Western Shale Products Co. v. City of Fort Scott

266 P.2d 327, 175 Kan. 643, 1954 Kan. LEXIS 332
CourtSupreme Court of Kansas
DecidedJanuary 23, 1954
Docket39,166
StatusPublished
Cited by13 cases

This text of 266 P.2d 327 (Western Shale Products Co. v. City of Fort Scott) is published on Counsel Stack Legal Research, covering Supreme Court of Kansas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Shale Products Co. v. City of Fort Scott, 266 P.2d 327, 175 Kan. 643, 1954 Kan. LEXIS 332 (kan 1954).

Opinions

The opinion of the court was delivered by

Wedell, J.:

Two actions were consolidated for trial in the district court. They have not been tried. The plaintiff appeals from intermediate orders involving pleadings.

We shall continue to refer to Western. Shale Products Company, as the plaintiff, and to the defendant, the city of Fort Scott, as the city.

This is the second chapter in this controversy. On a previous appeal by plaintiff it was held a ruling to consolidate actions under G. S. 1949, 60-765 and a ruling denying plaintiff’s motion to dismiss the city’s appeal from a condemnation award were not appealable orders. (Western Shale Products Co. v. City of Fort Scott, 172 Kan. 336, 239 P. 2d 828.) Those questions are not raised now and form no part of the instant appeals;

In order, however, to avoid confusion concerning statements in our own reports it should be stated the pleadings were amended at least in part after our former decision.

[645]*645Before treating the orders involved in this appeal a general statement may be helpful. On September 5, 1950, the city, pursuant to an extensive sewer development project, entered upon and laid a sewer line on plaintiff’s property without first instituting condemnation proceedings therefor. On October 16, 1950, plaintiff filed an action against the city for damages alleged to have been done to its property in laying the sewer line and prayed judgment in the sum of $15,869.00. On November 22, 1950, the city filed a petition for the condemnation of a strip of land fifty feet wide for an easement, the strip to be twenty-five feet on each side of the center line of the sewer, which it had previously laid. The commissioners appraised the land to be condemned at $5,534.17 and the city appealed from the award. The' court thereupon consolidated plaintiff’s damage action and the condemnation appeal over plaintiff’s objection. It appears thereafter separate pleadings, although many of them are the same or substantially so, were filed in each action which was separately numbered.

On May 29, 1952, plaintiff filed its second amended petition in the damage action in which it then sought recovery of $5,600. On the same day plaintiff filed its so-called second amended “bill of particulars” in the action denominated by the parties as the condemnation case. The latter was framed as two causes of action. Plaintiff sought recovery of damages in the sum of $5,600 in the first cause of action and $5,534.17 in the second, the latter being the amount at which the land taken was appraised by the commissioners in the condemnation proceeding.

On October 24, 1952, the city responded separately to plaintiff’s pleading in each case. In the damage action the city filed an answer containing, among other things, a general denial of all matters not admitted by it. The admissions are not material here. In the condemnation case it filed a joint answer and demurrer to both causes of action contained in plaintiff’s so-called second amended bill of particulars. This answer, among other things, also contained a general denial of all matters not admitted by the city. The answer in the damage action was made a part of this answer in the condemnation case. It is four adverse rulings pertaining to this answer of the city in the condemnation case, the character of which rulings will be noted later, that form one part of plaintiff’s appeal. It will be helpful, by reason of plaintiffs later contentions, to observe the general nature of the city’s answer.

[646]*646On April 7, 1953, the city filed a second amended cross petition in the damage action. In this cross petition it, in substance, alleged:

On or about June 13, 1932, it was the owner of a sewer line lawfully placed on the property of the Missouri, Kansas and Texas Railway Company and in Walker and Mulberry streets of the city and along the.south side of the right of way of the Missouri, Kansas and Texas Railway Company, which adjoined real estate owned and used by the plaintiff; plaintiff engaged in blasting operations on its own land and removed large quantities of shale from its own land onto the sewer line of the city to such a depth that the overburden crushed and broke the sewer line; the blasting by plaintiff and the overburden plaintiff placed on the city’s sewer line crushed and broke it; the overburden on its sewer line extended to a depth of forty or fifty feet and the city could not with reasonable expense dig down and through the overburden to repair the crushed sewer line; it was necessary to construct approximately 1,000 feet of new sewer to replace the one negligently and unlawfully buried by plaintiff; the lowest bid for constructing the new sewer line in 1932 or the early part of 1933 was $2,379.50 for which the city sought damages from the plaintiff.

It is from an adverse ruling on plaintiff’s demurrer to this cross-petition of the city that plaintiff also appeals.

One thing is entirely clear. It is that these pleadings are thoroughly confusing. That is especially true in view of the cross references to pleadings in the respective actions and with general denials contained in many of them. In order to avoid additional confusion it should be borne in mind that the effect of a consolidation of actions under G. S. 1949, 60-765 is to unite and merge all of the different actions consolidated into a single action for the purpose of all future proceedings the same as if the different causes of action involved had been joined in a single action. (Wentworth v. First Trust Co., 147 Kan. 466, 470, 77 P. 2d 976.) So construed we have here what is essentially a damage action by plaintiff against the city and a damage action by the city against plaintiff, with a condemnation proceeding involved in the pleadings.

We shall first consider the city’s contention plaintiff’s appeal from the order overruling its demurrer to the city’s second amended cross petition in the damage action should be dismissed. An answer to that contention requires a review of the proceedings previous to the [647]*647order from which the appeal is taken. On November 5, 1952, the court overruled plaintiff’s original demurrer to the city’s cross petition in the damage action. The next step by the plaintiff was irregular in that it filed a motion to make the cross petition definite and certain after plaintiff’s demurrer to the original cross petition had been overruled. The district court, however, considered the motion and sustained eight grounds thereof and overruled two of them. On December 31, 1952, the city filed an amended cross petition. On March 11, 1953, plaintiff filed a motion to strike the first amended cross petition for the city’s failure to comply with the court’s previous order to make its original petition definite and certain. On April 7, 1953, the city filed its second amended cross petition without waiting for a ruling on plaintiff’s motion to strike its first amended petition. On April 11, 1953, plaintiff demurred to the second amended cross petition. This demurrer was identical with the first demurrer to the original petition except that the last demurrer included the ground of laches. The last demurrer was overruled on April 28, 1953. Plaintiff appealed from this last ruling on May 8, 1953. That appeal was, therefore, within two months from the date of the ruling on the last demurrer and was in time. (G. S. 1949, 60-3309.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

State Highway Commission v. Steele
528 P.2d 1242 (Supreme Court of Kansas, 1974)
Gardner v. Pereboom
398 P.2d 293 (Supreme Court of Kansas, 1965)
Mayfield v. Hesston Manufacturing Co.
353 P.2d 789 (Supreme Court of Kansas, 1960)
Rockhill, Administrator v. Tomasic
352 P.2d 444 (Supreme Court of Kansas, 1960)
Schindler v. Ross
320 P.2d 813 (Supreme Court of Kansas, 1958)
Smith v. Wright
305 P.2d 810 (Supreme Court of Kansas, 1957)
Bortzfield v. Sutton
299 P.2d 584 (Supreme Court of Kansas, 1956)
Foster v. Humburg
299 P.2d 46 (Supreme Court of Kansas, 1956)
Brewer v. Hearne Motor Freight Lines, Inc.
297 P.2d 1108 (Supreme Court of Kansas, 1956)
Standard Steel Works v. Crutcher-Rolfs-Cummings, Inc.
269 P.2d 402 (Supreme Court of Kansas, 1954)
Western Shale Products Co. v. City of Fort Scott
266 P.2d 327 (Supreme Court of Kansas, 1954)

Cite This Page — Counsel Stack

Bluebook (online)
266 P.2d 327, 175 Kan. 643, 1954 Kan. LEXIS 332, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-shale-products-co-v-city-of-fort-scott-kan-1954.