Wheatland Contracting v. Jaco General Contractor, Inc.
Opinion
No. 120,401
IN THE COURT OF APPEALS OF THE STATE OF KANSAS
WHEATLAND CONTRACTING, LLC, Appellee,
v.
JACO GENERAL CONTRACTOR, INC.,
and
TRAVELERS CASUALTY AND SURETY COMPANY OF AMERICA, Appellants.
SYLLABUS BY THE COURT
The Kansas Fairness in Private Construction Contract Act, K.S.A. 16-1801 et seq., provides in K.S.A. 16-1806 that the venue for any action to enforce the Act shall be in the county where the real property is located. Parties to any construction contract covered by the Act cannot agree to a different venue.
Appeal from Johnson District Court; RHONDA K. MASON, judge. Opinion filed September 20, 2019. Affirmed.
Neil C. Gosch and Lisa L. Martin, of Triplett Woolf Garretson, LLC, of Wichita, for appellants.
Jody R. Gondring, of Hennessy & Gondring, P.A., of Kansas City, Missouri, and S. Owen Griffin, of Troppito Miller Griffin, LLC, of Kansas City, Missouri, for appellee.
Before HILL, P.J., LEBEN, J., and WALKER, S.J.
HILL, J.: This is an interlocutory appeal of an order denying a change of venue in a lawsuit arising out of a construction contract for a project in Johnson County. The subcontractor, Wheatland Contracting, LLC, sued the contractor, Jaco General Contractor, Inc., in Johnson County. In response, Jaco moved to transfer venue to Sedgwick County based on the forum selection clause in their contract. The district court denied Jaco's motion because the Kansas Fairness in Private Construction Contract Act states that venue for any action to enforce the Act shall be in the county where the real property is located. The sole question of law for us then, is, does the Act nullify this contract's choice-of-venue provision? It does.
Details provide a context for our decision.
Jaco and Wheatland agreed that Wheatland would perform plumbing and associated trade work on a Kentucky Fried Chicken restaurant in Johnson County. The contract contained a forum and venue selection clause that stated: "[T]o the fullest extent permitted by law, the parties agree and stipulate that the Eighteenth Judicial District, District Court, Sedgwick County, Kansas, is the court of exclusive jurisdiction and venue to determine any dispute between Contractor and Subcontractor arising out of or relating to this Subcontract."
Wheatland filed a mechanic's lien on the project in Johnson County. Jaco later substituted a bond for the mechanic's lien, which the court approved, and the court then discharged the lien. Wheatland proceeded to make a claim on that bond.
Wheatland sued in Johnson County District Court, claiming breach of contract, action on bond, violations of the Act, and quantum meruit. Jaco moved to dismiss or, in the alternative, to transfer venue to Sedgwick County. The district court denied the motion, ruling that despite the venue clause in the contract, the plain language of K.S.A.
16-1806 required the venue of the suit to be in the county where the project was located—Johnson County.
We granted Jaco's application for interlocutory review.
We review the Act.
Our task in answering this question of law is, as always, to look first at the statutes. We must try to learn legislative intent through the statutory language enacted, giving common words their ordinary meanings. When a statute is plain and unambiguous, an appellate court should not speculate about the legislative intent behind that clear language, and it should refrain from reading something into the statute not readily found in its words. With no ambiguity, the court need not resort to statutory construction. Only if the statute's language or text is unclear or ambiguous does the court use canons of construction or legislative history to construe the Legislature's intent. Ullery v. Othick, 304 Kan. 405, 409, 372 P.3d 1135 (2016). Because the Act is unambiguous, we need not look at the legislative history to determine legislative intent.
The Kansas Fairness in Private Construction Contract Act is comprised of seven statutes—K.S.A. 16-1801 through 16-1807. It regulates payments to contractors and subcontractors involved in nonresidential private construction. If payments of undisputed amounts are not paid, the Act calls for the mandatory imposition of prejudgment interest and attorney fees. Clearly, the Legislature is serious about enforcing the provisions of the Act because the first statute, K.S.A. 16-1801(b), voids all contract provisions that attempt to waive the rights and duties created by this law. In other words, parties cannot avoid the application of this law by contract.
We hold the purpose of this Act is to compel prompt payments of undisputed amounts that become due in these types of construction contracts. It covers all tiers in this
section of the construction industry—owner—contractor—subcontractor. We read the Act with that purpose in mind.
The heart of the Act is K.S.A. 16-1803, 16-1804, and 16-1805.
A quick review of those provisions shows how broad this law is. First, it bans certain specific provisions from all contracts. Then it eliminates a defense. It then establishes just what timeliness means for all of these construction contracts at the ownercontractor level and then at the contractor-subcontractor and subcontractor-subcontractor tiers. And then, the Act creates some tools that can be used to enforce the rights and duties created by the law.
K.S.A. 2018 Supp. 16-1803 begins by banning three provisions from all private construction contracts covered by the Act.
1. No provision of any contract will be enforced that waives the right to resolve disputes in court. (The Act does permit binding arbitration or alternate dispute resolution before litigation.)
2. No provision that waives lien rights for labor or material is enforceable, except as a condition for payment.
3. Any provision that tries to waive rights of subrogation for losses covered by liability or workers compensation insurance is not enforceable, except in limited circumstances.
K.S.A. 2018 Supp. 16-1803 provides that making payments to a subcontractor conditional upon payment from someone else, including the owner, is no defense to a claim to enforce a lien or a bond.
K.S.A. 2018 Supp. 16-1803 next establishes what timeliness means. If an owner does not pay the contractor within 30 days of any undisputed amount, then the owner is liable for 18 percent interest on the unpaid amount. Likewise, if a contractor does not pay a subcontractor within seven business days of any undisputed amount, then the contractor is liable for 18 percent interest on the unpaid amount. And finally, if a subcontractor fails to pay within seven business days any undisputed amount to another subcontractor, then the subcontractor is liable for 18 percent interest.
K.S.A. 2018 Supp. 16-1804 sets the maximum amount that can be retained for these construction contracts at 10 percent. And if that amount is not paid, then the party liable to pay the retainage is liable for 18 percent interest.
K.S.A. 16-1805 allows a contractor or subcontractor to suspend performance on the contract if not paid, including accrued interest, after giving notice.
Enforcement procedures are found in K.S.A. 16-1806.
K.S.A. 16-1806 directs that if a party has to sue to enforce any of these rights, the court shall award costs and attorney fees to the prevailing party. That statute also directs that venue for a lawsuit or a hearing in arbitration shall be in the county where the real property is located:
"In any action to enforce K.S.A. 16-1803, 16-1804 or 16-1805, and amendments thereto, including arbitration, the court or arbitrator shall award costs and reasonable attorney fees to the prevailing party. Venue of such an action shall be in the county where
the real property is located. The hearing in such an arbitration shall be held in the county where the real property is located." K.S.A. 16-1806.
The law, K.S.A. 16-1806, preempts venue-choice provisions in construction contracts covered by the Act.
Free access — add to your briefcase to read the full text and ask questions with AI
Wheatland Contracting v. Jaco General Contractor, Inc. (Wheatland Contracting v. Jaco General Contractor, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.