West Virginia Electric Supply Co. v. Ohio River Plaza Associates Ltd.

612 N.E.2d 1263, 82 Ohio App. 3d 605, 1992 Ohio App. LEXIS 4895
CourtOhio Court of Appeals
DecidedSeptember 25, 1992
DocketNo. 92CA7.
StatusPublished
Cited by1 cases

This text of 612 N.E.2d 1263 (West Virginia Electric Supply Co. v. Ohio River Plaza Associates Ltd.) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Virginia Electric Supply Co. v. Ohio River Plaza Associates Ltd., 612 N.E.2d 1263, 82 Ohio App. 3d 605, 1992 Ohio App. LEXIS 4895 (Ohio Ct. App. 1992).

Opinion

Harsha, Judge.

West Virginia Electric Supply Co., plaintiff-appellant, appeals from a summary judgment entered by the Gallia County Court of Common Pleas finding that its mechanic’s lien was invalid and, accordingly, that its claims for relief against Ohio River Plaza Associates, Ltd. (“ORPA”), Robert A. Darden Co. (“Darden”), and St. Paul Mercury Insurance Co. (“St. Paul”), defendantsappellees, were without merit.

Appellant assigns the following as its sole assignment of error:

“The trial court erred in holding that former Ohio Revised Code Section 1311.04 required a materialman to provide certificates or affidavits as a condition precedent to obtaining a valid mechanics’ lien.”

In 1988, ORPA entered into a contract with Darden to act as general contractor to design and construct the Ohio River Plaza in Gallipolis, Ohio. 1 The project was to consist of a Big Bear grocery store, several other stores, and various site improvements. Darden entered into a subcontract with Clark Electric Co. (“Clark”), a West Virginia corporation, in which Clark agreed to furnish the labor, material, and insurance required to complete all of the electrical work for the Big Bear grocery store. Appellant furnished materials to Clark for the project. St. Paul, the bonding company for Darden, acted as a surety on the mechanic’s lien bond filed for appellant’s protection.

At the time that construction was substantially completed, Darden had paid Clark the vast majority of the contract price. However, Clark never paid appellant for materials supplied by appellant for the project. Accordingly, appellant filed an affidavit and an amended affidavit of mechanic’s lien with *608 the Gallia County Recorder’s Office, noting a claim in the ultimate amount of $65,204.98.

Appellant filed, a complaint seeking to enforce its mechanic’s lien against ORPA, Darden, St. Paul, and to obtain a money judgment against Clark for the materials supplied. ORPA, Darden, and St. Paul filed a joint answer which asserted, in part, that appellant had failed to perfect its mechanic’s lien in accordance with Ohio law. These defendants also filed a cross-claim for indemnification against Clark. On August 5, 1991, the trial court entered a default judgment in favor of appellant and ORPA, Darden, and St. Paul against Clark in the amount of $61,096.22 ($65,204.98 minus credits due Clark). The trial court additionally granted leave to the remaining defendants to file a motion for summary judgment on the issue of whether appellant properly perfected its mechanic’s lien. The parties stipulated that the only issue as to the validity of appellant’s mechanic’s lien would be whether the lien was properly perfected. Upon the filing of the motion, the trial court granted summary judgment to appellees, finding that the applicable version of R.C. 1311.04 required materialmen such as appellant to provide a certificate or affidavit to the contractor showing the unpaid balance owed for materials furnished by appellant at the construction site. Since it was uncontested that appellant did not provide any certificate or affidavit, the court found that appellant’s mechanic’s lien was invalid.

Appellant’s sole assignment of error asserts that the trial court erred in holding that the applicable version of R.C. 1311.04 required a materialman to provide certificates or affidavits to the contractor as a condition precedent to obtaining a valid mechanic’s lien. We agree.

The portion of the applicable version of R.C. 1311.04 that is controlling in the case at bar provides:

“Whenever any payment of money becomes due from the owner, part owner, or lessee, or whenever the original contractor desires to draw any money from the owner, part owner, or lessee, under their contract, or whenever any mortgagee makes a written demand, the contractor shall make out and give to the owner, part owner, lessee, or mortgagee, or his agent, a statement under oath, showing the name and address of every laborer in his employ who has not been paid in full and also showing the name and address of every subcontractor in his employ, and of every person furnishing machinery, material, or fuel, and giving the amount which is due or to become due to them, or any of them, for work done, or machinery, material, or fuel furnished to him, which statement shall be accompanied by a certificate signed by every person furnishing machinery, material, or fuel to him. Address, as used in *609 this section and in section 1311.06 of the Revised Code, means last known address. * * *
« * * *
“The original contractor shall also deliver to the owner, part owner, lessee, or mortgagee similar sworn statements from each subcontractor, accompanied by like certificates from every person furnishing machinery, material, or fuel to the subcontractor. The owner, part owner, lessee, or his agent shall retain out of any money then due or to become due to the principal contractor, an amount sufficient to pay all demands that are due or to become due to the subcontractors, laborers, and materialmen, as shown by the contractors’ and subcontractors’ statements and the certificates of materialmen for work done or machinery, material, or fuel furnished, and shall pay said money to them according to their respective rights. All payments so made shall, as between such owner, part owner, lessee, or mortgagee, and the contractor, subcontractors, and persons performing labor or furnishing machinery, material, or fuel, be considered the same as if paid to the original contractor, and such owner, part owner, lessee, or mortgagee shall thereupon be released of any further liability to the extent of the payments so made.
“Until the statements are made and furnished in the manner and form provided for in this section, the contractor has no right of action or lien against the owner, part owner, or lessee, on account of such contract, and the subcontractor has no right of action or lien against the owner, part owner, lessee, or contractor, until he has furnished such statements, and any payments made by the owner, part owner, or lessee, before such statements are made or without retaining sufficient money, if that amount is due or it is to become due, to pay the subcontractors, laborers, or materialmen, as shown by the statements and certificates, are illegal and made in violation of the rights of the persons intended to be benefited by sections 1311.01 to 1311.24 of the Revised Code, and the rights of the subcontractors, laborers, and materialmen to a lien, are not affected thereby. When the appropriate period within which any liens can be filed has expired, and no liens on account of the improvement exist, then the failure of the contractor to furnish the affidavit as provided in this section shall not act as a bar or defense in any suit or cause of action to collect any claim. If the owner, part owner, lessee, or his agent cannot be found within the county, then it is not necessary for the contractor or subcontractor to make and deliver the statements and certificates as a prerequisite to a lien or to the institution of a suit or proceedings.” (Emphasis added.)

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Joest Vibratech, Inc. v. North Star Steel Co.
109 F. Supp. 2d 746 (N.D. Ohio, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
612 N.E.2d 1263, 82 Ohio App. 3d 605, 1992 Ohio App. LEXIS 4895, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-virginia-electric-supply-co-v-ohio-river-plaza-associates-ltd-ohioctapp-1992.