Inline Electric Supply Co. v. Eskildsen

198 So. 3d 524, 2015 Ala. Civ. App. LEXIS 288, 2015 WL 8567254
CourtCourt of Civil Appeals of Alabama
DecidedDecember 11, 2015
Docket2140917
StatusPublished
Cited by1 cases

This text of 198 So. 3d 524 (Inline Electric Supply Co. v. Eskildsen) is published on Counsel Stack Legal Research, covering Court of Civil Appeals of Alabama primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Inline Electric Supply Co. v. Eskildsen, 198 So. 3d 524, 2015 Ala. Civ. App. LEXIS 288, 2015 WL 8567254 (Ala. Ct. App. 2015).

Opinion

THOMPSON, Presiding Judge.

Inline Electric Supply Company, Inc. (“Inline”), appeals from a summary judgment the Jefferson Circuit Court (“the trial court”) entered in favor of Samuel Esk-ildsen and Jennifer Eskildsen regarding Inline’s, effort to enforce an “unpaid-balance” materialman’s lien.

' The record indicates the following. On March 26, 2012, the Eskildsens entered into a contract with Rusert Homes, LLC (“Rusert”), for the construction of a residence in Jefferson County (“the construction project”). The contract specified that the price of the construction project was $550,000. Rusert had entered into a “credit purchase agreement” with Inline in 2008, pursuant to which Inline would provide material and labor for the construction of homes that Rusert was building. Between April 10, 2013, and' May 1, 2013, Inline delivered materials to the site of the construction project. Those materials had a value of .$6,690.68.

In an affidavit submitted to the trial court in support of a motion for a summary judgment, Samuel Eskildsen stated that, before' the construction project was completed, Rusert “defaulted on the work and contract, ceased its work and abandoned the work on [the construction project].” Specifically, Eskildsen said that, at the time Rusert abandoned the construction project, there were defects in the work that had been done and work that Rusert had failed to correct or complete. Although in an excerpt from Samuel Esk-ildsen’s deposition included in the record Eskildsen testified that he made no payments to Rusert after April 29, 2013, there is no evidence in the record as to exactly when Rusert abandoned the construction project or how much work remained to be done before the project would have been completed. Eskildsen also stated in his affidavit that, to complete the construction project in accordance with -the contract, he incurred costs in excess of what was to have been paid to Rusert under the contract. Therefore, Eskildsen stated, there was no unpaid balance owed to Rusert in connection with the construction project. [526]*526Again, however, there is no evidence in the record to indicate how much the Eskild-sens paid to complete the construction project.

On June 17, 2018, Inline served the Esk-ildsens with notice of its intent to file a materialman’s lien (“the lien”) against the property where the construction project was taking place. The lien was for the $6,690.68 that Inline claimed Rusert owed Inline for materials it had provided for the construction project. The lien was filed in the- Jefferson Probate Court on June 19, 2013. .. ..

On June 21, 2013, the Eskildsens made payments by check directly to two subcontractors pursuant to “joint check- agreements” they had entered into with Rusert and the two subcontractors. The joint check agreements had been executed before the Eskildsens received notice of Inline’s intent to file the hen. The-payment to one subcontractor was $14,446.87, and the payment to the other subcontractor was $3,966.47, for a total amount of $18,411.34.

, On July 5, 2013, Inline filed a civil action against numerous defendants, including Rusert -and the Eskildsens. The only claim alleged against the Eskildsens was to enforce the lien,. Because the claims against the other defendants .are not relevant to this appeal, they will not be discussed in this opinion. We do note, however, that Inline ultimately received a judgment against Rusert in the amount of $106,682.38,

• The Eskildsens filed a motion for a summary judgment against Inline, asserting that there was no unpaid balance owed to Rusert at the time they received the notice from Inline that it intended to file a lien on the property at the site of the construction project. Inline opposed the motion. The trial court heard arguments from .the parties on the motion, and on May 26, 2015,'it entered a summary judgment in favor of the Eskildsens. In the judgment, the trial court stated that any lien claim Inline had against the Eskildsens was limited by the unpaid balance between the Eskildsens and Rusert. - The trial court determined that, based on. the evidence submitted in support of and in opposition to the Eskild-sens’ motion for a summary judgment, no such unpaid balance existed and that, therefore, the Eskildsens were entitled to a judgment in their favor. The judgment became final on June 23, 2016, when a judgment was entered on Inline’s remaining claims. Inline filed a timely notice of appeal to the Alabama Supreme Court, which transferred the appeal to this court pursuant to §' 12-2-7(6), Ala.Code 1975.

The standard by which this court reviews summary judgments is well settled.

“This Court’s review of a summary judgment is de novo. Williams v. State Farm Mut. Auto. Ins. Co., 886 So.2d 72, 74 (Ala.2003). We apply the same standard of review as the trial court applied. Specifically, we must determine whether the movant has made a prima facie showing that no genuine issue of material fact exists and that the movant is entitled to a judgment as a matter of law. Rule 56(c), Ala. R. Civ. P.; Blue Cross & Blue Shield of Alabama v. Hodurski, 899 So.2d 949, 952-53.(Ala.2004). In making such a determination, we must review the evidence in the light most favorable "to the nonmovant. Wilson v. Brown, 496 So.2d 756, 758 (Ala.1986). Once the movant makes a prima facie showing that there is no genuine issue of material fact, the burden then shifts to the nonmovant to produce ‘substantial evidence’ as to the existence of a genuine issue of material fact. Bass v. SouthTrust Bank of Baldwin County, 538 So.2d 794, 797-98 (Ala.1989); Ala. Code 1975, § 12-21-12. ‘[Substantial [527]*527evidence is evidence of such weight and quality that fair-minded persons in the exercise of impartial judgment can reasonably infer the existence of the fact sought to be proved.’ West v. Founders Life Assur. Co. of Fla., 547 So.2d 870, 871 (Ala.1989).”

Dow v. Alabama Democratic Party, 897 So.2d 1035, 1038-39 (Ala.2004).

Inline first argues that the trial court erred in entering the summary judgment in favor of the Eskildsens because, it says, Samuel Eskildsen’s affidavit, in which he states that there was no unpaid balance on the contract, was inadmissible.1 Specifically, Inline argues that-Eskildsen’s affidavit was not accompanied by evidence to support what Inline called the Eskildsens’ “conclusory allegation” that' there was no unpaid balance on the contract. The statement was unsubstantiated by any fact, Inline said, and was therefore inadmissible to support the Eskildsens’ motion for a summary judgment.

Arguably, the statement that Inline now challenges is a statement of fact and not a conclusory allegation. However, for purposes of this opinion, we need not reach the issue whether the challenged statement constitutes an allegation or á factual statement. As the Eskildsens point out, and as our review of the record demonstrates, Inline did not move to strike the affidavit at issue. In Ex parte Secretary of Veterans Affairs, 92 So.3d 771 (Ala.2012), our supreme court reiterated the requirements for successfully challenging the admissibility of an affidavit submitted in support of or in opposition to a motion for a summary judgment, writing:

“Cases decided after Perry [v. Mobile County, 533 So.2d 602 (Ala.1988),] have not always been clear in holding that a party challenging the admissibility of an affidavit must object to the affidavit and move to strike it. See Ex parte Diversey Corp.,

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Turner v. Wells Fargo Bank, N.A.
254 So. 3d 194 (Court of Civil Appeals of Alabama, 2016)

Cite This Page — Counsel Stack

Bluebook (online)
198 So. 3d 524, 2015 Ala. Civ. App. LEXIS 288, 2015 WL 8567254, Counsel Stack Legal Research, https://law.counselstack.com/opinion/inline-electric-supply-co-v-eskildsen-alacivapp-2015.