West Bank Steel Erectors Corp. v. Charles Carter & Co.

248 So. 2d 52, 1971 La. App. LEXIS 6281
CourtLouisiana Court of Appeal
DecidedApril 19, 1971
DocketNo. 8289
StatusPublished
Cited by5 cases

This text of 248 So. 2d 52 (West Bank Steel Erectors Corp. v. Charles Carter & Co.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
West Bank Steel Erectors Corp. v. Charles Carter & Co., 248 So. 2d 52, 1971 La. App. LEXIS 6281 (La. Ct. App. 1971).

Opinion

LOTTINGER, Judge.

This is a suit filed by West Bank Steel Erectors Corporation, as petitioner, for the balance allegedly due under a subcontract with Charles Carter & Company, Inc., the general contractor, and the Roman Catholic Church of the Archdiocese of New Orleans, the owner, as defendants. The Lower Court rendered a judgment in favor of petitioner and against defendants, in solido, in the sum of $3,131.79. The defendants have appealed.

This suit arises as a result of an alleged balance due under a subcontract by West Bank Steel Erectors Corporation against Charles Carter & Company, Inc., as the general contractor, and the Roman Catholic Church of the Archdiocese of New Orleans, the owner of the construction, same being a building complex in the vicinity of Houma, Louisiana, formerly known as the Houma Catholic High School (Vande-bilt Catholic High School). Defendants answered, admitting that the full amount of the price under the subcontract had not [54]*54been paid because the subcontractor failed to install certain reinforcing steel properly, thus necessitating extensive remedial work to make the school building structurally sound. Charles Carter & Company, Inc. (hereinafter referred to as Carter) reconvened seeking damages against its subcontractor West Bank Steel Erectors Corporation (hereinafter referred to as West Bank), resulting from the latter’s failure to perform as required by the subcontract, including reasonable attorney fees as stipulated in the subcontract. West Bank answered the reconventional demand in the form of a general denial.

Following trial, the Lower Court took the matter under advisement, and, as shown by its written reasons for judgment, concluded that: (1) Carter failed to prove by a preponderance of the evidence that West Bank failed to install the reinforcing steel in a workmanlike manner and in accordance with the plans and specifications, and (2) Carter owed a duty to West Bank to obtain an inspection of West Bank’s reinforcing steel work by the architect’s consulting structural engineer. The Lower Court rendered judgment in favor of West Bank and against Carter and the Roman Catholic Church of the Archdiocese of New Orleans (hereinafter referred to as owner) in solido, in the net principal sum of $3,131.79, with legal interest and costs. The Lower Court further dismissed Carter’s reconventional demand. From this judgment, Carter and owner have perfected this, a suspensive appeal.

The evidence reflects that on August 12, 1964, Carter entered into a general contract with owner for the construction of the school situated near the City of Houma, in the Parish of Terrebonne, Louisiana. On the same day the subcontract was entered into by the contractor with West Bank under which West Bank was to install the reinforcing steel and reinforcing mesh for the construction of the said high school.

The evidence reflects that Building C was the first of the buildings to be erected, and no problem was encountered with the reinforcing steel placed in the beams and joists of the first floor of said building. Mr. Robert Froedge, representative of West Bank, took over the installation of the reinforcing steel on the second floor of Building C and installed the reinforcing steel only in the areas of the first and second concrete pours of the second floor of said building. After these two pours, the reinforcing steel work was performed by another representative on behalf of West Bank. It was in the area of both the first and second concrete pours of the second floor of Building C that the reinforcing steel was allegedly uniformly misplaced.

This misplacement was originally detected by Mr. Thomas A. Fromherz, the structural consulting engineer employed by the architect, who testified upon trial that when he examined the area of the second pour of the second floor of Building C, prior to the pouring of the concrete thereon, he noted the beam and joist reinforcing steel was not placed as required by the contract drawings and specifications. Because of the uniform misplacement of the steel in this area, Mr. Fromherz concluded that the beam and joist reinforcing steel had likewise been misplaced in the area of the first pour of the second floor of Building C in which area the concrete had already been poured. To verify this conclusion, he required that test holes be made in the concrete of the first pour in the areas where the reinforcing steel was supposed to have been placed, personally examined the numerous test holes and verified that his fears were correct and that the reinforcing steel had uniformly likewise been improperly installed and misplaced in this area.

In its reasons for judgment, the Lower Court said:

“There is no doubt that the reinforcing steel was not placed in the beams where the architects’ consulting engineers, wanted, or expected, it to be. The test holes, cut in the beams revealed, at least where the holes were cut, that the steel [55]*55was not where it was expected to be. However this court is not prepared to say that plaintiffs’ foreman, Froedge, did not properly read, and follow, the directions which appeared on the various sheets of prints and instructions for the setting of the steel.
Defendant and reconvenor introduced in evidence sheet 13 of Reconvenor Exhibit No. 1, purporting to show how the steel was to be set. (Tr. pp. IS, 16) In that connection, Froedge stated that he did not use that sheet (architect’s drawing) but rather the reinforcing steelprint sent out by the company that bonds (fabricates) the steel. He insisted that he set the steel correctly according to the cut sheets or shop drawings, ‘the prints I worked with.’ ”

The overwhelming weight of the evidence discloses that the laying of these steel beams was not in accordance with the plans and specifications supplied West Bank. Whether or not the installation was in a good and workmanlike manner is certainly subject to great doubt because of the testimony of the various engineers and representatives of the architectural firm that it was necessary to strengthen the defective beams by the use of steel plates and channel iron applied externally to them.

In Biedenharn v. Waters, 169 La. 1006, 126 So. S08, the Court held that a subcontractor cannot escape responsibility for failure to comply with the express provisions or plans or specifications merely by showing he performed in an average way or in a way suitable to other contractors.

We therefore feel that in the installation of these beams, West Bank was in violation of its contract with Carter, which was a usual and customary form of contract wherein the subcontractor undertook to perform certain labor and furnish certain materials for the erection, construction, and completion of the school as per plans and specifications prepared by the particular architect. By entering into the contract, the subcontractor obligated himself to perform in accordance with the said plans and specifications unless same were changed by the architect or some other responsible party.

With regard to the question of inspection a representative of the architect on the job testified that although there was no requirement in the contract that an inspection be made before the pour, it is better practice for the contractor to let the architect-engineer know. This is because there is a responsibility on the contractor to see that the job is performed in accordance with plans and specifications. Of course, there was also an obligation on the subcontractor to perform in accordance with the plans and specifications.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

O & M Construction, Inc. v. State, Division of Administration
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
O & M CONST. v. State, Div. of Admin.
576 So. 2d 1030 (Louisiana Court of Appeal, 1991)
Eastover Corp. v. Martin Builders
543 So. 2d 1358 (Louisiana Court of Appeal, 1989)
Charles Carter & Co. v. Charles W. Hogg Co.
355 So. 2d 16 (Louisiana Court of Appeal, 1977)
McGowan-Rigsby Sup., Inc. v. CHARLES CARTER & CO. INC.
268 So. 2d 716 (Louisiana Court of Appeal, 1972)

Cite This Page — Counsel Stack

Bluebook (online)
248 So. 2d 52, 1971 La. App. LEXIS 6281, Counsel Stack Legal Research, https://law.counselstack.com/opinion/west-bank-steel-erectors-corp-v-charles-carter-co-lactapp-1971.