Western Watersheds Project v. United States Department of the Interior

677 F.3d 922, 2012 WL 1416087, 2012 U.S. App. LEXIS 8292
CourtCourt of Appeals for the Ninth Circuit
DecidedApril 25, 2012
Docket10-35836
StatusPublished
Cited by18 cases

This text of 677 F.3d 922 (Western Watersheds Project v. United States Department of the Interior) is published on Counsel Stack Legal Research, covering Court of Appeals for the Ninth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Watersheds Project v. United States Department of the Interior, 677 F.3d 922, 2012 WL 1416087, 2012 U.S. App. LEXIS 8292 (9th Cir. 2012).

Opinion

OPINION

SCHROEDER, Circuit Judge:

The Government appeals from an award of attorneys’ fees to a plaintiff conservation group in a long-running dispute involving federal grazing permits in Idaho. Plaintiff-Appellee conservation group is Western Watersheds Project (‘WWP”) and the permits were issued by Defendant-Appellant U.S. Department of the Interior. The issue is whether the district court properly awarded fees to WWP for legal work done in the administrative proceedings conducted before the civil litigation in which the district court held that the Interior Board of Land Appeals (“IBLA”) had acted arbitrarily and capriciously in upholding the Government’s award of some of the grazing permits.

The precise legal issue concerns the interpretation of the U.S. Supreme Court’s decision in Sullivan v. Hudson, 490 U.S. 877, 109 S.Ct. 2248, 104 L.Ed.2d 941 (1989), and whether it permits an award of fees under 28 U.S.C. § 2412(d)(1)(A) to a prevailing party in district court for the work done in the administrative proceedings that preceded the district court action. Here, the district court awarded the fees because it concluded that the administrative proceedings were closely tied to its own resolution of the issues. Although the Government did not extensively argue its position on statutory interpretation before the district court, it contends more fully and persuasively to us that the fees awarded under § 2412(d)(1)(A) should not have included fees for the administrative proceedings. This is because fees for administrative proceedings can be awarded under § 2412(d)(1)(A) only when the proceedings have been ordered in a district court action that remains pending until the conclusion of the administrative proceedings. Hudson, 490 U.S. at 892, 109 S.Ct. 2248. That was the situation in Hudson, but that is not the situation here, where the district court action was not filed until after the administrative proceedings had concluded.

*924 We therefore must vacate the fee award and remand for the district court to reduce the award by the amount that represents fees incurred in the administrative proceedings.

BACKGROUND

The chronology of the underlying dispute over grazing permits is important to understanding the relationship between the administrative permit proceedings and the civil litigation in district court that followed them, and in which the fees at issue were awarded. The seeds of this fee dispute were sown in 1997, when WWP filed an action in Idaho district court challenging the Bureau of Land Management’s (“BLM”) issuance of grazing permits to cattle ranchers for 68 public land allotments in the Owyhee Resource Area in Southwestern Idaho. See Idaho Watersheds Project v. Hahn, 307 F.3d 815, 820- 21 (9th Cir.2002), abrogated on other grounds by Winter v. Nat. Res. Def. Council, Inc., 555 U.S. 7, 29-31, 129 S.Ct. 365, 172 L.Ed.2d 249 (2008).

In that case, the district court held in February 2000 that the BLM had violated the National Environmental Policy Act (“NEPA”), Pub.L. 91-190, 83 Stat. 852 (1969) (codified as amended in 42 U.S.C.), and the court granted WWP’s request for a permanent injunction. Id. at 820, 823. The injunction required the BLM to conduct, within a set schedule, a new NEPA analysis. Id. at 823. In conducting the new analysis, the BLM found that its grazing management policies in the Nickel Creek allotments, a portion of the 68 allotments in the Owyhee Resource Area, failed to meet any of the applicable range-land health standards. The BLM sought to address this problem (and meet its obligation under the injunction) in its 2003 Final Decision for the Nickel Creek allotments. The BLM supported the Final Decision with an Environmental Assessment (“EA”) and a Finding of No Significant Impact (“FONSI”), pursuant to NEPA, see 42 U.S.C. §§ 4321-4347. The Final Decision provided for ten-year grazing permits that would incorporate a grazing rotation schedule and eight management guidelines necessary to improve rangeland health conditions. The management guidelines, however, were not mandatory.

WWP promptly, and not surprisingly, filed an administrative appeal in December 2003 with the Department of Interior Office of Hearings and Appeals, challenging the BLM’s Final Decision. The administrative law judge (“ALJ”) held a fifteen-day evidentiary hearing, at which the parties presented over a dozen witnesses and hundreds of exhibits. On September 28, 2007, the ALJ issued a lengthy opinion in WWP’s favor. The ALJ found that the BLM “failed to comply with the grazing regulations on the fundamentals of range-land health, and failed to comply with [NEPA].” The Government appealed the ALJ’s decision to the IBLA, and in December 2008, the IBLA reversed the ALJ’s rulings. The IBLA held that the 2003 Final Decision did not violate NEPA, and, because it would make significant progress in improving allotment conditions, it did not violate the Fundamentals of Rangeland Health Regulations, see 43 C.F.R. § 4180.

WWP then sought judicial review in district court under the Administrative Procedure Act (“APA”), 60 Stat. 237 (1946) (codified as amended at 5 U.S.C.), arguing that the IBLA’s decision was arbitrary and capricious. The district court in December 2009 granted partial summary judgment for WWP, finding that the IBLA’s decision was arbitrary and capricious because it had, without any explanation, reversed the ALJ’s determination that the *925 BLM’s 2003 Final Decision violated the Fundamentals of Rangeland Health Regulations. The district court remanded the matter to the BLM with instructions to include the management guidelines as mandatory terms and conditions of the permits and to render a new decision on the Nickel Creek allotments. The Government did not appeal to this court.

The controversy then shifted to fees. WWP timely moved for an award of attorneys’ fees and expenses under the Equal Access to Justice Act (“EAJA”), Pub.L. 96-481, 94 Stat. 2325 (1980) (codified in scattered sections of 5, 15, 28, and 42 U.S.C.). WWP requested fees pursuant to 5 U.S.C. § 504 and 28 U.S.C. § 2412(d) for the administrative appeals and district court proceedings, in which it had challenged the BLM’s 2003 Final Decision for the Nickel Creek allotments. The Government conceded that WWP was the prevailing party and under § 2412(d)(1)(A) was entitled to reasonable fees and costs incurred in district court, but argued that WWP was not entitled to fees under either § 504 or § 2412(d) for the administrative proceedings.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
677 F.3d 922, 2012 WL 1416087, 2012 U.S. App. LEXIS 8292, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-watersheds-project-v-united-states-department-of-the-interior-ca9-2012.