Westmoreland-LG&E Partners v. Virginia Electric & Power Co.

39 Va. Cir. 56, 1995 Va. Cir. LEXIS 1328
CourtRichmond County Circuit Court
DecidedAugust 9, 1995
DocketCase No. LX-2859-1
StatusPublished

This text of 39 Va. Cir. 56 (Westmoreland-LG&E Partners v. Virginia Electric & Power Co.) is published on Counsel Stack Legal Research, covering Richmond County Circuit Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Westmoreland-LG&E Partners v. Virginia Electric & Power Co., 39 Va. Cir. 56, 1995 Va. Cir. LEXIS 1328 (Va. Super. Ct. 1995).

Opinion

By Judge Melvin R. Hughes, Jr.

A hearing on defendant’s Demurrer and Plea in Bar to plaintiff’s Amended Motion For Judgment was held on June 21, 1995, in this case. The Amended Motion For Judgment was filed after the court sustained defendant’s Demurrer to the original Motion For Judgment. The issue now as before is whether the plaintiff has stated a claim for payments due under the parties’ written Power Purchase and Operating Agreement (the PPO or the contract). A demurrer tests the legal sufficiency of the pleading, and for these purposes, the facts alleged are given as true which are well pleaded. Bellamy v. Gates and Gill, 214 Va. 314 (1973).

The parties, Westmoreland-LG&E Partners (WLP), plaintiff, and Virginia Electric and Power Company (Virginia Power), defendant, are electric power companies supplying power to consumers and businesses in Virginia and other places. WLP is a Virginia general partnership operating as an independent power producer. Virginia Power is a Virginia corporation operating as a publicly regulated electric utility.

The parties entered into a contract in 1989, restated in 1991, whereby WLP agreed to provide electrical power to power facilities operated by Virginia Power through North Carolina Power in North Carolina. WLP [57]*57built a power plant in North Carolina to provide the electrical power Virginia Power agreed to purchase under the contract. This plant has generated power exclusively for Virginia Power since it became operational. Essentially, under the contract WLP agreed to provide electrical power from its power plant when Virginia Power decides it is needed. WLP’s claim is that under the contract Virginia Power is liable for payment during forced outage days and seeks a money judgment for those amounts. Virginia Power’s Demurrer questions whether WLP has stated a claim under the contract, and its Plea in Bar seeks to have WLP’s claim of constructive fraud dismissed under the statue of limitations.

The Amended Motion for judgment is in three counts. The first is essentially the same contract claim made in the original motion for judgment except that the number of days for which WLP seeks payment has been increased. WLP has reasserted this claim asking the court to reconsider its ruling that as pleaded the facts alleged do not constitute a cause of action for breach. The second count is new, a claim of constructive fraud. Virginia Power asserts that the statute of limitations bars this count. The third is also a contract claim seeking payment for eight days of dependable capacity payment. WLP argues that this count is an alternative breach of contract claim which accepts the court’s prior interpretation of the parties’ contract on the first demurrer.

The court sustained the demurrer to the original motion for judgment ruling that WLP had not alleged an action for breach because by the terms of the PPO agreement Virginia Power was not obliged to make payments when WLP failed to provide dependable capacity. Dependable capacity is a rated level of electricity WLP is capable of providing. The court accepted Virginia Power’s position that section 10.15(d) of the PPO allows reduced payments even down to zero for days when plaintiff fails to deliver more than 45% of the dispatched level of power (the actual amount of power requested) according to a formula for reduction of payment provided in that section. WLP argued that payment under the PPO is due irrespective of whether capacity is actually provided. The crux of the parties’ dispute is whether WLP is entitled to payment for forced outage days, days when dependable capacity is at reduced levels. WLP maintained and still maintains by Count I that such payments are due on forced outage days. WLP cites another provision of the PPO, 10.15(g), and takes the position, contrary to the Virginia Power’s interpretation of this provision, that it is permitted a number of forced outage days without interruption of capacity payments. On the earlier ruling the court accepted Virginia [58]*58Power’s argument that 10.15(g) only applied to liquidated damages WLP is entitled to for forced outage days in excess of those allowed under the contract. As such, the court ruled this section is an independent provision of the contract determining the amount of liquidated damages as a separate matter.

The new second count alleging fraud is based on the allegation that prior to and after the execution of the PPO agreement, Virginia Power represented to WLP that capacity payments would be unaffected by forced outage days. It is alleged that it was not until 1994 that Virginia Power changed its position that the PPO did not require it to make capacity payments on forced outage days. Virginia Power argues that the two year statute of limitations in § 8.01-243(A) bars this count because WLP first knew of this inconsistency when the PPO was entered into as restated in 1991, two years beyond the filing date of this action. In addition, Virginia power states that WLP cannot have reasonably relied on any representation of how the dependable capacity payments work between the parties because WLP is fully capable of understanding the meaning of the PPO agreement. WLP has not alleged reliance before entering the contract. Lastly, this count should not proceed, according to Virginia Power, because a claim of constructive fraud cannot be sustained without an allegation of a special relationship which WLP has not pleaded.

Count III, WLP contends, accepts the basis for the first ruling and has nothing to do with the payments due for forced outage days. Thus, the liability does not arise from the application of Section 10.15(d) but arises from Virginia Power’s failure to satisfy certain contract conditions in order to be relieved of any obligation to make those payments. Section 10.15(d) is not implicated or involved in this count for damages under the parties’ contract according to WLP.

The question a demurrer raises, of course, is whether the pleading states a claim upon which relief can be granted, whether a cause of action, legally cognizable, is asserted. Lentz v. Morris, 236 Va. 78 (1988). As such, a demurrer tests the legal sufficiency of a pleading, not matters of proof. Luckett v. Jennings, 246 Va. 303 (1993). In ruling on this demurrer and the previous one, the court is free to examine not only the allegations set out in the motion for judgment but also the PPO agreement attached to it and made a part of the pleading. And while neither of the parties have challenged the court’s right to do this, the approach Virginia Power has taken in arguing its demurrer is that the contract as read does not establish a breach under the facts as a matter of contract interpretation or construe[59]*59tion. On reconsideration it is too early on demurrer for the court to get into interpreting the parties’ agreement if the motion for judgment alleges facts that would permit a recovery under the contract terms. The office of a demurrer is to only test the facts alleged as to their legal sufficiency to establish a cause of action. The question is, when stated, do the facts alleged support a claim. Here they do. WLP’s claim is that while there may be a reduction in dependable capacity during forced outage days, yet there is a right of recovery according to its view of the contract terms. To the extent of any doubt, for purposes of consideration of the demurrer, the doubt must be resolved in favor of the construction given the contract by WLP in its pleading. Fun v. Virginia Military Institute, 245 Va. 249, 253 (1993).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Doswell Ltd. Partnership v. Virginia Electric & Power Co.
468 S.E.2d 84 (Supreme Court of Virginia, 1996)
Bellamy v. Gates and Gill
200 S.E.2d 533 (Supreme Court of Virginia, 1973)
Lentz v. Morris
372 S.E.2d 608 (Supreme Court of Virginia, 1988)
Luckett v. Jennings
435 S.E.2d 400 (Supreme Court of Virginia, 1993)
Fun v. Virginia Military Institute
427 S.E.2d 181 (Supreme Court of Virginia, 1993)

Cite This Page — Counsel Stack

Bluebook (online)
39 Va. Cir. 56, 1995 Va. Cir. LEXIS 1328, Counsel Stack Legal Research, https://law.counselstack.com/opinion/westmoreland-lge-partners-v-virginia-electric-power-co-vaccrichmondcty-1995.