Wells v. Board of Education

44 N.W. 267, 78 Mich. 260, 1889 Mich. LEXIS 838
CourtMichigan Supreme Court
DecidedDecember 28, 1889
StatusPublished
Cited by11 cases

This text of 44 N.W. 267 (Wells v. Board of Education) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wells v. Board of Education, 44 N.W. 267, 78 Mich. 260, 1889 Mich. LEXIS 838 (Mich. 1889).

Opinion

Long, J.

On October 18, 1886, tbe' parties to this suit entered into a written contract which, omitting the formal parts, reads as follows:

“ That the said party of the first part agrees to furnish all materials and labor necessary to finish completed the work required in the erection of two two-story brick additions to the brick school-house in the First ward of "West Bay City, Michigan, in accordance with the drawings and specifications thereof drawn by D. P. Clark, and which said drawings and specifications are made a part of this agreement, as much as if written herein.
“It is furthermore agreed by the party of the first part that the work shall be commenced immediately, and pushed forward as rapidly as consistent with good, safe construction, and as the weather will allow; that the building shall be inclosed, and the plastering done, on or-before January 1, 1887, and the entire work finished, ready for occupancy, on or before March 1, 1887, and, in case of failure to complete the work at that date, he shall pay all damages sustained by the party of the second part in consequence thereof, each and every day the work is delayed beyond the time specified through, the fault of the party of the first part, to be retained out of any moneys that may be due and unpaid on this contract.
“It is mutually agreed that the work shall be under the supervision of the architect, who shall have the right to visit and inspect the work, and the power to reject any work or materials not in accordance with the drawings and specifications. And the architect shall also have the power, through the party of the second part, in case of failure of the party of the first part to rectify errors or complete the work within the contract date, to employ other parties to complete the work, at the expense of the party of the first part.
“It is furthermore mutually agreed that, if the party of the second part shall at any time desire any changes in the work, their wishes shall be conceded to and executed by the party of the first part, and the work [263]*263executed in the manner desired, without in any way violating or vitiating this contract; and, in case said changes shall increase the cost of the work, they shall be allowed for, at a fair and reasonable valuation; and, in case the work is diminished thereby, a fair and reasonable deduction shall be made from the contract price agreed upon between the party of the second part and the party of the first part.
“It is further mutually agreed that the work shall be kept fully insured, to cover the interests of both parties as they shall appear, from the moment the roof is on until the work shall be completed and accepted, the insurance to be placed and the premiums to be paid by the party of the second part.
“In consideration of the prompt and faithful performance of the work, and terms of this agreement, the party' of the second part hereby agrees to pay unto the party of the first part, or his legal representatives, the sum of three thousand nine hundred and seventy dollars: (§3,970.00), in manner following: Payments to be made,, as the work progresses, to the amount of seventy-five per cent, of the amount of the architect’s estimate, which shall be made fortnightly, and include only such material and labor as are upon the building site and in the work at the time said estimate is made, until the completion of the work to the satisfaction of the architect, and' thirty days thereafter, at which time the twenty-five per cent, retained, together with all moneys due on the contract, shall be paid unto the party of the first part: Provided, that the work is then in good condition, and there are no claims or liens, from any source whatever, against either party, and that the drawings and specifications have all been returned to the architect.’’

The work was commenced under the contract in October, when the architect, finding the foundation insufficient, directed the contractor to make it broader, and for which §170 additional was to be paid. The plaintiff claims that in performing this additional work he found it difficult to procure stone; and that the architect, on account of unfavorable weather, stopped and delayed him in his work, but that he prosecuted the work diligently, and that it was not delayed through any fault of his; [264]*264and that he did not come within the provision of the contract which made him liable for delay, or that which authorized the architect to take possession and complete the job because it was not finished and completed within the time specified in the contract; that on March 9, 1887, the architect took possession of the work, and plaintiff was prevented from completing it. It is also claimed that when the architect took possession the 'work was nearly finished and that the costs of completion did not exceed $600. The work and material, it is claimed, that were put in the building up to that time by plaintiff amounted to $3,573.47, and the plaintiff had received $2,600. The suit was brought to recover the balance under the contract over and above the amount paid, and the costs of -completion. Plaintiff had judgment for the sum of $675.

It appears that the plaintiff, in making the estimate of the amount he had expended upon the building before the architect took possession, included therein the sum of nearly $1,000 for work and material for which he had not paid. The defendant sought to show that of this indebtedness it had paid, after it took charge of the work, about $386.57, for brick, lime, hardware, and lumber, and that the balance of plaintiff’s said indebtedness still remained unpaid; that the creditors of the plaintiff were looking to the officers of the defendant and the defendant for the payment of such demands; and that a suit was then pending in the circuit court of Bay county to recover from such officers the sum of $108 of such indebtedness. The .court refused to receive evidence upon this subject, and held that the defendant could not gain any advantage by reason of such payments, or from the indebtedness of the plaintiff remaining unpaid.

The defendant also attempted to show the cost of completion of the work, and, in establishing the cost and [265]*265expense, made proofs of the items of labor and material procured and paid for by it, among such items being one of $106, which defendant had paid for material to H. & H. S. Lewis. This was objected to, for the reason that it was not included in the bill of particulars of the defendant’s set-offs. This was excluded by the court, and the defendant, though moving to amend its bill of particulars by inserting this item, was not permitted to do so.

It appears that, before the architect took possession of the work, the plaintiff had made a contract with Mr. Clark to furnish the material and put the slate on the roofs for $160. At the time the defendant took charge of the work a portion of the slate had been put on, and Clark had all the slate on the ground, for its completion. The plaintiff paid Clark nothing upon the contract; and the defendant, after it took charge, arranged with Clark to complete his' contract, and, after its completion, paid him $160, the full contract price. Defendant sought to set this amount off, but the court held that for all the work done 'by Clark while plaintiff was in possession the defendant was liable to the plaintiff in this action, even though the defendant had paid Clark for the work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Kammer Asphalt Paving Co. v. East China Township Schools
504 N.W.2d 635 (Michigan Supreme Court, 1993)
Paxton & Vierling Iron Works v. Village of Naponee
186 N.W. 976 (Nebraska Supreme Court, 1922)
Crowe v. Boyle
193 P. 111 (California Supreme Court, 1920)
Lake Shore Stone Co. v. Westgate
179 N.W. 264 (Michigan Supreme Court, 1920)
C. A. Burton Machinery Co. v. Ruth
186 S.W. 737 (Missouri Court of Appeals, 1916)
Smith v. Hubbell
106 N.W. 547 (Michigan Supreme Court, 1906)
Huebner v. Nims
94 N.W. 180 (Michigan Supreme Court, 1903)
Stephenson v. Monmouth Min. & Mfg. Co.
84 F. 114 (Sixth Circuit, 1897)
Arndt v. Keller
71 N.W. 651 (Wisconsin Supreme Court, 1897)
Weinberg v. Regents of University
56 N.W. 605 (Michigan Supreme Court, 1893)

Cite This Page — Counsel Stack

Bluebook (online)
44 N.W. 267, 78 Mich. 260, 1889 Mich. LEXIS 838, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wells-v-board-of-education-mich-1889.