Western Pennsylvania Water Co. v. Commonwealth

560 A.2d 905, 127 Pa. Commw. 26, 104 Oil & Gas Rep. 403, 1989 Pa. Commw. LEXIS 438
CourtCommonwealth Court of Pennsylvania
DecidedJune 21, 1989
Docket2285 C.D. 1988
StatusPublished
Cited by3 cases

This text of 560 A.2d 905 (Western Pennsylvania Water Co. v. Commonwealth) is published on Counsel Stack Legal Research, covering Commonwealth Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Pennsylvania Water Co. v. Commonwealth, 560 A.2d 905, 127 Pa. Commw. 26, 104 Oil & Gas Rep. 403, 1989 Pa. Commw. LEXIS 438 (Pa. Ct. App. 1989).

Opinion

COLINS, Judge.

Western Pennsylvania Water Company (WPW) petitions for review of an order of the Environmental Hearing Board (Board) dated August 25, 1988 which denied the Department of Environmental Resources’ (DER) Motion for Summary Judgment and denied WPW’s appeal from DER’s order of September 13, 1988.

WPW is a Pennsylvania corporation which sells drinking water to customers in Washington County. In May, 1983, WPW acquired a twenty-foot wide permanent easement and right-of-way across the property of Leah Bellaire in order to extend its distribution system in McDonald Borough, Washington County. Mrs. Bellaire’s property is located near the center of an active oil field discovered in the 1890’s.

On November 10, 1983, during excavations and pipe laying activities on the easement, Alex Paris Contracting Co., a contractor hired by WPW, encountered an abandoned oil well about one and one-half feet below the ground surface. 1 At the same time, a greenish substance determined to be *28 crude oil seeped into the trench that they were digging. DER oil and gas inspectors visited the site of the abandoned oil well on November 11, 13 and 14, 1983 at which time they instructed WPW to collect the oil, gather up the contaminated soil and have it properly disposed of but not to cover the abandoned well. Paris employees pumped the water and oil from the open trench into a 500 gallon tank over a three to four week period subsequent to the incident. The portion of the mixture deemed to be water was drained out of the tank on to the ground surface. The contaminated soil was removed from the trench and placed on to a pile seven to eight feet high on the adjacent grounds. The trench was then completely backfilled, covering over the abandoned well.

DER issued an order to WPW on September 13, 1984, pursuant to Sections 5, 316, 402 and 610 of what is commonly referred to as the Clean Streams Law, Act of June 22, 1937, P.L.1987, as amended, 35 P.S. §§ 691.5, 691.316, 691.402 and 691.610; Sections 502 and 503 of the Gas Operations, Well-Drilling Petroleum and Coal Mining Act, Act of November 30, 1955, P.L. 756, as amended, (Gas Operations Law), 52 P.S. §§ 2502 and 2503, repealed by Section 606(a) of the Act of December 19, 1984, P.L. 1140; 2 Sections 104(7) and 602 of the Solid Waste Management Act, Act of July 7, 1980, P.L. 380, as amended, (SWMA), 35 P.S. §§ 6018.104(7) and 6018.602; and Section 1917-A of the Administrative Code of 1929, Act of April 9, 1929, P.L. 177, as amended, added by Section 20 of the Act of December 3, 1970, P.L. 834, 71 P.S. § 510-17. This order directed WPW to: (1) within thirty days file with the Bureau of Oil and Gas Management a notice of intent to plug the well and a plat of the abandoned oil well pursuant to Section 205 of the Gas Operations Law, 52 P.S. § 2205; 3 (2) within thirty days *29 of filing the notice of intent to plug the well and a plat, to plug the well in accordance with Section 206(c) of the Gas Operations Law, 52 P.S. § 2206(c); (3) submit a plan within thirty days to the Bureau of Oil and Gas Management setting forth the measures WPW will take to prevent the occurrence of such pollutional incidents in the future and measures WPW will take should such a pollutional event occur; (4) within thirty days, submit to the Bureau of Solid Waste Management an ER-SWM-14 request for approval for disposal of a solid waste for the disposal of the contaminated soil in an approved landfill and within twenty-one days of written department approval, dispose of the contaminated soil in the approved landfill; and (5) within forty-five days, submit to the Department for its approval a report prepared by a hydrogeologist determining the extent of ground water contamination in the vicinity of the oil well and the Hi-View water well, 4 and proposing abatement measures, and a schedule for implementation.

WPW appealed that order to the Board on October 15, 1984. On December 11, 1985, DER filed a Motion for Summary Judgment with respect to WPW’s liability under Section 316 of the Clean Streams Law. On January 10, 1986, the Board ruled that any evidence bearing on foreseeability or negligence with respect to WPW’s excavation activity would be excluded at the forthcoming hearing as irrelevant pursuant to National Wood Preservers, Inc. v. Department of Environmental Resources, 489 Pa. 221, 414 A.2d 37 (1980). A hearing on the merits was held before the Board on January 21 through January 23, 1986. The Board issued an Adjudication and Order on August 25, 1988 which denied DER’s Motion for Summary Judgment and denied WPW’s appeal from the September 13, 1984 *30 order of DER. WPW now petitions this Court for review of the August 25, 1988 order.

We must affirm the Board unless we determine that an error of law has been committed, constitutional rights have been violated, or that necessary factual findings are not supported by substantial evidence. Section 704 of the Administrative Agency Law, 2 Pa.C.S. § 704; Pennsylvania Game Commission v. Department of Environmental Resources, 97 Pa.Commonwealth Ct. 78, 509 A.2d 877 (1986), aff'd, 521 Pa. 121, 555 A.2d 812 (1989).

WPW first argues that as an easement holder, its interest in the real property is not sufficient to render it an occupant within the meaning of Section 316 of the Clean Streams Law, 35 P.S. § 691.316. We disagree. That section provides in pertinent part:

Whenever the department [DER] finds that pollution or a danger of pollution is resulting from a condition which exists on land in the Commonwealth the department may order the landowner or occupier to correct the condition in a manner satisfactory to the department____ For the purpose of this section, ‘landowner’ includes any person holding title to or having a proprietary interest in either surface or subsurface rights.

(Emphasis added.)

The Board held that a permanent easement for the installation of a water pipe line is a sufficient interest 5 in land to bring the owner of the easement within the scope of Section 316 of the Clean Streams Law. WPW maintains that its easement is a limited purpose right-of-way and that it was only temporarily present for the purpose of installing a water pipeline; therefore, it is not an owner or occupant of the land. It cites Redevelopment Authority of Allegheny County v. Stepanik, 25 Pa.Commonwealth Ct. 180, 360 A.2d 300 (1976), aff'd, 479 Pa. 199, 387 A.2d 1292 (1978), for *31

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Diess v. Pennsylvania Department of Transportation
935 A.2d 895 (Commonwealth Court of Pennsylvania, 2007)
Commonwealth v. Berresford
590 A.2d 1379 (Commonwealth Court of Pennsylvania, 1991)
Newlin Corp. v. Commonwealth, Department of Environmental Resources
579 A.2d 996 (Commonwealth Court of Pennsylvania, 1990)

Cite This Page — Counsel Stack

Bluebook (online)
560 A.2d 905, 127 Pa. Commw. 26, 104 Oil & Gas Rep. 403, 1989 Pa. Commw. LEXIS 438, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-pennsylvania-water-co-v-commonwealth-pacommwct-1989.