Wheeler v. Marvin's, Inc.

593 So. 2d 61, 1991 Ala. LEXIS 1152, 1991 WL 251676
CourtSupreme Court of Alabama
DecidedNovember 27, 1991
Docket1900818, 1900819
StatusPublished
Cited by8 cases

This text of 593 So. 2d 61 (Wheeler v. Marvin's, Inc.) is published on Counsel Stack Legal Research, covering Supreme Court of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheeler v. Marvin's, Inc., 593 So. 2d 61, 1991 Ala. LEXIS 1152, 1991 WL 251676 (Ala. 1991).

Opinion

These appeals arise from suits brought by materialmen pursuant to Code of Alabama 1975, § 35-11-218, to enforce liens against the "unpaid balance" due by a homeowner under contract.1 Following nonjury proceedings, the trial court entered judgments for the materialmen. We affirm.

On August 7, 1989, Scott and Deborah Wheeler entered into a contract with Davenport Companies, Inc., Davenport Property, Inc., Davenport Building Company, Inc., and James D. Davenport (all of whom we shall call "Davenport") for the construction of a house on the Wheelers' property in Tuscaloosa, Alabama. The original contract price of the Wheelers' home was $667,000. The Wheelers obtained a loan from Central Bank of the South ("Central Bank") for that amount; a "draw" or construction account was set up to pay approved draws on the loan.

The Wheelers hired Ray Harris as their architect and to oversee the construction project. Davenport hired several subcontractors and materialmen. Among the materialmen were Pinson Valley Millworks, Inc. ("PVM"), which supplied windows, doors, and moldings, and Marvin's, Inc., which supplied various building materials.

Davenport commenced construction in August 1989. On November 17, 1989, the Wheelers were notified that Davenport had gone out of business. On November 20, 1989, the Wheelers assumed the control of the construction of the house. Also on November 20, Marvin's served a lien notice on the Wheelers; on November 27, 1989, Marvin's filed a verified statement of lien in Tuscaloosa County Probate Court for $34,459.71. On November 22, 1989, PVM served on the Wheelers a lien notice; on November 30, 1989, PVM filed a verified statement of lien in Tuscaloosa County Probate Court for $17,217.91. The construction was 46 percent complete when Davenport ceased operation.

On November 24, 1989, the Wheelers completed the fourth application requesting additional money. The Wheelers received $60,000, and these funds were deposited into the construction account. As of November 24, there had been four draws on this account, totalling $304,465.

Marvin's and PVM allege that, notwithstanding the lien notices filed by them, the Wheelers used $35,238.75 of the $60,000 loan to pay certain subcontractors and a materialman for work performed before Davenport ceased operation. The Wheelers claim that in order to continue the construction work as scheduled, they were forced to pay in full some of the debts owing to the subcontractors and a materialman that pre-existed Davenport's termination. Those who were paid out of the $60,000 loan were:

1. K. Feltman, subcontractor — $ 3,501.00 2. Madison Masonry, subcontractor — $16,272.00 3. Lowery Electric, subcontractor — $ 9,467.00 4. J.F. Day, supplier — $ 5,998.75

These preferential payments totalled $35,238.75. The house was completed in May 1990, and the final cost was $741,176.

In December 1989, Marvin's and PVM filed complaints in the Circuit Court of Tuscaloosa County, Alabama, against Davenport, Central Bank, and the Wheelers. Both Marvin's and PVM sought to enforce their liens on the Wheelers' property for materials supplied to Davenport for construction of the Wheelers' house. *Page 63

The two cases were consolidated for trial with suits filed against the Wheelers by two other lien claimants, Kilpatrick Concrete Company ("Kilpatrick") and Barnes Excavating Company ("Barnes"). On November 19 and 20, 1990, a nonjury trial was conducted on all four cases; the trial judge issued his initial judgment in favor of Marvin's and PVM and against Davenport and the Wheelers; in favor of Kilpatrick, and against the Wheelers; and in favor of the Wheelers and against Barnes.

On December 20, 1990, the trial court entered an order setting aside the judgment in favor of Kilpatrick and entered a judgment in favor of the Wheelers and against Kilpatrick. In addition, the court imposed liens against the Wheelers' property based on claims filed by Marvin's and PVM.

The Wheelers filed a motion to amend the judgment and a motion for new trial, and on January 28, 1991, the trial court entered a "Second Amended Judgment and Order On Motion for New Trial," which read as follows:

"After considering [Wheeler's] motion for new trial, the Court amends its judgment as follows:

"This Court amends its factual findings as follows:

"The original contract price of the home was $667,000.00. The court finds that the home could not have been completed for the contract price, and the difference between the contract price and the actual reasonable and necessary price to complete the home should be deducted from the unpaid balance. The actual price to complete the home was $741,176.00. This figure included the following expenses not included in the original contract:

Swimming Pool $22,500 Fence Around pool $ 7,000 Finishing Two additional Rooms $ 8,500 Unnecessary Christmas Bonus to Olmstead $ 1,000 Security $17,400 Fee to Pave Pro $ 1,500 Shutters Amount exceeded allowance $ 4,000 Survey 150 Extra for architect 950 Over allowance sprinkler system 600 ------- TOTAL expenses not in contract $63,650

"If this sum is deducted from $741,176.00, the actual cost to complete the house as contracted is $677,526.00. The difference between $677,526.00 and the contract price is $10,526.00. The defendant Wheelers are entitled to have this sum deducted from the unpaid balance as previously ordered by this Court, i.e., $61,810.60 — $10,526.00 = $51,284.60

"The lien notice filed by plaintiff [Marvin's] was for $34,459.71 and by plaintiff Pinson Valley Millworks Inc. was for $17,217.91. These plaintiffs are entitled to share the unpaid balance on a pro rata basis.

"The sum total of the lien claimed by the plaintiffs is $51,677.62, which is $393.02 more than the unpaid balance. Liens are hereby established in favor of plaintiff [Marvin's] in the amount of $34,155.54 and in favor of plaintiff Pinson Valley Millworks, Inc. in the amount of $17,129.06. The previous judgments as last amended are to remain otherwise unchanged and the defendants' motion for new trial is overruled and denied."

Where the evidence is presented to the trial court ore tenus, as it was in this case, the trial court determines the weight and credibility of the testimony, and its findings are presumed correct and will not be disturbed on appeal unless the record reveals the evidence to be plainly and palpably wrong or manifestly unjust. Tibbs v. Anderson, 580 So.2d 1337, 1339 (Ala. 1991); Justice v. Arab Lumber Supply, Inc.,533 So.2d 538, 543 (Ala. 1988).

"Under the 'ore tenus rule,' a presumption of correctness accompanies the trial court's judgment when it has made findings of fact based on oral testimony without a jury, and its judgment will not be reversed unless it is shown to be plainly and palpably wrong, considering all of the evidence and all inferences that can be logically drawn from the evidence. King v. Travelers Ins. Co., 513 So.2d 1023 (Ala. 1987); McCrary v. Butler, 540 So.2d 736 (Ala. 1989). The trial court's judgment in such a case will be affirmed, if, under any reasonable aspect of the testimony, there is credible evidence to *Page 64 support the judgment. McCrary v. Butler, supra; Jones v. Jones, 470 So.2d 1207 (Ala. 1985)."

Clark v. Albertville Nursing Home, Inc.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Inline Electric Supply Co. v. Eskildsen
198 So. 3d 524 (Court of Civil Appeals of Alabama, 2015)
Smith v. Smith
196 So. 3d 1191 (Court of Civil Appeals of Alabama, 2015)
Corner Stone Funeral Chapel, Inc. v. MVMG, LLC
170 So. 3d 626 (Supreme Court of Alabama, 2014)
RLI Ins. Co. v. MLK AVE. REDEVELOP. CORP.
925 So. 2d 914 (Supreme Court of Alabama, 2005)
Cadle Co. v. Friedman
631 So. 2d 962 (Supreme Court of Alabama, 1994)
Buckner v. Alpha Lumber and Supply Co.
628 So. 2d 450 (Supreme Court of Alabama, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
593 So. 2d 61, 1991 Ala. LEXIS 1152, 1991 WL 251676, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheeler-v-marvins-inc-ala-1991.