Western Surety Company v. U.S. Engineering Company

211 F. Supp. 3d 302, 2016 U.S. Dist. LEXIS 135539
CourtDistrict Court, District of Columbia
DecidedSeptember 30, 2016
DocketCivil Action No. 2015-0327
StatusPublished
Cited by5 cases

This text of 211 F. Supp. 3d 302 (Western Surety Company v. U.S. Engineering Company) is published on Counsel Stack Legal Research, covering District Court, District of Columbia primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Surety Company v. U.S. Engineering Company, 211 F. Supp. 3d 302, 2016 U.S. Dist. LEXIS 135539 (D.D.C. 2016).

Opinion

MEMORANDUM OPINION

TANYA S. CHUTEAN, United States District Judge

Plaintiff Western Surety Company brought this suit for declaratory and in-junctive relief seeking to enjoin Defendant U.S. Engineering Company from compelling arbitration proceedings against Plaintiff and making a claim on a surety bond issued by Plaintiff. Defendant has filed a motion to dismiss under Rule 12(b)(6), arguing that the parties are contractually bound to arbitrate their dispute over the bond. Plaintiff responded by filing a motion for partial summary judgment solely on the issue of whether it must arbitrate its dispute with the Defendant. For the reasons stated herein, Defendant’s motion will be DENIED, and Plaintiffs motion will be GRANTED.

I. BACKGROUND

On January 25, 2012, Turner Construction and Defendant entered into a contract for Defendant to perform construction and renovation work at the South African Embassy in Washington, D.C. (ECF No. 16, PI. Statement of Facts (“SOF”) ¶ 1). Defendant then awarded a subcontract for sheet metal work on the project to United Sheet Metal, Inc. {Id. ¶ 2). The subcontract contains the following provisions that are pertinent for the pending motions:

• The introductory paragraph identifies U.S. Engineering as the “Contractor” for purposes of the contract, who enters into a “subcontract” with United Sheet Metal.
• Paragraph 26, which is entitled “Arbitration,” states:
Any controversy or claim of Contractor against Subcontractor or Subcontractor against Contractor shall be resolved by arbitration pursuant to the Construction Industry Arbitration Rules of the American Arbitration Association in effect on the date on which the demand for arbitration is made
[[Image here]]
• Paragraph 31, the Merger Clause, integrates the prior communications and representations “between Contractor and Subcontractor,” and notes that the subcontract is the “final and complete agreement between Contractor and Subcontractor.”

(PI. Ex. 1).

After entering into the subcontract with Defendant, United Sheet Metal negotiated *305 with Plaintiff to issue a surety bond for $585,000. (PI. Ex. 2). Under the terms of the surety bond:

• United Sheet Metal is named as the “Contractor,” Plaintiff is the “Surety,” and Defendant is the “Owner.” (PI. Ex. 2 at p. 1).
• “The Contractor and Surety [Plaintiff], jointly and severally, bind themselves, their heirs, executors, administrators, successors and assigns to the Owner [Defendant] for the performance of the Construction Contract, which is incorporated herein by reference.” (Id. § 1).
• “Any proceeding, legal or equitable, under this Bond may be instituted in any court of competent jurisdiction in the location in which the work or part of the work is located ...”

(PI. Ex. 2, §§ 15,1,11.)

In early 2013, a dispute over the performance of the subcontract arose between Defendant and United Sheet Metal, which led to Defendant terminating the subcontract. (PI. SOF ¶¶ 11-12). Defendant hired a replacement subcontractor to finish the sheet metal work, and United Sheet Metal sought to compel arbitration, seeking $331,242 in damages. (Id. ¶¶ 13-14). Defendant filed a counterclaim for $417,379 in damages. (Id. ¶ 14). The arbitration proceedings between Defendant and United Sheet Metal have not concluded. (Id. ¶ 15).

On June 9, 2014, Plaintiff received a letter from Defendant stating that it had terminated United Sheet Metal’s performance of the subcontract, and that Defendant intended to make a claim under the surety bond. (Id. ¶ 16). On March 4, 2015, Defendant filed a request to join Plaintiff as a party in Defendant’s arbitration proceedings with United Sheet Metal. (Id. ¶ 18). Plaintiff refused to consent to the joinder, and instead filed its Complaint in this court on March 6, 2015. (See id. ¶ 19).

Defendant argues that because the bond agreement incorporates the subcontract by reference, Plaintiff is bound by the arbitration clause in the subcontract to arbitrate its claim on the surety bond, as well as any issues of arbitrability. Plaintiff asserts that it never consented to arbitration, and that it is impossible to interpret the text of the bond or the subcontract to bind Plaintiff to the arbitration clause.

II. STANDARD OF REVIEW

Though Defendant’s motion is styled as a motion to dismiss, a motion that seeks to compel or preclude arbitration is evaluated under the summary judgment standard “as if it were a request for ‘summary disposition of the issue of whether or not there had been a meeting of the minds on the agreement to arbitrate.’” Aliron Int’l, Inc. v. Cherokee Nation Indus., Inc., 531 F.3d 863, 865 (D.C. Cir. 2008) (internal quotation marks omitted); see also W & T Travel Servs., LLC v. Priority One Servs., Inc., 69 F.Supp.3d 158, 164 (D.D.C. 2014) (“Both motions to stay and compel arbitration focus judicial scrutiny on the arbitrability of the dispute, rather than the dispute itself and, when both motions are made concurrently, they may be addressed together as cross-motions for summary judgment.”), appeal dismissed, No. 14-7152, 2015 WL 7693578 (D.C. Cir. Nov. 2, 2015).

Summary judgment is appropriate where there is no disputed genuine issue of material fact, and the movant is entitled to judgment as a matter of law. Fed. R. Civ. P. 56(a); Celotex Corp. v. Catrett, 477 U.S. 317, 325, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). In determining whether a genuine issue of material fact exists, the court must view all facts in the light most favorable to the non-moving party. See Matsushita Elec. Indus. Co. v. Zenith Radio *306 Corp., 475 U.S. 574, 587, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986). The moving party bears the “initial responsibility of informing the district court of the basis for its motion, and identifying those portions of the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits ... which it believes demonstrate the absence of a genuine issue of material fact.” Celotex Corp., 477 U.S. at 323, 106 S.Ct. 2548 (internal quotation marks omitted). The nonmoving party, in response, must “go beyond the pleadings and by [its] own affidavits, or by the depositions, answers to interrogatories, and admissions on file, designate specific facts showing that there is a genuine issue for trial.” Id. at 324, 106 S.Ct.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
211 F. Supp. 3d 302, 2016 U.S. Dist. LEXIS 135539, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-surety-company-v-us-engineering-company-dcd-2016.