Western North Carolina Alliance v. North Carolina Department of Transportation

312 F. Supp. 2d 765, 2003 U.S. Dist. LEXIS 25120, 2003 WL 23356521
CourtDistrict Court, E.D. North Carolina
DecidedJuly 1, 2003
Docket5:02-cv-00343
StatusPublished
Cited by7 cases

This text of 312 F. Supp. 2d 765 (Western North Carolina Alliance v. North Carolina Department of Transportation) is published on Counsel Stack Legal Research, covering District Court, E.D. North Carolina primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western North Carolina Alliance v. North Carolina Department of Transportation, 312 F. Supp. 2d 765, 2003 U.S. Dist. LEXIS 25120, 2003 WL 23356521 (E.D.N.C. 2003).

Opinion

ORDER

TERRENCE W. BOYLE, Chief Judge.

This matter is before the Court on Plaintiffs’ and Defendants’ Cross-Motions for Summary Judgment pursuant to Rule 56 of the Federal Rules of Civil Procedure. The matters have been fully briefed and are ripe for ruling.

BACKGROUND

This suit arises out of the planned expansion of 1-26 from four to six lanes between NC 225 and NC 280. The project, designated as 1-4400, is a stretch of 13.6 miles of existing highway located primarily in Henderson County, North Carolina. 1 Defendant North Carolina Department of Transportation (“NCDOT”) has a Transportation Improvement Program (“TIP”) which identifies and recommends transportation improvements throughout the State. Although not previously on the list of long-term TIP projects, project I-4400 was added to avoid losing 54 million dollars of existing funding. The public planning for the project was started in 2000. On May 4, 2001, Defendants approved and published the Environmental Assessment (“EA”), and on January 18, 2002, a Finding of No Significant Impact (“FONSI”) was issued for 1^400.

The following projects, which also involve improvements to the 1-26 corridor, are being pursued and are in varying stages of planning: 1) 1 — 4700, the expansion from four to six lanes of 8.6 miles of 1-26 from the northern end of 1-4400 north to the intersection of 1-26 and 1-40 in Asheville, NC; 2) 1-2513, the development of a 3.5 mile segment that will connect 1-26 south of Asheville with US-19-23 north of Asheville; and, 3) FS-0113B, the addition of lanes to U.S. 19-23 (future 1-26) from 1-240 in Asheville to south of SR 2148 in Buncombe County, a distance of 15 miles. One additional project, A-10, is presently under construction. This project is upgrading US-19-23-70 from 1-240 in Asheville to the Tennessee state line to meet interstate standards. Presently, I-26 runs from Charleston, South Carolina, northward through western North Carolina, and terminates at its intersection with 1-40 in Asheville, North Carolina. *DCCCX Ultimately, the proposed construction of all of the segments will expand and extend 40 miles of highway through Henderson and Buncombe Counties and north to Tennessee where 1-26 will connect with 1-81. The segment involving 1-26 in Buncombe County will impact boundaries with the Blue Ridge Parkway and the Biltmore Estate.

Plaintiffs are Western North Carolina Alliance, Citizens for Transportation Planning, Smart Growth Partners of Western North Carolina, Inc., and North Carolina Alliance for Transportation Reform. Plaintiffs contend that Defendants have violated the National Environmental Policy Act (“NEPA”) by issuing an EA and FON-SI for 1-4400. Plaintiffs assert that the EA and FONSI are inadequate under NEPA in the following respects: 1) Defendants violated NEPA by failing to consider the cumulative impacts of the total proposed 40 mile expansion of 1-26; 2) Defendants failed to complete a comprehensive EIS that adequately addresses the combined impacts of the development of the four segments; and, 3) The EA prepared for 1-4400 failed to take the required “hard-look” at the planned expansion of I-4400. In an Order filed on October 7, 2002, the Court granted Plaintiffs Motion for Preliminary Injunction and enjoined Defendants from proceeding further with project 1-4400 pending resolution of this lawsuit or until further order of this Court. Plaintiffs now ask the Court to grant their Motion for Summary Judgment and issue a permanent injunction until Defendants comply with NEPA.

Defendants are the NCDOT; Lyndo Tippett, Secretary of NCDOT; the Federal Highway Administration (“FHWA”); and Nicholas Graf, Division Administrator for FHWA. 2 Defendants contend that the EA complies with NEPA and that a single EIS is not required for what they view as distinct projects. Defendants also argue that, in any case, the EA and FONSI did address the cumulative impacts of the other projects and determined that they were not significant. Finally, Defendants contend that the EA took the required “hard look” at the environmental consequences of 1-4400.

DISCUSSION

A court may grant summary judgment only if there is no genuine issue as to any material fact and the moving party is entitled to judgment as a matter of law. Fed. R.Civ.P. 56(c); Celotex Corp. v. Catrett, 477 U.S. 317, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986). The court must determine “whether the evidence presents sufficient disagreement to require submission to a jury or whether it is so one-sided that one party must prevail as a matter of law.” Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 251-52, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986). The moving party bears the initial burden to show the court that there is an absence of genuine issue concerning any material fact and that the non-moving party cannot prevail. See Celotex, 477 U.S. at 325, 106 S.Ct. 2548. In order to survive the motion, the non-moving party must then show that there is “evidence from which a jury might return a verdict in his favor.” Anderson, 477 U.S. at 257, 106 S.Ct. 2505. The court must view the facts and all inferences drawn from the facts in the light most favorable to the non-moving party. See id. at 255, 106 S.Ct. 2505.

In reviewing a claim that an agency acted in violation of NEPA the Court’s narrow role is to determine if the decision was “arbitrary and capricious.” 5 U.S.C. *DCCCXI § § 706(2)(A), (C). A decision is arbitrary and capricious if:

The agency has relied on factors which Congress has not intended it to consider, entirely failed to consider an important aspect of the problem, offered an explanation for its decision that runs counter to the evidence before the agency, or is so implausible that it could not be ascribed to a difference in view or the product of agency expertise.

Hughes River Watershed, Conservancy v. Johnson, 165 F.3d 283, 287 (4th Cir.1999) (citing Motor Vehicle Mfrs. Ass’n of the United States v. State Farm Mutual Auto. Ins. Co., 463 U.S. 29, 43, 103 S.Ct. 2856, 77 L.Ed.2d 443 (1983)). The role of a court is not to substitute its judgment, but to look for a “clear error” of judgment by the agency. Johnson, 165 F.3d at 287. The court must determine whether the agency took a “hard look” at the project’s effects. Hughes River Watershed Conservancy v. Glickman, 81 F.3d 437, 443 (4th Cir.1996).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
312 F. Supp. 2d 765, 2003 U.S. Dist. LEXIS 25120, 2003 WL 23356521, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-north-carolina-alliance-v-north-carolina-department-of-nced-2003.