Westside Dixon Associates LLC v. Utah Power & Light Co.

2002 UT 31, 44 P.3d 775, 443 Utah Adv. Rep. 37, 2002 Utah LEXIS 59
CourtUtah Supreme Court
DecidedMarch 19, 2002
Docket20000731
StatusPublished
Cited by11 cases

This text of 2002 UT 31 (Westside Dixon Associates LLC v. Utah Power & Light Co.) is published on Counsel Stack Legal Research, covering Utah Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westside Dixon Associates LLC v. Utah Power & Light Co., 2002 UT 31, 44 P.3d 775, 443 Utah Adv. Rep. 37, 2002 Utah LEXIS 59 (Utah 2002).

Opinion

DURHAM, Justice.

INTRODUCTION

1 1 This case arises from the installation of a master meter for the provision of electric service by petitioner Westside Dixon Associ *777 ates, LL.C. (Westside) to its condominium units in the Broadway Lofts Building (Broadway Lofts). Westside challenges the determination of the Utah Public Service Commission (the PSC) that it was prohibited from installing a master meter under Utah Admin. Code Rule 746-210, and that no exemption applied to it under the rule. We affirm.

BACKGROUND

T2 The instant petition for review arises from the conversion of the Broadway Lofts building in downtown Salt Lake City from a warehouse into a building containing a mix of commercial and retail space on the lower level and individual residential condominium space on the upper levels. The building, originally known as the J.G. MeDonald Building, was built in 1901. In December 1999, a "gut" renovation of the Broadway Lofts was substantially completed, including the installation of separate heating and cooling systems for each unit. There is no central boiler or central chiller for the condominium units. In July, 1998, Westside, the project's developer, obtained a building permit as required by Salt Lake City to undertake the renovation.

T3 As part of the conversion of the building, Westside installed a "master meter" system for metering electrical service to the condominiums. Master metering is the practice of metering and billing the electric usage of multiple tenants or individuals through one utility meter. Westside's metering system is also "sub-metered." Sub-metering is the practice whereby the tenant or individual is metered and billed by an entity other than the utility. Westside contracted with Relms, Inc. (Relms) to provide the sub-metering and billing for the condominium owners.

T4 Douglas Marks (Marks), PacifiGorp's operations manager, testified before the PSC that PacifiCorp received two Requests for Electric Service from Westside for the provision of electricity to the Broadway Lofts, but neither requested master metering. Both requests stated that there were 101 units involved, thus suggesting that PacifiCorp would individually meter all the condominium units. While Westside contends that it submitted plans to PacifiCorp in February 1998 "showing master metering/sub metering," Westside did not introduce these plans into evidence before the Commission. Marks testified that Westside submitted an electrical site plan, but that it did not show or suggest master metering.

T5 During the construction of the condominium units at the Broadway Lofts, Pacifi-Corp supplied power to the contractor. As the project neared completion, the contractor informed Westside that arrangements for the permanent provision of electricity would have to be made. On December 10, 1999, Pacifi-Corp's attorney wrote a letter to Westside's attorney informing him that the master metering system in place at the Broadway Lofts was forbidden under the Commission's rules. PacifiCorp stated that electricity would be provided to the condominiums as long as PacifiCorp could install its own meters.

T 6 In light of Westside's refusal to permit PacifiCorp to install meters, on December 21, 1999, PacifiCorp informed Westside that power to the condominium units would be terminated on January 3, 2000. The termination was based on Westside's non-compliance with Utah Administrative Rule 746-210 and PacifiGorp's Electric Service Regulation No. 7. In response, Westside filed a Formal Complaint with the PSC on January 4, 2000. The PSC adopted the Report and Order of the administrative law judge, who found that Westside was in violation of Rule 746-210, and did not qualify for an exemption under the rule. Upon Westside's request for review, the PSC granted it a second opportunity to establish that it qualified for an exemption under Rule 746-210. Finding that Westside failed again to support its claimed entitlement to an applicable exemption, the PSC dismissed the complaint. Westside petitioned this court for judicial review.

STANDARD OF REVIEW

T7 The Utah Administrative Procedures Act, Utah Code Ann. section 63-46b-1 to -22 (1997) (UAPA), governs the appropriate standards of review of an agency determination. When reviewing an agency action that is "contrary to a rule of the agency," Utah Code Ann. § 63-46b-16(4)(h)(i), we ap *778 ply an intermediate standard of review, deferring to an agency's interpretation as long as it is both reasonable and rational. Thorup Bros. Constr. v. State Tax Comm'n, 860 P.2d 324, 327 (Utah 1993), see also SEMECO Indus. v. State Tax Comm'n, 849 P.2d 1167, 1174 (Utah 1993) (Durham, J., dissenting). This standard applies to the first issue argued as agency error by Westside, regarding the interpretation of Utah Admin.Code Rule 746-210.

18 As to the second and third claims of error, regarding the determination of whether an exemption applied to Westside according to the terms of the statute and whether or not any waiver was made, section 63-46b-16(4)(g) of UAPA is implicated. That subsection of the statute may permit granting relief to an appellant who "has been substantially prejudiced" if "the agency action is based upon a determination of fact, made or implied by the agency, that is not supported by substantial evidence when viewed in light of the whole record before the court[.]" Id. These issues are also governed by a reasonableness standard, in view of the fact that the Commission, "by virtue of its experience or expertise, is in a better position than the courts to give effect to the regulatory objective to be achieved." Morton Int'l, Inc. v. State Tax Comm'n, 814 P.2d 581, 586 (Utah 1991); SEMECO, 849 P.2d at 1172. 1

ANALYSIS

I. PUBLIC UTILITY REGULATORY POLICIES ACT

T9 Utah Administrative Code Rule 746-210, whose interpretation and application is at the heart of this dispute, is derived from the federal Public Utility Regulatory Policies Act of 1978, 16 U.S.C. section 2601-2645 (2000) et seq. (PURPA). PURPA's aims include "conservation of energy" and "optimization of the [electric utility] efficiency." 16 U.S.C. § 2611. PURPA's stance on master metering is unambiguous. It states, "to the extent determined appropriate under section 2625(d) of this title, master metering of electric service in the case of new buildings shall be prohibited or restricted to the extent necessary to carry out the purposes of this chapter." 16 U.S.C. § 2623(b)(1)(2000) (emphasis added). Section 2625(d) states:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Monticello v. Public Service Commn
2019 UT 43 (Utah Supreme Court, 2019)
Hollenbach v. Salt Lake City Corporation
2016 UT App 64 (Court of Appeals of Utah, 2016)
Kendell v. Department of Workforce Services, Workforce Appeals Board
2013 UT App 73 (Court of Appeals of Utah, 2013)
Taylorsville City v. Taylorsville City Employee Appeal Board
2013 UT App 69 (Court of Appeals of Utah, 2013)
Dorsey v. Department of Workforce Services, Workforce Appeals Board
2012 UT App 364 (Court of Appeals of Utah, 2012)
Jex v. Labor Commission
2012 UT App 98 (Court of Appeals of Utah, 2012)
Murray v. Labor Commission
2012 UT App 33 (Court of Appeals of Utah, 2012)
ABCO Enterprises v. Utah State Tax Commission
2009 UT 36 (Utah Supreme Court, 2009)
Barnard & Burk Group, Inc. v. Labor Commission
2005 UT App 401 (Court of Appeals of Utah, 2005)

Cite This Page — Counsel Stack

Bluebook (online)
2002 UT 31, 44 P.3d 775, 443 Utah Adv. Rep. 37, 2002 Utah LEXIS 59, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westside-dixon-associates-llc-v-utah-power-light-co-utah-2002.