Whistler v. Burlington Northern Railroad

741 P.2d 422, 228 Mont. 150, 44 State Rptr. 1415, 1987 Mont. LEXIS 970
CourtMontana Supreme Court
DecidedAugust 18, 1987
Docket86-582
StatusPublished
Cited by12 cases

This text of 741 P.2d 422 (Whistler v. Burlington Northern Railroad) is published on Counsel Stack Legal Research, covering Montana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Whistler v. Burlington Northern Railroad, 741 P.2d 422, 228 Mont. 150, 44 State Rptr. 1415, 1987 Mont. LEXIS 970 (Mo. 1987).

Opinions

MR. JUSTICE HARRISON

delivered the Opinion of the Court.

Plaintiffs appeal the denial of their application for a preliminary injunction entered by the District Court of the Thirteenth Judicial District in and for Yellowstone County. We affirm.

Plaintiffs (the “Morledges”) initiated this action to challenge the [152]*152issuance of a building permit issued by Yellowstone County to the Burlington Northern Railroad. The permit was issued on February 6, 1986, and authorized construction of a 35,000 barrel diesel tank and excavation and site work for an accompanying retaining dike. The Morledges own land adjacent to the location of the fuel tank.

Burlington designed this fuel tank to facilitate the transportation of diesel fuel used in its everyday operations. The tank is located near the intersection of the Yellowstone and Powder River Pipelines. The Yellowstone Pipeline is a ten-inch line running east and west, originating in Billings, Montana and terminating in Moses Lake, Washington. Finished petroleum products are moved through this pipeline in ten day cycles, with separate batches of gasoline, distillate and diesel fuel transported in a patterned sequence during each cycle.

The Powder River Pipeline is a four-inch line running generally north and south, and was previously used to deliver crude oil to Laurel, Montana. The two pipelines intersect north of Laurel at a point named Alkali Creek Station.

For economic reasons, Burlington sought a way to transport diesel fuel from refineries in Billings to its Laurel railyards via pipeline rather than by railroad tank cars. Hence, Burlington designed a plan to transport fuel from the Billings refineries west through the Yellowstone Pipeline to Alkali Creek Station and then south to Laurel through the Powder River line.

However, because of the mismatched pipe diameters, the cycling of other products on the Yellowstone line and the amount of fuel to be transported, Burlington’s fuel could not pass directly from the Yellowstone to the Powder River line. Burlington therefore designed this fuel tank so that its fuel could be transported at high pressure along the Yellowstone line, directed into the fuel tank, and then repumped at a lower pressure into the Powder River line. By necessity with this design, this tank, in addition to orchestrating the change of flow of the fuel, would also have to store temporarily the fuel that would accumulate before it could all be repumped into the Powder River line.

With this design in mind, Burlington submitted its application for a building permit to construct the tank and related accessories. The property upon which Burlington sought to construct its tank is zoned Agricultural-Open Space (“A-O”) by the Yellowstone County Jurisdictional Area Zoning Plan.

Typically, this County Zoning Plan permits certain land uses [153]*153within each particular zoning designation as well as certain other uses deemed accessory to the specified allowed uses. Under the terms of this Plan, pipelines are permitted uses within an A-0 zone. Liquid petroleum storage, on the other hand, is permitted as a primary use only in the Heavy Industrial Zone and in certain other (non A-O) zones pursuant to special exception.

Burlington submitted its building permit application on November 4, 1985. Upon initial review, the Zoning Coordinator and the City-County Planning Department determined the project was not permitted in an A-0 zone. Following this initial decision, Burlington and Continental Pipe Line Company (co-owner and operator of the Yellowstone line and owner and operator of the Power River line), through legal counsel, submitted a letter to the Zoning Coordinator. The letter contained additional factual information and legal authority supporting Burlington’s position that the fuel tank and associated facilities were permitted in an A-O zone. On December 23, 1985, a meeting was held to discuss the project and zoning issues, and shortly thereafter, the city-county zoning officials concluded this fuel tank was part of the pipeline and therefore permitted in an A-O zone. The county issued Burlington the necessary building permits and construction began.

The Morledges commenced this action in the District Court,1 requesting relief which included, inter alia, an order declaring the issuance of the building permit to Burlington arbitrary, capricious, an abuse of discretion and unlawful and an order permanently enjoining the construction of the fuel tank and retaining dike. In addition, the Morledges filed an application for preliminary injunction seeking to enjoin commencement or continuation of construction of the tank and its accessories. The District Court issued a show cause order regarding the preliminary injunction and set a hearing for March 13, 1986.

Following the hearing, the District Court denied the Morledges’ application for preliminary injunction. The parties later stipulated that the court’s findings and conclusions should be treated as final, thereby resolving the case on its merits before the District Court. Pursuant to the written stipulation, the District Court entered judgment denying the requests for all relief sought by the Morledges and dismissed their complaint with prejudice. The Morledges now appeal.

On appeal, appellants appear to present essentially two arguments. They first contend that the District Court erred in its conclusion [154]*154that the zoning officials’ decision was lawful, regular and reasonable. Appellants instead insist that the zoning officials’ decision was arbitrary, capricious and an abuse of discretion. Second, appellants argue that as a matter of law, the District Court erred in its interpretation of the County Zoning Plan. Both arguments center upon the contention that this fuel tank, regardless of its stated purpose, will store fuel, and is therefore not permitted in an A-0 zone. Though the arguments are related, we will address each separately.

I

We are first asked to determine whether substantial, credible evidence supports the District Court’s conclusion that the zoning officials’ decision was lawful, regular and reasonable.

We initially note that when an administrative decision or order is reviewed by a district court, it is entitled to a rebuttable presumption in favor of the decision of the agency. Thornton v. Commissioner of the Dept. of Labor and Industry (Mont. 1980), [190 Mont. 442,] 621 P.2d 1062, 1064-65, 37 St.Rep. 2026, 2028. This rebuttable presumption is generally recognized in the zoning and planning context. See Gordon Paving Co. v. Blaine County Board of County Commissioners (1977), 98 Idaho 730, 731, 572 P.2d 164, 165. The Oregon Supreme Court, addressing the issuance of a building permit, stated in Murphy v. S.A. Hutchins & Associates Const. Co., Inc. (1972), 263 Or. 245, 501 P.2d 1273, 1275:

“[A] presumption of validity, regularity, and reasonableness accompanies the acts of the city officials charged with the enforcement of the ordinance.” [Citation omitted.]

The District Court correctly recognized this presumption.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Planned Parenthood v. State
2022 MT 157 (Montana Supreme Court, 2022)
Williams v. Board of County Commissioners
2013 MT 243 (Montana Supreme Court, 2013)
Sutey Oil Co. v. Anaconda-Deer Lodge County Planning Board
1998 MT 127 (Montana Supreme Court, 1998)
Patterson v. Utah County Board of Adjustment
893 P.2d 602 (Court of Appeals of Utah, 1995)
Patterson v. UTAH CTY. BD. OF ADJUSTMENT
893 P.2d 602 (Court of Appeals of Utah, 1995)
Benson v. City of Helena
Montana Supreme Court, 1993
McElwain v. County of Flathead
811 P.2d 1267 (Montana Supreme Court, 1991)
Schendel v. Board of Adjustment
774 P.2d 379 (Montana Supreme Court, 1989)
Whistler v. Burlington Northern Railroad
741 P.2d 422 (Montana Supreme Court, 1987)

Cite This Page — Counsel Stack

Bluebook (online)
741 P.2d 422, 228 Mont. 150, 44 State Rptr. 1415, 1987 Mont. LEXIS 970, Counsel Stack Legal Research, https://law.counselstack.com/opinion/whistler-v-burlington-northern-railroad-mont-1987.