Joest Vibratech, Inc. v. North Star Steel Co.

109 F. Supp. 2d 746, 2000 U.S. Dist. LEXIS 11594, 2000 WL 1146615
CourtDistrict Court, N.D. Ohio
DecidedAugust 9, 2000
Docket4:00-cv-00810
StatusPublished
Cited by2 cases

This text of 109 F. Supp. 2d 746 (Joest Vibratech, Inc. v. North Star Steel Co.) is published on Counsel Stack Legal Research, covering District Court, N.D. Ohio primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Joest Vibratech, Inc. v. North Star Steel Co., 109 F. Supp. 2d 746, 2000 U.S. Dist. LEXIS 11594, 2000 WL 1146615 (N.D. Ohio 2000).

Opinion

ORDER AND OPINION

GWIN, District Judge.

On May 12, 2000, Defendant North Star Steel Company filed a motion to dismiss Plaintiff Joest Vibratech, Inc.’s complaint. 1 [Doc. 12]. On June 22, 2000, the Court converted the motion to dismiss into a motion for summary judgment pursuant to Rules 12 and 56. 2 [Doc. 19]. For the reasons stated below, the Court grants Defendant North Star Steel’s motion for summary judgment on all counts.

I. FACTUAL BACKGROUND

Plaintiff Joest Vibratech is an Ohio resident that supplies materials for use in various manufacturing processes.

Defendant North Star Steel is a Minnesota corporation operating a steel mill in Youngstown, Ohio.

This action stems from Defendant North Star Steel’s ordering materials as the property owner in a construction project to upgrade the steel mill. Defendant North Star Steel entered into a contract with the primary contractor, Industrial Conveyor Design. Industrial Conveyor Design then hired Plaintiff Joest Vibratech as a subcontractor on the project.

Defendant North Star Steel did not order materials from Plaintiff Joest Vibra-tech. Instead the primary contractor, Industrial Conveyor Design, ordered the materials. Plaintiff Joest Vibratech says two groups of materials were involved. Plaintiff Joest Vibratech delivered the first shipment to the construction location. As to the materials making up this first *748 shipment, Defendant North Star Steel paid primary contractor Industrial Conveyor Design for the work completed and the material supplied in connection with that work. Industrial Conveyor Design later went bankrupt without paying Joest Vibratech for any materials ordered. As to the second group of materials, Plaintiff Joest Vibratech never delivered the second shipment, which remains in storage under the plaintiffs control. Joest Vibra-tech brings this action to recover payment directly from Defendant North Star Steel.

Plaintiff Joest Vibratech makes claim for a mechanic’s lien and foreclosure on that lien, payment for the delivered materials as an intended beneficiary, payment on the account for both delivered and undelivered materials, and quantum meruit for all the materials. On the briefs and evidence submitted by both parties, the Court finds that there is no issue of material fact for trial. Accordingly, the Court grants Defendant North Star Steel’s motion for summary judgment.

II. LEGAL STANDARD

Fed. R. Civ. P. 56(c) states the rule for summary judgment and says in pertinent part:

The judgment sought shall be rendered forthwith if the pleadings, depositions, answers to interrogatories, and admissions on file, together with the affidavits, if any, show that there is no genuine issue as to any material fact and that the moving party is entitled to a judgment as a matter of law.

In considering a motion for summary judgment, the court must view the facts and all inferences drawn in the light most favorable to the non-moving party. See Adickes v. S.H. Kress & Co., 398 U.S. 144, 158-59, 90 S.Ct. 1598, 26 L.Ed.2d 142 (1970); 60 Ivy Street Corp. v. Alexander, 822 F.2d 1432, 1435 (6th Cir.1987); SEC v. Blavin, 760 F.2d 706, 710 (6th Cir.1985). The moving party must conclusively show that no genuine issue of material fact exists. See 60 Ivy Street Corp., 822 F.2d at 1435.

Factual disputes about matters essential to adjudication preclude the Court from granting summary judgment. See id. But not every factual dispute between the parties will prevent summary judgment. Rather, the disputed facts must be material, The facts must be such that, under the substantive law governing the issue, they might affect the outcome of the suit. See Anderson v. Liberty Lobby, Inc., 477 U.S. 242, 106 S.Ct. 2505, 91 L.Ed.2d 202 (1986).

The factual dispute must also be genuine. If the facts, once proven at trial, could cause a reasonable jury to return a verdict for the non-moving party, then the court must deny summary judgnent. See id. at 248, 106 S.Ct. 2505. The non-moving party need not resolve the disputed issues conclusively in its favor, but it must present some significant probative evidence which makes it necessary to resolve the parties’ differing versions of the dispute at trial. See 60 Ivy Street, 822 F.2d at 1435 (citing First Nat’l Bank of Arizona v. Cities Serv. Co., 391 U.S. 253, 88 S.Ct. 1575, 20 L.Ed.2d 569 (1968)); see also Celotex Corp. v. Catrett, 477 U.S. 317, 322, 106 S.Ct. 2548, 91 L.Ed.2d 265 (1986); Matsushita Elec. Indus. Co., Ltd. v. Zenith Radio Corp., 475 U.S. 574, 106 S.Ct. 1348, 89 L.Ed.2d 538 (1986).

Thus, the judge’s function at the summary judgment stage is limited to determining whether the parties submitted sufficient evidence to make the issue a proper jury question, and not to judge the evidence and make findings of fact. See 60 Ivy Street, 822 F.2d at 1436.

The Court reviews the motion with these standards in mind.

III. DISCUSSION

A. Mechanic’s Lien

Defendant North Star Steel says that Plaintiff Joest Vibratech is not entitled to a mechanic’s lien because it did not strictly follow the procedures for acquiring the *749 lien. The Court finds Defendant’s argument persuasive.

To obtain a valid mechanic’s lien against real property, a subcontractor must fulfill two requirements. First, he must serve a notice of furnishing on the property owner within twenty-one days of beginning work or delivering materials, provided the owner properly filed a notice of commencement. Second, he must file an affidavit for the lien within seventy-five days from the last date labor was performed or materials delivered. See OHIO REV. CODE §§ 1311.05(A), 1311.06(B)(3).

If the land owner files a notice of commencement, and the subcontractor fails to serve a notice of furnishing upon the land owner, the subcontractor has not protected its lien rights. See OHIO REV. CODE § 1311.05(A). Defendant North Star Steel properly filed a notice of commencement. See

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
109 F. Supp. 2d 746, 2000 U.S. Dist. LEXIS 11594, 2000 WL 1146615, Counsel Stack Legal Research, https://law.counselstack.com/opinion/joest-vibratech-inc-v-north-star-steel-co-ohnd-2000.