Wheeler Lumber, Bridge & Supply Co. v. White

145 N.W. 917, 164 Iowa 495
CourtSupreme Court of Iowa
DecidedMarch 17, 1914
StatusPublished
Cited by4 cases

This text of 145 N.W. 917 (Wheeler Lumber, Bridge & Supply Co. v. White) is published on Counsel Stack Legal Research, covering Supreme Court of Iowa primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wheeler Lumber, Bridge & Supply Co. v. White, 145 N.W. 917, 164 Iowa 495 (iowa 1914).

Opinion

Withrow, J.

I. The plaintiff, Wheeler Lumber, Bridge & Supply Company, commenced this action to establish and foreclose á mechanic’s lien, making the owners of the property, the contractors, and Carr & Adams Company, a junior lienholder, defendants. The contractors made default, the owners denied liability, and the junior lienholder filed a cross-petition, asking that its lien be established and foreclosed junior to the lien of the plaintiff. Upon hearing, the trial court entered judgment against the contractors for the amount of the claims of plaintiff and cross-petitioner, and established the claims as liens in the order prayed, from which the owners appeal.

[497]*4971. L,iBNs':Ncontract ri«w:seo£' parties. [496]*496II. On September 26,1911, Geo. F. White entered into a written contract with Burnett Bros, under which the .latter [497]*497were to furnish the material and construct a dwelling ‘ ‘ on land owned by party of the first part,” according to plans and specifications, for a total eonsideration of $3,510, which was to- be paid in cer- . ’ , tain amounts at different times as the work progressed, aggregating $2,225, and the balance, or $1,285, was payable when the dwelling was completed.

The land, in fact, belonged to Caroline J. White, the wife of George F. White, but it is shown by the testimony of both husband and wife that the contract was made with her approval; that she had knowledge of it; and that at all times during the progress of the work she knew of it and of the claims of various materialmen. She claims, however, that she expressly stated that she would expend only $3,510 in the construction of the' dwelling, and that, as the establishment of the liens sought to be enforced in the present action would exceed the total amount payable under the contract, she nor her property cannot be held liable for such excess. In her testimony she stated that she recognized her liability for certain extras which had gone into the building, and which would increase the total cost. Other conditions permitting, the right to a lien upon her land for material used in the building, under this showing of facts cannot be questioned. Band v. Posher, 73 Iowa, 396. The record shows that during the progress of the work White paid to the contractors various amounts aggregating $2,125, the last of which was on March 16, 1912. The claims for liens which are made by the plaintiff and by the cross-petitioners are for material which either admittedly went into the building, or is proven by such facts as satisfy us that the defendants received the benefit of all for which claim is made.

5. save: time for evidence0.*106' The last item in the claim of the Wheeler company is dated May 13th, and is for roofing material, the amount charged being $2. The next preceding item in the bill is dated March 11th. The claim for mechanic’s lien, as a subcontractor, was filed by plaintiff June 12, 1912, or within thirty days after May 13th. Upon [498]*498the claim that the filing was too late, evidence was introduced on the part of the, defendants tending to show that the item of May 13th was not furnished, and that therefore the rights of the plaintiff must depend upon its account with the last item being March 11th. The evidence shows that a charge ticket for that item was made by plaintiff in the usual way of business, although there was a dispute as to the actual delivery, but their records do so stale, and it is upon this that the appellant relies; but it does appear that material of the kind for which the charge is made was used as roofing for the porch some time in May, this being testified to by appellant, and also by men who were then engaged in the work, and from it we hold that the charge was a proper one.

III. Reaching the conclusion that the claims for liens were filed in time, and also that the rights and liability of Mrs. White must in all respects be determined as though she had personally made the contract with the Burnett Bros., and as though she had performed the acts done by her husband in settling with materialmen, as such will be hereafter considered, we turn to the facts bearing upon the claims of the Wheeler Company and the Carr & Adams Company, which were, by the decree of the trial court, established in the amounts claimed as liens against the property, there being no real dispute as to the items, excepting as we have stated, but upon their right to liens.

3. Same: rights of subcontractors. IY. It is urged by the appellants that the contract provided that the payment of the balance above the $2,225, which was to be paid at various times, was not due until the building was completed; that there was a failure on the part of the contractor to do the work according to the plans and specifications; that it was defective or inferior in many respects, and' unfinished ; and that therefore the final payment was not due; and that the claims of subcontractors can only be asserted against a payment or obligation at the time actually due. There can be no question of the rule in its general application that the sub[499]*499contractor can only assert his claim against such rights, as are held by the principal contractor (Code, Section 3093), and that the owner cannot be compelled to pay a greater amount than is provided in his contract. But, as recognized in cases which we will later consider, there may arise instances when, from some act of the owner in which he fails to protect himself against outstanding material claims of which he has knowledge, that the rule of liability upon which the appellants rely does not control.

The last item in the account of Carr & Adams Company was January 30, 1912, and their claim for lien was filed June 13th following. To bring themselves within the protection of Code, Section 3094, as to claims of subcontractors filed after thirty days, a notice as provided by that section was served upon Mrs. White. While appellants admit the presence at their home of the officer whose return shows the service, and its manner, they deny that service was had upon them. The return of the officer, which is presumptively correct, is supported by his testimony as to what was done; and from the record we are satisfied with the conclusion upon this branch of the ease that there was proper service of the notice. The claim for a lien of the Wheeler Company, filed June 12th, was in time under Code, Section 3093, and that of the Carr & Adams Company filed June 13th, and followed immediately by the notice to the parties, gave to each the general rights of subcontractors. We must then determine whether, under the facts shown in this record, as subcontractors, there was a fund due and payable under the original contract which is subject to their liens.

V. It is conceded that the appellants paid, on the order of the contractor, to the Des Moines Clay Company $100 on July 6th and $200 on July 7th; to Edwin Cutler, plumber, $275 on April 13th; Clifford & Company, April 29th, $169.80; Garver Hardware Company, July 18th, $75; and the Citizens’ Electric Company, July 27th, $30 — all of such payments being on account of material used in the construction of the [500]*500building, but for which no liens had been filed. It is admitted by the appellants that the material furnished by the Carr & Adams Company was delivered.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lane-Moore Lumber Co. v. Kloppenburg
215 N.W. 637 (Supreme Court of Iowa, 1927)
Mason City Brick & Tile Co. v. Lamson
190 Iowa 365 (Supreme Court of Iowa, 1920)
Orcutt Co. v. Schlappi
188 Iowa 378 (Supreme Court of Iowa, 1919)
Reese Gabriel & Co. v. Cornell
172 Iowa 734 (Supreme Court of Iowa, 1915)

Cite This Page — Counsel Stack

Bluebook (online)
145 N.W. 917, 164 Iowa 495, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wheeler-lumber-bridge-supply-co-v-white-iowa-1914.