Westside Galvanizing Services, Inc. v. Georgia-Pacific Corporation and Southeastern Conveyor Fabricators, Inc., Aaa Steel Detailing, Inc., Intervenor

921 F.2d 735
CourtCourt of Appeals for the Eighth Circuit
DecidedJanuary 24, 1991
Docket89-2941
StatusPublished
Cited by6 cases

This text of 921 F.2d 735 (Westside Galvanizing Services, Inc. v. Georgia-Pacific Corporation and Southeastern Conveyor Fabricators, Inc., Aaa Steel Detailing, Inc., Intervenor) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westside Galvanizing Services, Inc. v. Georgia-Pacific Corporation and Southeastern Conveyor Fabricators, Inc., Aaa Steel Detailing, Inc., Intervenor, 921 F.2d 735 (8th Cir. 1991).

Opinion

STUART, Senior District Judge.

Westside Galvanizing Services, Inc. (Westside) appeals from a decision of the district court 1 awarding Westside only partial relief on its claims arising out of a construction project in southeastern Arkansas. In 1987, Georgia-Pacific Corporation (Georgia-Pacific), a Georgia corporation, built a chip thickness screening facility at its Crossett, Arkansas, papermill. Southeastern Conveyor Fabricators, Inc. (Southeastern), an Alabama corporation, furnished steel for the project. AAA Steel Detailing, Inc. (AAA Steel) provided plans to Southeastern for use in fabricating the steel, and Westside, a Louisiana corporation, galvanized the steel before it was shipped to the project.

By contract dated April 10, 1987, Georgia-Pacific agreed to pay $201,131.00 to Southeastern for fabrication, galvanization, and shipping of, among other things, 295 linear feet of steel posts, handrails, and toeboards. The contract provided that Georgia-Pacific would pay twenty-five dollars per foot of additional posts, handrails, and toeboards. By purchase order dated August 26, 1987, Georgia-Pacific ordered, among other things, an additional 222 feet of handrails pursuant to the original contract. The total additional cost of materials ordered was $31,350.00, yielding a total contract price of $232,481.00.

Southeastern contracted with AAA Steel for steel detailing and with Westside for galvanizing the fabricated steel. Westside shipped the galvanized steel directly to the worksite but sent the invoices to Southeastern for payment.

By the end of September, 1987, Southeastern had defaulted on its contracts with Georgia-Pacific, AAA Steel, and Westside. At that time, Southeastern owed $28,201.50 to Westside. Georgia-Pacific already had made substantial payments to Southeastern under its contract but withheld $43,-625.60 upon Southeastern’s default.

During late August and early September, Westside contacted Georgia-Pacific to determine whether Georgia-Pacific was paying Southeastern. Westside eventually decided to stop shipping material, but Georgia-Pacific persuaded Westside to ship what it had. Georgia-Pacific indicated that it had withheld payments from Southeastern and that it would make sure that West-side got paid. In a letter dated September 21, Georgia-Pacific informed Southeastern of the situation and indicated that no more *738 payments would be made until the problem was resolved. On September 24, Westside shipped to the worksite a final load of steel galvanized at a cost of $1,264.50. Georgia-Pacific did not pay Westside.

In order to complete the project, Georgia-Pacific purchased 478 feet of handrail from G.T. Contractors, Inc., at a cost of $23,018.03. Georgia-Pacific also paid $2,825.65 for correction of misfabrications by Southeastern.

Westside sued Georgia-Pacific in state court, seeking to establish a materialman’s lien and to claim unjust enrichment. After the action was removed to federal court, Westside amended the complaint to add Southeastern as a defendant, to claim promissory estoppel, and to request interest and attorney’s fees. Georgia-Pacific filed a cross-complaint against Southeastern, and AAA Steel intervened.

Southeastern declared bankruptcy and defaulted. After a bench trial, the district court denied Westside’s lien claim and unjust enrichment claim. The trial court’s decision is published at 724 F.Supp. 644 (W.D.Ark.1989). The court awarded $1,264.50 to Westside on its detrimental reliance claim. Id. at 647. The court held that Georgia-Pacific was entitled to a set-off against the $43,625.60 holdback in the amount of $13,893.68 ($2,825.65 for misfa-brication and $11,068.03 for additional cost of handrail over the cost of purchasing it pursuant to the Southeastern contract). Id. at 647-48. Of the remaining $29,731.92 holdback, Westside’s pro rata share was $19,757.59 and AAA Steel’s share was $9,974.33. Accordingly, the court entered a judgment of $21,022.09 ($1,264.50 plus $19,757.59) for Westside. No prejudgment interest or attorney’s fees were awarded. Westside appealed and Georgia-Pacific cross-appealed.

On appellate review, the district court’s interpretation of state law is entitled to substantial deference. See Alumax Mill Prod., Inc. v. Congress Fin. Corp., 912 F.2d 996, 1007 (8th Cir.1990); Giove v. Stanko, 882 F.2d 1316, 1319 (8th Cir.1989), cert. denied, — U.S. —, 110 S.Ct. 1812, 108 L.Ed.2d 943 (1990). Although we are not bound by the district court’s interpretation of state law, we will reverse the district court’s interpretation only if the court has misapplied the state law or the court’s interpretation is fundamentally deficient in analysis, without a reasonable basis, or contrary to a reported state court opinion. See Alumax, 912 F.2d at 1007; Bennett v. Allstate Ins. Co., 889 F.2d 776, 779 (8th Cir.1989).

The district court held that, under Arkansas law, notice must be given to a landowner before there is a delivery of materials in order for a materialman’s lien to be perfected against the land. 724 F.Supp. at 646. See Ark.Stat.Ann. § 51-608.1 (Supp.1985) (codified at Ark. Code Ann. § 18-44-115(a) (1987)). 2 A statutory exception to the notice requirement provides that no notice is necessary if the transaction is a direct sale to the property owner. Ark.Stat.Ann. § 51-608.5 (codified at Ark.Code Ann. § 18-44-115(e)). A sale is a direct sale only if the owner or his authorized agent personally orders the materials from the lien claimant. Id.

The district court observed that the Arkansas Supreme Court considers whether the material was “charged to, shipped to, and received by” the property owner and whether an invoice and monthly statement were sent to the owner in determining whether there is a direct sale. 724 F.Supp. at 646 (citing National Lumber Co. v. Advance Dev. Co., 293 Ark. 1, 732 S.W.2d 840, 846 (1987), and Duncan v. Davis & Earnest, Inc., 285 Ark. 143, 685 S.W.2d 509 (1985)). The court found that galvanized steel was shipped to and received by Georgia-Pacific, but all Westside invoices were charged to Southeastern. Id. The court held that the shipments did not amount to a direct sale since Georgia-Pacific was not the party being charged. Id. at 646-47.

We agree with the district court’s interpretation and application of the Arkansas materialman’s lien statute. The Arkansas *739 court strictly construes lien statutes since they provide an extraordinary remedy. See National Lumber, 732 S.W.2d at 846; Dews v. Halliburton Indus., Inc., 288 Ark. 532, 708 S.W.2d 67, 70 (1986).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
921 F.2d 735, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westside-galvanizing-services-inc-v-georgia-pacific-corporation-and-ca8-1991.