Weber v. Milpitas County Water District

201 Cal. App. 2d 666, 20 Cal. Rptr. 45, 1962 Cal. App. LEXIS 2644
CourtCalifornia Court of Appeal
DecidedMarch 22, 1962
DocketCiv. 19242
StatusPublished
Cited by1 cases

This text of 201 Cal. App. 2d 666 (Weber v. Milpitas County Water District) is published on Counsel Stack Legal Research, covering California Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Weber v. Milpitas County Water District, 201 Cal. App. 2d 666, 20 Cal. Rptr. 45, 1962 Cal. App. LEXIS 2644 (Cal. Ct. App. 1962).

Opinion

TOBRINER, J.

The specific provision of a contract requiring the contractor to obtain “all necessary permits” must prevail over the conjectural theories of the contractor that the custom of the industry, an “implied condition” of the contract, or an estoppel, casts the duty upon the district of procuring an encroachment permit for the performance of pipe installation work on the highway. Neither can we find any statutory provision that imposes this responsibility upon the district. We are, therefore, constrained to hold that the trial *668 court erred in positing damages against the district because of the lateness of the issuance of the permit, particularly when the contractor did not show that the charged negligence of the district delayed the issuance of the permit or, indeed, that the contractor himself could have obtained it sooner. We are likewise unable to find any basis for damages against the district because of faulty design of the water system.

As we have stated above, the first issue of the case involved the provisions of the contract and the actions of the parties with respect to the procurement of a so-called encroachment permit. On October 13, 1953, Matthew Weber, a general contractor (hereinafter referred to as “the contractor”), entered into an agreement with Mark Thomas & Co., district engineers for the Milpitas County Water District (hereinafter referred to as “the district”), to install a system for the distribution of water in Milpitas County Water District. The contract required the contractor to commence the work within 10 days and complete performance within 120 days of the formation of the contract. Since the major portion of the work involved laying pipe along State Highway 17, the job could not be performed unless an encroachment permit were procured pursuant to the Streets and Highways Code.

The specifications annexed to the contract provided, “The Contractor shall, at his expense, obtain all necessary permits and licenses for the construction of the project, give all necessary notices, pay all fees required by law, and comply with all laws, ordinances, rules and regulations relating to the work and to the preservation of the public health and safety.” (Emphasis added.) Nevertheless, the contractor did not at any time apply for such an encroachment permit. The water district did apply for the permit on July 27, 1953, nearly three months prior to the formation of the contract. The Division of Highways, however, issued the permit to the water district (e/o Mark Thomas Company) as of December 8, 1953, and on December 13, 1953, the contractor was so informed.

Between the date of formation of the contract and the time of the issuance of the permit, the parties engaged in correspondence regarding the permit. The contractor sent two letters to the district, one dated October 30, 1953, which stated that a Mr. Savio of Mark Thomas & Co. had advised the contractor that he could not proceed until a sewer contractor had finished his work, and that the district had not yet obtained the permit. The second letter, dated November 23, 1953, stated that the contractor was unable to commence work *669 because the sewer contractor had still not completed his operations.

Due to the delay in obtaining the permit the contractor did not complete performance under the contract prior to the onset of winter rains. In order to avoid penalties for delayed performance the contractor requested the district to extend the time for the completion of the contract, and it did so, continuing the period from the original terminal date to July 10, 1954. The wet weather, which intervened, necessitated additional work to prevent interference with the normal flow of traffic.

Moreover, in the laying of the pipe, numerous leaks occurred, requiring additional work on the part of the contractor. He now contends that these leaks resulted from the inadequate size of the pipe used; that the district knew that working pressures would exceed the 150 pound test pressure. Although the contractor contends that the specifications annexed to the contract called for the installation of class 150 asbestos pipe, examination of the specifications discloses as the only provision regarding size of pipe the following paragraph: “2.5—Asbestos-Cement Pipe: The pipe shall be asbestos-cement water pipe in the sizes indicated on the Plans and shall conform to the Tentative Standard Specifications for Asbestos-Cement Pipe, approved as tentative on May 15, 1953, by the American Water Works Association and published as AWWA C400-53T. The Contractor shall furnish at the request of the District Engineers a sworn statement by the manufacturer of said pipe that the requirements of the Standard Specifications hereinabove referred to, have been met.” Perhaps the contractor means to state that the “test pressure” required in the specifications was 150 pounds per square inch, which under such “Tentative Standard Specifications” called for class 150 pipe.

Two engineers testified that this type of pipe sufficed for this project. Although the above mentioned “Tentative Standard Specifications” states that class 150 pipe should be used for maximum working pressures of 150 pounds, the expected pressure here reached 160-165 pounds. The evidence discloses that on some projects the district now uses class 200 pipe, but that it also utilizes class 150 pipe. Moreover, class 150 pipe was installed in another water line constructed at about the same time and subject to the same working pressures as that involved here; yet that line experienced only the normal number of leaks. Some testimony indicates that *670 the contractor’s workmen did not lay the pipe carefully and that many leaks resulted both from the type of joint used and improper joining of the pipes.

Turning to the complaint, we note that it alleges four causes of action. The first two counts refer to the district’s alleged failure to procure an encroachment permit; the third and fourth causes pertain to the district’s alleged improper design of the water system. Thus the contractor alleges in the first count that the contractor and the district entered into a contract which required the district under the laws of California to obtain the permit and that it negligently failed to do so, thereby causing the contractor additional expenses. The second count essentially duplicates the first, with the exception that here the contractor alleges breach of an implied covenant or condition requiring the district to procure an encroachment permit.

The third cause alleges that the district negligently designed the water system in that the specifications annexed to the contract provided for a class of asbestos pipe which proved insufficient to withstand the encountered pressures in the system. The contractor, at an added cost of $10,000, repaired the leaks caused by the district’s claimed negligence. Alleging substantially the same facts as the third cause, the fourth count differs from it only in that here the contractor claims the existence of an implied covenant that the water system had been properly designed and that the district wrongfully breached this covenant.

The trial court found that all of the allegations in the first two causes were correct, but fixed the amount of damage due to the extra work at $4,000 instead of $8,000.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Bert G. Gianelli Distributing Co. v. Beck & Co.
172 Cal. App. 3d 1020 (California Court of Appeal, 1985)

Cite This Page — Counsel Stack

Bluebook (online)
201 Cal. App. 2d 666, 20 Cal. Rptr. 45, 1962 Cal. App. LEXIS 2644, Counsel Stack Legal Research, https://law.counselstack.com/opinion/weber-v-milpitas-county-water-district-calctapp-1962.