Western Contracting Corporation v. The Dow Chemical Company, the Dow Chemical Company v. Western Contracting Corporation

664 F.2d 1097, 1981 U.S. App. LEXIS 15593
CourtCourt of Appeals for the Eighth Circuit
DecidedDecember 1, 1981
Docket81-1339
StatusPublished
Cited by20 cases

This text of 664 F.2d 1097 (Western Contracting Corporation v. The Dow Chemical Company, the Dow Chemical Company v. Western Contracting Corporation) is published on Counsel Stack Legal Research, covering Court of Appeals for the Eighth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Western Contracting Corporation v. The Dow Chemical Company, the Dow Chemical Company v. Western Contracting Corporation, 664 F.2d 1097, 1981 U.S. App. LEXIS 15593 (8th Cir. 1981).

Opinion

LAY, Chief Judge.

This appeal arises from consolidated cases brought by Western Contracting Corporation (Western) on grounds of breach of contract and fraud and by Dow Chemical Company (Dow) for payments due and for foreclosure of a mechanic’s lien. Pursuant to a trial to the court, the Honorable Earl R. Larson presiding, a judgment of $328,177.11 was entered for Dow, and Western appeals, claiming that: (1) the trial court erred in concluding that the contract unambiguously required Dow to exercise its “best efforts” regarding fragmentation; (2) the trial court erred in finding that Dow, in fact, had exercised its “best efforts” in contract performance; (3) the trial court erred in finding that Dow made no fraudulent representation regarding control of fragmentation size; and (4) the trial court erred in its factual findings regarding the extent of Dow’s damages. Upon review of the record and briefs, we affirm the judgment of the district court.

*1099 Facts.

On April 17, 1974, Western contracted with United States Steel (Steel) for site preparation and rough excavation for construction of four additions to Steel’s Minntac facility at Mountain Iron, Minnesota. By mid-February 1975, Western had encountered significant scheduling and other difficulties in its performance of the contract. At that time Western contacted Dow’s general manager of explosives for assistance, as he had demonstrated to Western earlier in 1973 Dow’s blasting products and the capabilities of its “delta crater” method of blast design. A series of four test shots, which were engineered partly by Western and partly by Dow in late 1974 and early 1975, demonstrated that Dow could more efficiently effectuate the Minntac rock excavation with smaller fragmentation. Western then subcontracted the blasting operation to Dow on March 20, 1975, subject to the following pertinent provisions:

Article II — Rate of performance.
2.1 The work to be performed under this Agreement shall be commenced within one day after receipt of notice to proceed from Western but in no event later than 30 days from the date hereof.
2.2 The rock to be removed shall be fragmented to sizes at least as small as the rock fragments that resulted in two Dow test “shots” previously completed at U.S. Steel’s Minntac Concentrator Area and shall be tumbled to unlock the “shot” rock.
2.3 Dow shall drill, load and shoot rock for removal at the rate of 16,000 cubic yards per each regular working day for a total of 400,000 cubic yards per month.
Article III — Best Efforts.
3.1 Dow’s obligation under this Agreement shall be to use its best efforts only to perform the work at the Rate of Performance spelled out in Article II, above.
3.2 Dow shall utilize its best efforts to blast the rock such that bottoms of excavations will be within neat line tolerances as planned; however, Dow will not be subject to penalty for over blasting beyond neat lines.

As the Minntac job progressed, Western incurred increased difficulty and delay in rock removal due to the size of fragmentation from the blasting operations; generally, the larger the fragmentation, the greater the time and difficulty involved in Western’s removal operations. Dow and Western attempted to alleviate these problems through blast design revisions and secondary blasting.

At the project’s completion Western sued Dow in federal district court on grounds that Dow breached the subcontract agreement and that the agreement was induced by the fraudulent misrepresentation that Dow possessed a blasting system with which it could control the size of rock fragmentation. Dow counterclaimed on grounds of Western’s nonpayment of sums owing for work performed. A separate state action by Dow to foreclose a mechanic’s lien was removed to federal district court, and both actions were consolidated for trial in the district of Minnesota. The court found that Dow had exercised its “best efforts” as required by the contract, and that Western had relied upon the test shot results, not upon any representations by Dow regarding fragmentation size.

The “Best Efforts” Clause.

Western first claims that Dow failed to blast the rock to sufficiently small fragmentation to comply with the subcontract, and that such failure damaged Western by, inter alia, preventing receipt of a $625,000 bonus from Steel. 1 The district court held *1100 that the “best efforts” requirement of paragraph 3.1 of the subcontract clearly and unambiguously pertains to all of the contractual obligations encompassed in article II, entitled “Rate of performance.” Specifically, the court held that Dow was required to exercise its “best efforts” in fragmenting rock to sizes equivalent to that in the test shots. The trial court, after weighing the conflicting testimony, found that Dow substantially complied with this requirement, and, therefore, did not breach the agreement.

Western contends that the best efforts obligation of paragraph 3.1 clearly and unambiguously applies only to the rate of performance stated in paragraph 2.3. Western argues that paragraphs 2.1 and 2.2 contain other conditions of performance, but no “rates”, despite inclusion in article II. Therefore, it is Western’s contention that the best efforts requirement does not apply to fragmentation size, and that Dow’s performance was not equivalent to that in the test shots. Alternatively, Western urges that inclusion of paragraphs 2.1 and 2.2 in article II creates an ambiguity because they do not refer to rates of performance but appear in the article so entitled. Western further submits that parol evidence, specifically the original oral agreement and purchase order, is admissible to explain this ambiguity in the subcontract to mean that duplication of the test shot results was intended. Finally, it is Western’s assertion that Dow’s performance fell far short of the test shot results.

As to the presence or absence of an ambiguity and interpretation of the contract, such a question is a matter of law and is not, therefore, subject to the “clearly erroneous” standard of review by this court. Swanson v. Baker Industries, Inc., 615 F.2d 479, 483 (8th Cir. 1980). A careful reading of paragraph 3.1 in conjunction with article II of the subcontract leads this court to the conclusion that the district court properly held that Dow’s obligation regarding fragmentation was clearly and unambiguously exercise of its best efforts. Because we find the contract unambiguous, the contradictory parol evidence was properly excluded. Republic National Life Insurance v. Lorraine Realty, 279 N.W.2d 349 (Minn. 1979.)

As to whether Dow fulfilled this obligation to exercise its best efforts to match test shots fragmentation, this court is bound by the “clearly erroneous” standard of review. Fed.R.Civ.P.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Marvin Klehr v. Charles R. Crafts
69 F. App'x 818 (Eighth Circuit, 2003)
Marvin Lumber & Cedar Co. v. PPG Industries, Inc.
223 F.3d 873 (Eighth Circuit, 2000)
Nordale, Inc. v. Samsco, Inc.
830 F. Supp. 1263 (D. Minnesota, 1993)
Olympia Hotels Corp. v. Johnson Wax Development Corp.
908 F.2d 1363 (Seventh Circuit, 1990)
Spitzmueller v. Burlington Northern Railroad
740 F. Supp. 671 (D. Minnesota, 1990)
National Union Fire Insurance Co. v. Evenson
439 N.W.2d 394 (Court of Appeals of Minnesota, 1989)
Mutsch v. Rigi
430 N.W.2d 201 (Court of Appeals of Minnesota, 1988)
Rauenhorst v. United States
104 F.R.D. 588 (D. Minnesota, 1985)
ACLI International Commodity Services, Inc. v. Lindwall
347 N.W.2d 522 (Court of Appeals of Minnesota, 1984)

Cite This Page — Counsel Stack

Bluebook (online)
664 F.2d 1097, 1981 U.S. App. LEXIS 15593, Counsel Stack Legal Research, https://law.counselstack.com/opinion/western-contracting-corporation-v-the-dow-chemical-company-the-dow-ca8-1981.