White v. County of San Diego

608 P.2d 728, 26 Cal. 3d 897, 163 Cal. Rptr. 640, 1980 Cal. LEXIS 161
CourtCalifornia Supreme Court
DecidedApril 14, 1980
DocketL.A. 31131
StatusPublished
Cited by18 cases

This text of 608 P.2d 728 (White v. County of San Diego) is published on Counsel Stack Legal Research, covering California Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
White v. County of San Diego, 608 P.2d 728, 26 Cal. 3d 897, 163 Cal. Rptr. 640, 1980 Cal. LEXIS 161 (Cal. 1980).

Opinions

Opinion

NEWMAN, J.

Plaintiffs appeal from a judgment denying them declaratory and injunctive relief against special assessments levied by defendant San Diego County to help pay the cost of widening and improving Mission Gorge Road, a major thoroughfare adjacent to the assessed parcels. Plaintiffs contend (1) that the assessments were not justified by any special benefits to their property, and (2) that each parcel’s assessment was not in proportion to that parcel’s benefits.

As explained below, well-established rules answer the first contention. The second contention presents this issue, new in this court: When a right-of-way is obtained for street widening, is the requirement of proportionality necessarily violated by a policy that fixes the part of each assessment attributable to the cost of acquisition at an amount equal to what was paid for that segment of the right-of-way acquired from the assessed parcel when (1) no similar component is included in the assessment made against parcels from which other segments previously have been dedicated without compensation, and (2) the record and judicially [901]*901noticed facts are consistent with a reasonable legislative conclusion that each acquired segment is substantially proportionate in value to the front footage of the parcel from which it is taken?

The project covered 4.5 miles of Mission Gorge Road. Until widened in 1974-1975 the road covered only 40 feet of a 60-foot right-of-way; yet it was used heavily not only for commuting and other through traffic but also for access to commercial enterprises that adjoined the road, including gas stations, drive-ins, shopping centers, trailer parks, and apartment complexes. The project widened the right-of-way to 102 feet and the road to 82 feet, consisting of four 12-foot lanes divided by an 18-foot median (used for left turns) and flanked by 8-foot shoulders (used for parking). A bridge was enlarged; curbs, gutters, sidewalks, storm drains, traffic signals, and related facilities were installed.

Initiated in 1971, the project was financed partly from the county road fund and partly through an assessment district formed under the Improvement Act of 1911 (Sts. & Hy. Code, § 5000 et seq.).1 The arrangement was the county’s first use of Policy J-16, adopted in 1970. It deals with the financing of improvements to highways that were then designated as “Select System roads” (former §§ 186.3, 186.4, 2106). It requires that abutting owners bear the cost of acquiring the right-of-way for and constructing the improvement’s “local interest portion,” defined as “that portion of the road used primarily for access to adjacent land and generally consisting] of a travel lane and parking lane (20 feet in combined width), and concrete curb, gutter, and sidewalk on each side of the through roadway.” It states that the county will bear costs of engineering, drainage, appraisal negotiations, and damage to abutting property.

The board of supervisors’ resolution of March 14, 1972, which instituted assessment proceedings for the Mission Gorge project, declared that the county would “contribute. . . the cost of all work abutting publicly owned property.. . and the cost of all engineering, right of way acquisition (except the actual land purchase cost), construction of two travel lanes, median strip and bridge widening, installation. . .of. . . drainage facilities [and] traffic signals, and relocation of any utility not the responsibility of a utility company.” The remaining costs were substantially those that Policy J-16 pronounced to be the responsibility of abutting owners.

[902]*902On March 6 and June 5, the board adopted plans and specifications and an Assessment District Map delineating a district comprising the property fronting on the improvement. On July 10 the board resolved that the project was “of more than local and ordinary benefit to the public” and declared the new district “to be the district benefited by said work and improvement and to be assessed to pay the costs and expenses thereof.” At ensuing hearings the owners, substantially all of whose property was commercial, complained that the project would mostly benefit the through traffic and thus should be paid for out of general funds or by assessing a larger district. On May 8 and June 5, 1974, the board reaffirmed its declarations of special benefit to the described district. The construction contract was awarded in July 1974; the project was completed in October 1975. Of the total cost the assessed owners contributed $649,571; the county, $2,516,009.

One hundred forty-three parcels were assessed as follows: (1) construction cost at $16.50 per front foot less credit for improvements privately constructed; (2) right-of-way costs; (3) administrative expense ($25 plus 0.56 percent of construction cost).

Plaintiffs’ main objection to the apportionment of assessments involves the method of assessing right-of-way cost. As explained by county officials at the hearings, the disputed method was “based on the precept that each parcel will provide the right of way for that portion of the road upon which the parcel fronts and the benefit to the parcel is equal to the value of the strip of right of way taken.” That value was fixed at either the amount paid for the land or the appraiser’s estimate if that amount had not yet been determined. It did not include compensation for elements such as improvements, easements, or damages. There was no right-of-way assessment for 30 parcels from which the right-of-way already had been dedicated under planning and zoning regulations, including an “Official Centerline Ordinance” that conditioned permission for private development on such dedication.

The policy of “assessing back” amounts paid for land taken, not articulated in Policy J-16, seems to have antedated this assessment proceeding. It apparently was articulated at a public meeting held in August 1971 to explain the project.

There is practically no information in the record on variations between ratios of right-of-way assessments to front footage or other parcel characteristics. From statements of protesting property owners and of [903]*903officials at the hearings, however, it appears that some owners vigorously negotiated or litigated the amounts they were to receive for rights-of-way and that consequent disparities in compensation paid produced corresponding disparities in the right-of-way component of the assessments.

The board finally confirmed the assessments on January 28, 1976, and plaintiffs filed for declaratory and injunctive relief on February 26 and 27. After a consolidated trial the two actions were consolidated for all purposes. The trial court made findings of fact and conclusions of law, and adjudged against plaintiffs.

Did plaintiffs receive a fair hearing?

Plaintiffs concede that the county adopted the resolutions, held the hearings, and followed all other steps necessary to form the district and impose the assessments. They contend, though, that the board did not accord a fair hearing because it had prejudged critical issues. They point to Policy J-16’s formulation of what improvement costs should be assessed against abutting owners and to prior formulation of the scheme that assesses owners (1) for construction costs on a front-foot basis, and (2) for right-of-way costs measured by the amount paid for the strip taken from each assessed parcel.

The contention is without merit.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Coziahr v. Otay Wat. Dist.
California Court of Appeal, 2024
Capistrano Taxpayers Ass'n v. City of San Juan Capistrano
235 Cal. App. 4th 1493 (California Court of Appeal, 2015)
Griffith v. Pajaro Valley Water Management Agency
220 Cal. App. 4th 586 (California Court of Appeal, 2013)
Town of Tiburon v. Bonander
180 Cal. App. 4th 1057 (California Court of Appeal, 2009)
Bauer v. City of Olathe
894 P.2d 823 (Supreme Court of Kansas, 1995)
Tahoe Keys Property Owners' Ass'n v. State Water Resources Control Board
23 Cal. App. 4th 1459 (California Court of Appeal, 1994)
California Radioactive Materials Management Forum v. Department of Health Services
15 Cal. App. 4th 841 (California Court of Appeal, 1993)
Knox v. City of Orland
841 P.2d 144 (California Supreme Court, 1992)
San Diego Gas & Electric Co. v. San Diego County Air Pollution Control District
203 Cal. App. 3d 1132 (California Court of Appeal, 1988)
Untitled California Attorney General Opinion
California Attorney General Reports, 1987
Moore v. City of Chandler
713 P.2d 325 (Court of Appeals of Arizona, 1985)
J. W. Jones Companies v. City of San Diego
157 Cal. App. 3d 745 (California Court of Appeal, 1984)
City of San Diego v. Holodnak
157 Cal. App. 3d 759 (California Court of Appeal, 1984)
White v. County of San Diego
608 P.2d 728 (California Supreme Court, 1980)

Cite This Page — Counsel Stack

Bluebook (online)
608 P.2d 728, 26 Cal. 3d 897, 163 Cal. Rptr. 640, 1980 Cal. LEXIS 161, Counsel Stack Legal Research, https://law.counselstack.com/opinion/white-v-county-of-san-diego-cal-1980.