Western Surety Co. v. Alliance Steel Construction, Inc.

487 F. Supp. 2d 1041, 2007 U.S. Dist. LEXIS 38845, 2007 WL 1536881
CourtDistrict Court, W.D. Wisconsin
DecidedMay 24, 2007
Docket06-C-326-C
StatusPublished

This text of 487 F. Supp. 2d 1041 (Western Surety Co. v. Alliance Steel Construction, Inc.) is published on Counsel Stack Legal Research, covering District Court, W.D. Wisconsin primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Surety Co. v. Alliance Steel Construction, Inc., 487 F. Supp. 2d 1041, 2007 U.S. Dist. LEXIS 38845, 2007 WL 1536881 (W.D. Wis. 2007).

Opinion

OPINION AND ORDER

CRABB, District Judge.

Defendant Alliance Steel Construction, Inc. had a contract with the Army Corps of Engineers to build a dining facility. Defendant subcontracted much of the work to third-party defendant Westra Construction, Inc., which failed to finish the project on time. As a result, defendant withheld approximately $263,000 of the balance owed on the contract, claiming expenses incurred by the delay as well as lost profits.

Third-party defendant Westra assigned its rights under the contract to plaintiff Western Surety Company, which is suing defendant for the amount that remains unpaid. The parties are of diverse citizenship and the amount in controversy is greater than $75,000, providing a basis to exercise jurisdiction under 28 U.S.C. § 1332(a). Now before the court is plaintiffs motion for partial summary judgment. Plaintiff concedes that there is a genuine factual dispute regarding the expenses defendant says it incurred because of the delay. However, because I agree with plaintiff that the contract does not permit recovery of lost profits, I will grant plaintiffs motion for partial summary judgment.

From the parties’ proposed findings of fact and the record, I find the following facts to be undisputed.

UNDISPUTED FACTS

Plaintiff Western Surety Company’s state of incorporation and the location of its principal place of business is South Dakota; Wisconsin is the state of incorporation for defendant Alliance Steel Construction, Inc. and location of its principal place of business. (Neither side proposes facts about third-party defendant Westra Construction, Inc.’s citizenship, which has *1043 not yet made an appearance in the case and may no longer be in existence. In any event, even if a third-party defendant’s citizenship is the same as another party’s, it does not eliminate diversity jurisdiction. HB General Corp. v. Manchester Partners, L.P., 95 F.3d 1185, 1197 (3d Cir.1996).)

In 2003 defendant entered into a contract with the Army Corps of Engineers that was related to a construction project for a dining facility at Fort McCoy in Monroe County, Wisconsin. Defendant subcontracted much of this work to third-party defendant Westra Construction, Inc. for $2,928,160. Defendant’s agreement with third-party defendant Westra includes the following provisions:

The Subcontractor [third party defendant Westra] agrees as follows:
5. To pay for any expense the Contractor [defendant] may suffer as a result of the Sub-Contractor’s failure to carry out the provisions of this agreement.
10. To be bound to the Contractor by the terms of the general conditions of the specifications, special provisions and addenda, and to conform to and comply with the drawings and specifications, special and addenda, to furnish such shop drawings or samples as may be required and to assume toward the Contractor all the obligations and responsibilities that the Contractor assumes in and by the aforesaid documents toward the Owner [the Army Corps of Engineers], in so far as they are applicable to this particular contract.
15. That in case the Sub-contractor [third-party defendant Westra] shall fail to correct, replace and/or reexecute faulty or defective work done and materials furnished under this contract, when and as required by the Contractor [defendant], or shall fail to complete or diligently proceed with this contract within the time herein provided for, the Contractor upon three days’ written notice to the Sub-contractor shall have the right to correct, replace and/or re-execute such faulty or defective work, or to take over this contract and complete same, and to charge the cost thereof to the Sub-Contractor, together with any liquidated damages caused by a delay in the performance of this contract.

After entering into the subcontract with defendant, third-party defendant Westra issued two bonds for$2,858,160, naming plaintiff as surety, defendant as obligee and itself as principal. Plaintiff entered into a “general agreement of indemnity” with third-party defendant Westra under which Westra assigned its rights under the contract to plaintiff.

The Corps set October 27, 2004 as the completion date for the construction project, but the Corps did not consider the project “substantially complete” until January 31, 2005. As a result, the Corps assessed $75,050 in liquidated damages against defendant. In turn, third-party defendant Westra paid defendant $73,470 in liquidated damages through a reduction of its invoices.

The Corps later issued a performance evaluation of “unsatisfactory” to defendant and third-party defendant Westra. As a result of the evaluation, defendant estimates its future lost profits to be $864,510.

In July 2005, third-party defendant Westra notified plaintiff that it was ceasing all operations. Pursuant to its rights as surety and assignee under the “general indemnity agreement,” plaintiff sought payment from defendant for the remaining balance on defendant’s contract with Wes- *1044 tra, which was $262,845.04. Defendant has not paid any of that amount. Defendant alleges that it incurred $151,979.05 in expenses as a result of the delay in completing the project.

Defendant never terminated its agreement with third-party defendant Westra.

OPINION

I begin with the issues on which the parties agree for the purpose of plaintiffs motion for partial summary judgment. They agree that third-party defendant Westra did not complete the construction project on the date it was required by contract, that Westra paid approximately $73,000 to defendant in liquidated damages as a result of the delay and that approximately $263,000 remains unpaid on defendant’s contract with Westra. In addition, the parties agree that Wisconsin law applies to the dispute and that, as Westra’s assignee, plaintiff stands in the shoes of Westra for the purpose of collecting any unpaid balances on defendant’s contract with Westra.

The sole question raised by plaintiffs motion for partial summary judgment is whether defendant was entitled to deduct its future lost profits from the remaining balance of $263,000. As every law student knows from reading Hadley v. Baxendale, 9 Ex. 341, 156 Eng. Rep. 145 (1854), lost profits may be recovered in some instances if they were foreseeable by the breaching party and if the amount of lost profits is reasonably certain. See also Lindevig v. Dairy Equipment Co., 150 Wis.2d 731, 740, 442 N.W.2d 504, 508 (Ct.App.1989) (reasonably certain); Reiman Assocs., Inc. v. R/A Advertising, Inc., 102 Wis.2d 305, 320-22, 306 N.W.2d 292, 300-01 (Ct.App.1981) (foreseeable). Most of defendant’s brief is devoted to attempting to demonstrate these elements.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Lindevig v. Dairy Equipment Co.
442 N.W.2d 504 (Court of Appeals of Wisconsin, 1989)
Just v. Land Reclamation Ltd.
456 N.W.2d 570 (Wisconsin Supreme Court, 1990)
Estate of Matteson v. Matteson
2007 WI App 23 (Court of Appeals of Wisconsin, 2007)
Campion v. Montgomery Elevator Co.
493 N.W.2d 244 (Court of Appeals of Wisconsin, 1992)
Reiman Associates, Inc. v. R/A Advertising, Inc.
306 N.W.2d 292 (Court of Appeals of Wisconsin, 1981)
Dykstra v. Arthur G. McKee & Co.
284 N.W.2d 692 (Court of Appeals of Wisconsin, 1979)
Dykstra v. Arthur G. McKee & Co.
301 N.W.2d 201 (Wisconsin Supreme Court, 1981)
Just v. Land Reclamation, Ltd.
461 N.W.2d 447 (Wisconsin Supreme Court, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
487 F. Supp. 2d 1041, 2007 U.S. Dist. LEXIS 38845, 2007 WL 1536881, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-surety-co-v-alliance-steel-construction-inc-wiwd-2007.