.

Point I: Breach of Contract

In Count I of his first amended petition, contractor alleges that he and owner had an agreement that he would perform the repair work on owner’s home. He contends that an oral contract was established by his bid and owner’s representation- that he would be the contractor performing the work. The trial court directed the verdict on this count, finding that “the first count is not definite enough to form a contract.”

In order to make a submissible case of breach of contract, contractor was required to establish: (1) the existence of a *862 valid contract; (2) the rights and obligations of the respective parties; (3) a breach; and (4) damages. Howe v. ALD Services, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Williams v. Biden
E.D. Missouri, 2024
NTD I, LLC v. Alliant Asset Mgmt. Co.
362 F. Supp. 3d 664 (E.D. Missouri, 2019)
Angelina Jackson v. Higher Education Loan Authority of Missouri
497 S.W.3d 283 (Missouri Court of Appeals, 2016)
Blair v. City of Hannibal
179 F. Supp. 3d 901 (E.D. Missouri, 2016)
Mary Lowe v. Susan Hill
430 S.W.3d 346 (Missouri Court of Appeals, 2014)
Howard v. Turnbull
316 S.W.3d 431 (Missouri Court of Appeals, 2010)
Pitman v. City of Columbia
309 S.W.3d 395 (Missouri Court of Appeals, 2010)
Heritage Roofing, LLC v. Fischer
164 S.W.3d 128 (Missouri Court of Appeals, 2005)
Rhodes Engineering Co. v. Public Water Supply District No. 1
128 S.W.3d 550 (Missouri Court of Appeals, 2004)
Warren Davis Properties V, L.L.C v. United Fire & Casualty Co.
111 S.W.3d 515 (Missouri Court of Appeals, 2003)
Arndt v. Beardsley
102 S.W.3d 572 (Missouri Court of Appeals, 2003)
AMERICAN STANDARD INS. CO. OF WI v. Bracht
103 S.W.3d 281 (Missouri Court of Appeals, 2003)
American Standard Insurance Co. of Wisconsin v. Bracht
103 S.W.3d 281 (Missouri Court of Appeals, 2003)

Cite This Page — Counsel Stack

Bluebook (online)
39 S.W.3d 857, 2001 Mo. App. LEXIS 484, 2001 WL 265153, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-pruiett-moctapp-2001.