White v. Longley

2010 MT 254
CourtMontana Supreme Court
DecidedDecember 7, 2010
Docket10-0133
StatusPublished

This text of 2010 MT 254 (White v. Longley) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. Longley, 2010 MT 254 (Mo. 2010).

Opinion

December 7 2010

DA 10-0133

IN THE SUPREME COURT OF THE STATE OF MONTANA 2010 MT 254

STEVE WHITE and DONNA WHITE, husband and wife,

Plaintiffs and Appellees,

v.

TOM LONGLEY, individually and CASTLE HOMES, LLC,

Defendants and Appellants.

APPEAL FROM: District Court of the Nineteenth Judicial District, In and For the County of Lincoln, Cause No. DV 07-265 Honorable Michael C. Prezeau, Presiding Judge

COUNSEL OF RECORD:

For Appellants:

Douglas Scotti; Morrison & Frampton, PLLP, Whitefish, Montana

For Appellees:

Amy N. Guth; Attorney at law Libby, Montana

Submitted on Briefs: September 15, 2010

Decided: December 7, 2010

Filed:

__________________________________________ Clerk Chief Justice Mike McGrath delivered the Opinion of the Court.

¶1 Tom Longley and Castle Homes, LLC, appeal from the decision of the District

Court of the Nineteenth Judicial District awarding damages to Steve and Donna White.

Longley and Castle Homes present a number of issues for review which will be noted

below. We affirm.

BACKGROUND

¶2 In 2006 Steve and Donna White bought 28 acres near Troy, Montana as the site of

their retirement home. Upon the recommendation of a family member they contacted

Tom Longley in Washington state about building their home. They met with Longley

and showed him drawings and pictures of the type of house they wanted. They toured

Longley’s personal house that he had built, and observed the house next door that he also

built. Longley gave them a business card identifying himself as the general manager of

Castle Homes, LLC, and representing that he was a professional engineer with a

doctorate degree. The promotional materials for Castle Homes, LLC contained

endorsements by satisfied customers and a biographical sketch that indicated that

Longley had earned a Ph. D. in civil engineering from the University of Idaho. Neither

Longley nor the materials disclosed that his degree was in agricultural engineering.

¶3 The Whites asked about hiring an architect but Longley told them he could design

the house based upon the ideas and images they had provided. After Donna confirmed

that Longley’s contractor license in Washington was current and that the Better Business

Bureau had no complaints against him or Castle Homes, the Whites believed that they

2 had found the right contractor to build their home. In January, 2007 the Whites entered a

written contract with Longley and Castle Homes. The contract provided that Castle

Homes would do the foundation and framing and would contract out the rest of the work.

The Whites agreed to pay costs plus 30% and tendered a down payment of $2,000.

¶4 A month later Longley sent a set of drawings depicting the floor plan and exterior

views. The District Court found that the drawings contained a “remarkable lack of detail

regarding framing.”

¶5 Steve White retired from his job in California and moved to Montana to camp on

the property and help work on the house. Jason Ellis, an employee of Longley’s in

Washington, volunteered to come to Montana to work on the White house project. Ellis

also camped on the property and Steve White became his primary helper, even though

Steve had no experience in home building. Longley flew Ellis to Montana and back to

Washington weekly in Longley’s personal airplane.

¶6 Longley’s initial crew of workers did some foundation work and departed, leaving

Ellis to finish the foundation and pour the concrete walls. The project suffered

throughout from a lack of skilled workers. While Ellis had years of experience as a

carpenter, he was “over his head” trying to build the large and complicated house for the

Whites. For example, Longley called for insulated forms to be used to pour concrete

walls. Ellis had never worked with these forms, so Longley left an instructional DVD for

him along with the materials. While Longley berated Ellis during the weekly flights back

to Washington that the work was not progressing fast enough, Ellis would complain that

the crew was inadequate and that many mistakes were being made.

3 ¶7 One of the largest problems was that the house had not been adequately designed

and that the roof would have to be fitted to the structure once the framing was done.

Both Ellis and Steve White saw that there were substantial structural problems, not the

least of which was that there would be inadequate support for the heavy roof beams.

¶8 Meanwhile, Donna White, who was then working outside of the United States,

became concerned with Longley’s billings. These were coming in increments of $25,000

with little detail. In June, 2007, she returned to Montana and met with Longley and Steve

at the property. At that time, in what the District Court described as a “remarkably

audacious move,” Longley proposed to the Whites that their best course of action was to

pay him $30,000 to “buy out” the written contract with Castle Homes. Longley’s plan

was to continue with the project, complete the framing and installation of the windows

and winterize the structure. The Whites would then hire the subcontractors to complete

the work.

¶9 The Whites paid Longley the $30,000 to “buy out” the contract, and agreed to

keep Longley on the project until the framing was finished, the windows were in and the

house was secured from the weather for the winter. The District Court found that nothing

changed and that the “job continued to be understaffed and the work continued to be

woefully substandard.” The Whites continued to pay Longley in $25,000 increments in

July and August, 2007, when it came time to install the roof.

¶10 Longley never consulted a structural engineer about the structural requirements

and installation of the roof, which was complicated by multiple dormers and intersecting

angles. Instead he went to Larson Lumber in Troy to order beams and rafters for the

4 project. Larson employees told Longley that the roof system needed to be sufficient to

handle a snow load of 80 pounds per square foot, and that specification was sent on to

Boise Cascade, which was to manufacture the beams and rafters. Against Larson’s

advice, Longley ordered a roof package rated at 40 pounds per square foot, along with

custom-made support hangers that would allow the rafters to be attached despite the

framing mistakes. When Bonnie Larson at Larson Lumber objected, Longley told her

that he was an engineer and that she should butt out.

¶11 Longley later blamed Larson and Boise Cascade for the inadequacies in the roof,

and for selling him a miscalculated and undersized system. The District Court found

“Larson to be believable on this issue and Longley to be unbelievable.” The District

Court found that while it was “inconceivable” that both Larson and Boise Cascade would

make such fundamental mistakes with the roof, even if mistakes had been made it was

Longley’s duty as the contractor to “catch the error and send the undersized roof package

back.” The District Court concluded that “Longley’s version of the roof transaction is

simply not credible.”

¶12 Shortly after the roof system arrived on site, Longley and Ellis disagreed on how it

should be installed. Ellis quit. The District Court found that by this point the Whites had

paid Longley more than $180,000 for a “shoddily constructed unroofed structure.” The

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Brunner v. Lacasse
763 P.2d 662 (Montana Supreme Court, 1988)
First Bank (N.A.) — Billings v. Clark
771 P.2d 84 (Montana Supreme Court, 1989)
Sacco v. High Country Independent Press, Inc.
896 P.2d 411 (Montana Supreme Court, 1995)
Baltrusch v. Baltrusch
2003 MT 357 (Montana Supreme Court, 2003)
Ioerger v. Reiner
2005 MT 155 (Montana Supreme Court, 2005)
Town of Geraldine v. Montana Municipal Insurance Authority
2008 MT 411 (Montana Supreme Court, 2008)
Jacobsen v. Allstate Insurance
2009 MT 248 (Montana Supreme Court, 2009)
White v. Longley
2010 MT 254 (Montana Supreme Court, 2010)
Cruse v. Clawson
352 P.2d 989 (Montana Supreme Court, 1960)
People v. Pacific Landmark
29 Cal. Rptr. 3d 193 (California Court of Appeal, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2010 MT 254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-longley-mont-2010.