West Unity v. Merillat, Unpublished Decision (5-7-2004)

2004 Ohio 2682
CourtOhio Court of Appeals
DecidedMay 7, 2004
DocketNo. WM-03-016.
StatusUnpublished
Cited by9 cases

This text of 2004 Ohio 2682 (West Unity v. Merillat, Unpublished Decision (5-7-2004)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Unity v. Merillat, Unpublished Decision (5-7-2004), 2004 Ohio 2682 (Ohio Ct. App. 2004).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This case is before the court on appeal from a judgment of the Williams County Court of Common Pleas, which denied appellant's application for an injunction and petition for writ of mandamus.

{¶ 2} On July 29, 2002, the Building Committee for the village of West Unity ("Village"), met to discuss the construction of a pole barn to be used as a Village storage building. The Building Committee approved a set of plans and obtained a cost estimate for the proposed public improvement from Bell Engineering. Bell Engineering's estimate was $60,720. It is undisputed that the cost estimate submitted by Bell engineering did not include the prevailing wage rate for the locality in which the Village is situated. The Building Committee then submitted the plans to the Village Council, which approved the plans and let the contract out for bids. The Village Council awarded the contract to Dave Nixon Construction, which offered a bid of $54,921, and construction commenced on the storage building.

{¶ 3} On October 11, 2002, appellant, Jeff Beltz, instituted, pursuant to R.C. 733.59, a taxpayer's action on behalf of the Village. The named defendants in the complaint are appellees, Richard Merillat, the Mayor of the Village, and the six members of the Village Council. Appellant asserted that the estimate prepared by Bell Engineering was not "fairly estimated" within the meaning of Ohio's Prevailing Wage Law, R.C. 4115.03 to R.C.4115.16. He claimed that any properly calculated estimate would be in excess of the threshold, $62,549, that would require compliance with Ohio's Prevailing Wage Law.

{¶ 4} In Count 1 of his complaint, appellant therefore asked the court, pursuant to R.C. 733.56, for preliminary and permanent injunctions that would prevent the misapplication of Village funds, an abuse of Village corporate powers, and the performance of contracts in violation of Ohio law. Specifically, appellant wanted appellees restrained "from performing the contract with Dave Nixon Construction and from entering into any future contracts to perform construction on the storage building that might be in contravention of Ohio's Prevailing Wage Law. Count 2 of the complaint petitioned for a writ of mandamus compelling appellees to act in accordance with various provisions of R.C.4115.03 to R.C. 4115.16.

{¶ 5} On October 21, 2002, the trial court denied appellant's motion for a temporary restraining order and scheduled the hearing on the request for a preliminary injunction for October 31, 2002. However, upon appellant's request, the hearing date was continued until December 3, 2002. On that date, evidence was offered on the merits of both the application for a preliminary injunction and the application for a permanent injunction.

{¶ 6} At the hearing, and in a post-hearing brief, filed on March 31, 2003, appellant urged that in construing the relevant sections of Ohio's Prevailing Wage Law, and the regulations promulgated thereunder, together, Bell Engineering's cost estimate was required to include the "prevailing wage rate in the locality." Based on the evidence offered at the hearing, appellant claimed that a "fairly estimated" cost estimate is $86,675.38. Appellant again asked that the court restrain appellees from completing the construction of the storage building and to compel appellees to comply with the applicable provisions of R.C. 4115.03 to R.C. 4115.16.

{¶ 7} On July 1, 2003, the trial court denied appellant's application for preliminary and permanent injunctions and for a writ of mandamus. In interpreting prevailing wage law in conjunction Ohio Adm.Code: 9-4-17(A), the court found, in essence, that in "fairly estimating" a pre-bid cost for a project involving the new construction of a public improvement, the estimator, in this case, Bell Engineering, did not have to include the prevailing wage. Appellant appeals that judgment and sets forth the following assignments of error:

{¶ 8} "1. The trial court committed reversible error when it held that O.A.C. 4101:9-4-17(A) does not apply to new construction."

{¶ 9} "2. The trial court committed reversible error when it refused to hold that the prevailing wage law requires the use of the prevailing rate of wages in all construction cost estimates."

{¶ 10} "3. The trial court committed reversible error when it refused to give effect to the statutory standards under R.C.4115.03(B) that the `total overall project cost' be 'fairly estimated'."

{¶ 11} "4. The trial court committed reversible error when it refused to hold that the total overall project cost of the public improvement underlying this action, fairly estimated, is "$86,675.38 and thus subject to the prevailing wage law."

{¶ 12} We must first address the question of whether the appeal before us is moot. At the time of the hearing on appellant's causes of action, testimony revealed that the storage facility was "98%" complete-only the gutters and a little trim work remained to be done. On appeal, appellees contend that the storage building was completed by April 28, 2003.

{¶ 13} Appellant does not dispute this fact. Instead, appellant argues that any injunction issued by the trial court would not be prospective because the issue presented is "capable of repetition, yet, evading review" and of "great public or general interest." Consequently, appellant maintains that this appeal is not moot and, therefore, this court can address the issues raised herein.

{¶ 14} If a village solicitor believes that a village is misapplying village funds, abusing its corporate powers, or executing or performing a contract made, inter alia, on behalf of the village in contravention of laws or ordinances, the village solicitor may institute an injunctive action on behalf of the village. R.C. 733.56. When a village solicitor fails, upon the written request of a taxpayer, to bring such an action, the taxpayer has the right to initiate a suit seeking an injunction in his own name on behalf of the village. R.C. 733.59.

{¶ 15} Notwithstanding the right of a taxpayer to initiate proceedings on behalf of a Village, courts do not have the jurisdiction to consider moot issues. Carver v. Twp. ofDeerfield (2000), 139 Ohio App.3d 64, 77. Nonetheless, courts do have the jurisdiction to address issues in those cases where the issue or issues is "capable of repetition, yet evading review" or if it involves a matter of public or great general interest. Inre Suspension of Huffer (1989), 47 Ohio St.3d 12, paragraph one of the syllabus.

{¶ 16} Here, it is possible that a taxpayer's request for an injunction to deter the construction of a public improvement could be completely litigated before the construction project is finished.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Harvest Land Co-Op, Inc. v. Hora
2022 Ohio 2375 (Ohio Court of Appeals, 2022)
Sutelan v. Ohio State Univ.
2019 Ohio 4026 (Ohio Court of Claims, 2019)
Lucas Cty. Pit Crew v. Fulton Cty. Dog Warden
2016 Ohio 8526 (Ohio Court of Appeals, 2016)
Ohio Valley Associated Builders & Contractors v. Kuempel
949 N.E.2d 582 (Ohio Court of Appeals, 2011)
City of Cincinnati Ex Rel. Zimmer v. City of Cincinnati
982 N.E.2d 987 (Ohio Court of Appeals, 2008)
Village of West Unity Ex Rel. Beltz v. Merillat
861 N.E.2d 902 (Ohio Court of Appeals, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
2004 Ohio 2682, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-unity-v-merillat-unpublished-decision-5-7-2004-ohioctapp-2004.