West Texas Hospitality, Inc. D/B/A Enerserv Consultants v. Enercon International, Inc. and Paul Saxton

CourtCourt of Appeals of Texas
DecidedAugust 31, 2010
Docket07-09-00213-CV
StatusPublished

This text of West Texas Hospitality, Inc. D/B/A Enerserv Consultants v. Enercon International, Inc. and Paul Saxton (West Texas Hospitality, Inc. D/B/A Enerserv Consultants v. Enercon International, Inc. and Paul Saxton) is published on Counsel Stack Legal Research, covering Court of Appeals of Texas primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Texas Hospitality, Inc. D/B/A Enerserv Consultants v. Enercon International, Inc. and Paul Saxton, (Tex. Ct. App. 2010).

Opinion

NO. 07-09-0213-CV

IN THE COURT OF APPEALS

FOR THE SEVENTH DISTRICT OF TEXAS

AT AMARILLO

PANEL A

AUGUST 31, 2010

WEST TEXAS HOSPITALITY, INC. D/B/A ENERSERV CONSULTANTS, APPELLANT

v.

ENERCON INTERNATIONAL, INC. AND PAUL SAXTON, APPELLEES

FROM THE 99TH DISTRICT COURT OF LUBBOCK COUNTY;

NO. 2008-545,369; HONORABLE WILLIAM SOWDER, JUDGE

Before CAMPBELL and HANCOCK and PIRTLE, JJ.

MEMORANDUM OPINION

Appellant, West Texas Hospitality, Inc. d/b/a WTH Consultants ("WTH"), appeals the trial court's order issued in favor of Appellee, Enercon International, Inc. and Paul Saxton (collectively "Enercon") dismissing WTH's suit based upon a forum selection clause in a written contract. In a single issue, WTH asserts the trial court erred in its finding that there was an enforceable written contract between the parties. We reverse and remand for further proceedings consistent with this opinion.

Background

In February 2008, WTH[1] filed its Original Petition alleging Enercon[2] wrongfully retained monies paid by WTH in anticipation of execution of a written contractual agreement. WTH asserted actions for conversion, collection, and quantum meruit/unjust enrichment. In its Amended Special Appearance, Motion to Dismiss, and Original Answer filed in January 2009, Enercon sought to dismiss WTH's suit based upon a forum-selection clause contained in a written agreement which required any suit to be filed in Minnehaha County, South Dakota. WTH responded by contending that there was no written agreement because Enercon never signed the proposed contract as presented by WTH. In support of their respective arguments, the parties submitted evidence through affidavits and exhibits attached to their pleadings.

In January 2008, WTH approached Enercon asking for a proposed contract to review. Enercon offered its "Authorized Affiliate Agreement" ("Agreement"). Among other things, the Agreement provided that WTH would pay $43,900 to Enercon[3] in return for the right to sell Enercon products throughout the United States on a non-exclusive basis in addition to receiving training, customer support, a demonstration kit, startup quantities of Enercon's promotional materials and a "product credit" up to $45,000. WTH's "product credit" would be used on materials and services purchased from Enercon for projects approved by Enercon within 120 days of completion of WTH's initial training. The Agreement also provided, in pertinent part, as follows:

14. CHANGES TO AGREEMENT: This agreement may not be changed except by written consent of all parties and may not be changed orally.

16. ACCEPTANCE OF CONTRACT AND EXECUTION DATE: [WTH] shall sign duplicate originals of the Agreement and submit both originals with full payment to [Enercon]. Should [Enercon] reject the Agreement, [WTH] will be notified of such fact in writing and full payment shall be returned promptly. Should [Enercon] accept the agreement, [Enercon] will date and sign the duplicate originals of the agreement submitted and return one of the fully executed originals for [WTH] at [WTH's] address shown above. The Agreement shall be binding upon all parties the date [Enercon] dates and signs the duplicate originals, which shall be the "execution date of the Agreement." [WTH] shall have a right of rescission for three days from the date of the agreement.

18. SOLE AGREEMENT: There are no other agreements or understandings, either oral or in writing between the parties effecting this agreement or relating to the sale of the Product(s), except as otherwise specifically provided herein . . . . This agreement contains all the oral written agreements, representations and arrangements between the parties hereto. It is understood between the parties that there are no representations or warranties made or implied except as specifically set forth herein.

21. SUIT VENUE: This agreement is performable in Minnehaha County, South Dakota. Any claim, cause of action, or other legal suit arising from, or as a result of this agreement shall be brought in State Court in Minnehaha County, South Dakota . . . .

24. EXECUTION KNOWING AND VOLUNTARY: The parties hereby acknowledge and represent that they (a) have fully and carefully read this agreement prior to execution; (b) have been, or have had the opportunity to be fully apprised by any attorneys of their choice of the legal effects and meaning of this document and all terms and conditions hereof, . . . (d) are executing this agreement with full knowledge of the ramifications thereof.

30. SUPERCEDE: This contract supercedes and replaces any previous contract or agreement between the parties herein.

The Agreement also contained two signature blocks, one each for Enercon and WTH. Each signature block was prefaced by the statement "Accepted by [Enercon]" and "Accepted by [WTH]," respectively.

Kirit Desai, on behalf of WTH, made a number of handwritten changes to the proposed contract. Specifically, he extended the time within which Enercon was required to apply WTH's "product credit" from 120 days to 150 days of completion of WTH's initial training. He also amended the Agreement's terms regarding termination as follows: "This agreement may also be terminated by circumstances beyond [Enercon's] control that make it impossible or impractical for the business activities contemplated by this agreement to be continued, in which case the remaining balance from the payments made will be refunded if termination happens within 150 days from the payment." (Emphasis supplied on handwritten changes). In addition, Desai amended a number of the time-specific provisions in the termination paragraph to make ten day time limits, ten business days. (Emphasis supplied on handwritten changes).

On March 3, 2008, Desai signed the modified contract and, on March 4, wired his first installment of $26,000. The following day, Enercon received the modified contract signed by WTH and invoiced WTH for $43,900.[4] Prior to making their second installment payment, WTH ordered $5,000 worth of Enercon products. Enercon responded by invoicing WTH for "HiBrite Fixtures, Lamps, Retro Kit and freight, $5002.75," and stamped the invoice "PAID."

On April 7, Desai sent an internal e-mail to another WTH officer, and expressed concern that they had "not received a signed copy of [their] agreement with Enercon." Desai wanted to start a countdown of the number of days remaining to recover their $43,900 from Enercon, i.e., "[h]ow much time we have left and how much sales we have to generate within that time."

On April 7, Enercon and WTH exchanged a number of e-mails related to the deadline for WTH's "product credit." Paul Saxton sent an e-mail to Desai indicating that WTH's "product credit" was good for 120 days from completion of WTH's initial training. In response, Desai indicated that he had altered the Agreement as tendered by Enercon to permit WTH 150 days on the "product credit" deadline. Desai also indicated that his calculations indicated the "product credit" would not expire until August 18 and asked Saxton to verify there was a $42,000 "product credit" remaining. Saxton responded to Desai saying: "Did I sign that? I don't recall . . . I don't know why this would have been changed as we already increased it to 120 days from the usual 90 days."

On May 6, WTH made a second installment payment to Enercon, deducting $5,002.75 for the products purchased in March. WTH also requested Enercon's services to design projects and Enercon invoiced WTH for their services.[5]

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Fiess v. State Farm Lloyds
202 S.W.3d 744 (Texas Supreme Court, 2006)
Baylor University v. Sonnichsen
221 S.W.3d 632 (Texas Supreme Court, 2007)
Perry Homes v. Cull
258 S.W.3d 580 (Texas Supreme Court, 2008)
In Re Lyon Financial Services, Inc.
257 S.W.3d 228 (Texas Supreme Court, 2008)
Texas Disposal Systems Landfill, Inc. v. Waste Management Holdings, Inc.
219 S.W.3d 563 (Court of Appeals of Texas, 2007)
Domingo v. Mitchell
257 S.W.3d 34 (Court of Appeals of Texas, 2008)
Ramsay v. Texas Trading Co., Inc.
254 S.W.3d 620 (Court of Appeals of Texas, 2008)
Abraham Investment Co. v. Payne Ranch, Inc.
968 S.W.2d 518 (Court of Appeals of Texas, 1998)
Baccus v. Plains Cotton Cooperative Association
515 S.W.2d 401 (Court of Appeals of Texas, 1974)
Advantage Physical Therapy, Inc. v. Cruse
165 S.W.3d 21 (Court of Appeals of Texas, 2005)
United Concrete Pipe Corp. v. Spin-Line Co.
430 S.W.2d 360 (Texas Supreme Court, 1968)
McKnight v. Virginia Mirror Company
463 S.W.2d 428 (Texas Supreme Court, 1971)
Gilbert v. Pettiette
838 S.W.2d 890 (Court of Appeals of Texas, 1992)
Phoenix Network Technologies (Europe) Ltd. v. Neon Systems, Inc.
177 S.W.3d 605 (Court of Appeals of Texas, 2005)
Wohlfahrt v. Holloway
172 S.W.3d 630 (Court of Appeals of Texas, 2005)
Barnett v. Network Solutions, Inc.
38 S.W.3d 200 (Court of Appeals of Texas, 2001)
Harris v. Balderas
27 S.W.3d 71 (Court of Appeals of Texas, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
West Texas Hospitality, Inc. D/B/A Enerserv Consultants v. Enercon International, Inc. and Paul Saxton, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-texas-hospitality-inc-dba-enerserv-consultants-v-enercon-texapp-2010.