Western Wyoming Construction Co., Inc. v. Board of County Commissioners of Sublette County, Wyoming

2013 WY 63, 301 P.3d 512, 2013 WL 2168006, 2013 Wyo. LEXIS 67
CourtWyoming Supreme Court
DecidedMay 21, 2013
DocketS-12-0193
StatusPublished
Cited by5 cases

This text of 2013 WY 63 (Western Wyoming Construction Co., Inc. v. Board of County Commissioners of Sublette County, Wyoming) is published on Counsel Stack Legal Research, covering Wyoming Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Wyoming Construction Co., Inc. v. Board of County Commissioners of Sublette County, Wyoming, 2013 WY 63, 301 P.3d 512, 2013 WL 2168006, 2013 Wyo. LEXIS 67 (Wyo. 2013).

Opinion

KITE, Chief Justice.

[T1] Western Wyoming Construction Co., Inc. (WWC) submitted a bid for a highway project in Sublette County, Wyoming. The Board of County Commissioners of Sub-lette County (Commissioners) awarded the contract to another company whose bid was higher than WWC's, WWC filed a complaint in district court for an order awarding it the contract for the project. The Commissioners filed a motion for summary judgment which the district court granted. WWC appeals from the summary judgment order. We reverse and remand for further proceedings consistent with this opinion.

ISSUES

[12] WWC presents the issue for this Court's consideration as follows:

Whether pursuant to W.S. § 16-6-102(a) it is an abuse of discretion and, therefore, illegal for a Board of County Commissioners to refuse to award a public works contract to the lowest responsible resident bidder on the basis that the next lowest bid is not significantly higher and was submitted by a firm from the same county.

[13] The Commissioners restate the issues as follows:

1. Does a Board of County Commissioners have a right to exercise any discretion in awarding a public works contract? Subsumed within the question is the following subpart:
(a) Does Wyo. Stat. Annot. § 16-6-102(a) that allows for a 5% resident preference, foreclose the exercise of discretion in awarding a public works contract between resident bidders?
2. Was [WWC] a "responsible and responsive qualified Bidder" entitled to an award of the contract pursuant to the terms of the bid documents?

FACTS

[14] On September 6, 2011, Sublette County issued an invitation for bids for a reconstruction project on Horse Creek Road in Sublette County. WWC, a contractor based in Lander, Wyoming, submitted a bid for $4,232,854.50. The next lowest bid, submitted by a contractor based in Sublette County, was for $4,241,074.10. The County awarded the contract to the Sublette County contractor.

[15] WWC filed a complaint in the district court asserting that it had been prequal-ified by the Wyoming Department of Transportation to do the type of work required on the Horse Creek Road project and as a certified resident of Wyoming it was qualified for a five percent preference when bidding on public works projects in the State. WWC further asserted that Wyo. Stat. Ann. § 16-6-102(a) (LexisNexis 2011) mandated that the contract for the Horse Creek Road project be awarded to it because it was a responsible certified Wyoming resident and had submitted the lowest bid. Section 16-6-102(a) states in pertinent part:

§ 16-6-102. Resident contractors; preference limitation with reference to lowest bid or qualified response; ...
*514 (a) If a contract is let by ... any county ... for any public work or improvements, the contract shall be let, if advertisement for bids or request for proposal is not required, to a resident of the state. If advertisement for bids is required, the contract shall be let to the responsible certified resident making the lowest bid if the certified resident's bid is not more than five percent (5%) higher than that of the lowest responsible nonresident bidder.

[16] WWC sought an order enjoining the Commissioners from awarding the Horse Creek Road contract to any other bidder, awarding WWC the contract, and declaring WWC to be the responsible certified resident with the lowest bid and, therefore, entitled to the contract. WWC also asked the district court to find that the Commissioners breached the duty of good faith and fair dealing when they did not award the contract to the responsible certified resident with the lowest bid.

[T7] With its complaint, WWC filed a motion for temporary restraining order or preliminary injunction asking the district court to rescind any contract the Commissioners had awarded for the project. 1 The Commissioners opposed the motion elaiming, among other things, that they had reserved the right to reject any bid and had rejected WWC's bid because it did not submit a bond in the amount of ten percent of its bid as required by the bid instructions and invitation. They further asserted they awarded the contract to the second lowest bidder because it was a local contractor, its bid was only $8,000 more than WWC's and they believed it was "in the best interest of the project to support the local economy by awarding the project to [the second lowest bidder]."

The district court convened a hearing and heard the parties' arguments for and against the motion. It subsequently issued a decision denying the motion for temporary relief. Based upon the testimony and evidence presented, the district court concluded it did not have the authority to require the Commissioners to contract with WWC or to prevent them from contracting with another bidder; the record was insufficient to show whether the contract awarded or WWC's bid were valid or invalid; and WWC had failed to demonstrate that it was entitled to a temporary restraining order or injunctive relief. The district court subsequently entered an order consistent with its decision.

[19] The Commissioners then filed a motion for summary judgment asking for judgment as a matter of law on all of WWC's claims. WWC also filed a motion seeking partial summary judgment on its claim for breach of the covenant of good faith and fair dealing. After a hearing on the motions, the district court granted the Commissioners' motion. The district court entered an order reaffirming its prior ruling on WWC's claims for a temporary restraining order or injune-tive relief. The district court also held there was no contract between WWC and the Commissioners to support the claim for breach of the covenant of good faith and fair dealing. Finally, the district court denied WWC's claim for declaratory relief finding that the Commissioners did not act illegally, arbitrarily or capriciously in awarding the contract to the second lowest bidder. Rather, the court concluded, the Commissioners made a legitimate executive decision to award the contract to a company other than WWC. WWC timely appealed the district court's order.

STANDARD OF REVIEW

[110] We review a district court's order on summary judgment de novo. Carnahan v. Lewis, 2012 WY 45, ¶ 10, 273 P.3d 1065, 1070 (Wyo.2012).

DISCUSSION

[111] WWC contends that § 16-6-102(2) required the Commissioners to award the Horse Creek Road contract to the responsible certified Wyoming resident making the lowest bid. Because it was the responsible certified resident that submitted the lowest *515 bid, WWC asserts the Commissioners acted in contravention of the statute when they awarded the contract to a contractor that submitted a higher bid. WWC contends § 16-6-102 was intended to prohibit counties from creating their own preference system for local contractors. In support of its argument, WWC cites Green River v. DeBernardi, 816 P.2d 1287 (Wyo.1991).

[112] In DeBernardi, the City of Green River published notice for bids for a project involving the installation of a water main. Id.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
2013 WY 63, 301 P.3d 512, 2013 WL 2168006, 2013 Wyo. LEXIS 67, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-wyoming-construction-co-inc-v-board-of-county-commissioners-of-wyo-2013.