Webb v. Depew

116 N.W. 560, 152 Mich. 698, 1908 Mich. LEXIS 917
CourtMichigan Supreme Court
DecidedMay 26, 1908
DocketDocket No. 97
StatusPublished
Cited by11 cases

This text of 116 N.W. 560 (Webb v. Depew) is published on Counsel Stack Legal Research, covering Michigan Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Webb v. Depew, 116 N.W. 560, 152 Mich. 698, 1908 Mich. LEXIS 917 (Mich. 1908).

Opinion

Mooke, J.

This suit was brought in justice’s court on July 3, 1907. The plaintiff filed a written declaration containing a special count alleging a contract, breach and damages, and the common counts, with bill of particulars' attached. The defendant pleaded the general issue and gave notice of justification for the discharge of plaintiff and a set-off. The case was tried in justice’s court before a jury, and on July 17,1907, a judgment was rendered in favor of plaintiff for $190. Defendant appealed the case to the circuit court and on September 25, 1907, it came on for trial before a jury.

Counsel for plaintiff in his openiúg statement said that plaintiff and her daughter, Anna, were employed by defendant as domestics at defendant’s summer home near Muskegon, Michigan, for a period .from about June 21, 1907, to such time as defendant should leave said summer home, but to at least October 1, 1907; that after plaintiff and her daughter had worked for defendant under this contract for about ten days’, they were discharged by defendant without cause; that this suit was then instituted to recover the wages plaintiff and her daughter had already earned and damages for breach-of the contract on the part of defendant.

After the opening statement had been made, and before any evidence had been introduced, the trial court made a ruling that - plaintiff would be limited to recover such damages only as had accrued from the date of her discharge by defendant to the date of trial in justice’s court, a period of 17 days. To this ruling plaintiff’s counsel excepted.

Plaintiff’s counsel contended that, if the rule adopted [700]*700by the court was correct, plaintiff was still entitled to recover such damages as had accrued from the date of her discharge to the date when the case was tried in circuit court. The trial court held that the case must be determined as it existed in justice’s court, and no damages could be recovered beyond that time, to which ruling plaintiff’s counsel excepted.

The assignments of error are discussed by counsel under two heads:

First. The court erred in holding that plaintiff could not recover damages for the whole contract period, but that she was limited in her recovery to such damages as had accrued at the time of the trial in justice’s court.

Second. The court erred in not allowing plaintiff to recover such damages as had accrued up to the time of the trial in circuit court.

Before proceeding to discuss the two heads presented by counsel for appellants, some attention must be given to the contention of counsel for defendant. It is claimed the verdict was a consent verdict and not appealable. We do not so understand the record. The plaintiff claimed the right to prove her damages in full, but the court ruled she could not make proof of damages later than the date of trial in justice’s court. Exception was duly taken and the action of the court is reviewable.

• It is claimed the special count is not for a breach of the contract, but is an action on the contract to recover plaintiff’s wages. We do not agree with this contention. The special count set out the contract and its breach. A bill of particulars was filed, one item of which reads:

“ To damage by breach of contract being what plaintiff and daughter would have earned if allowed to complete contract, $144.”

Under her plea, defendant gave notice of justification for the discharge of plaintiff and her daughter. The defendant was not misled. See Costello v. Ten Eyck, 86 Mich. 348.

We now come to the important question and that is, [701]*701Was the trial court right in relation to the measure of damages ? An examination of the authorities will show that there is a hopeless conflict in them. The precise question is a new one in this State. This court has held that, in case of a contract for life, or during one’s ability and disposition to perform the duties of- his position, prospective damages are recoverable in an action for its breach, and that the plaintiff is entitled to recover such a sum as represents fairly and reasonably the extent of his loss, the measure of damages being the present value of the contract. Brighton v. Railway Co., 103 Mich. 420, 112 Mich. 217; Stearns v. Railway Co., 112 Mich. 651.

In Cutter v. Gillette, 163 Mass. 95, it was said:

“The remaining question is whether the jury should have been allowed to assess damages for the period of time subsequent to the trial. The plaintiff was hired for five years from April 25, 1892, and was discharged about the middle of July, 1892. He brought suit on November 10,1892, and the verdict was rendered on March 14,1894. The verdict assessed at the sum of $3,180.95 the plaintiff’s whole damages for breach of the contract for hiring, and stated that of the amount $1,392.95 was the damage to the time of trial. The defendant concedes that the plaintiff is entitled to recover damages for an entire breach, so far as such damages can be ascertained, but contends that, as the trial occurred before the expiration of the contract period, it was impossible for the jury to ascertain or assess the damage for the unexpired portion of the contract period subsequent to the time of trial. In support of this contention defendant cites the cases of Colburn v. Woodworth, 31 Barb. (N. Y.) 381, Fowler v. Armour, 24 Ala. 194, Litchenstein v. Brooks, 75 Tex. 196, and Gordon v. Brewster, 7 Wis. 355, in which cases it seems to have been held that, if the suit is begun before the- expiration of the contract period, damages can only be allowed to the time of the trial. He asserts that in the case of Howard v. Daly, 61 N. Y. 362, in which full damages were given, the writ was brought after the expiration of the contract period. On the other hand it has been held in Vermont that, if there has been such a breach as to authorize the plaintiff to treat it as entirely putting an end to the contract, he may recover damages for an [702]*702entire non-fulfillment, and is not limited to what he has actually sustained at the time of his bringing suit or the time of trial. Remelee v. Hall, 31 Vt. 582. And in Maine, in an action for breach of a contract for hiring, brought before the expiratiou of the contract period, it was held that the just recompense for the actual injury sustained by the illegal discharge was the stipulated wages, less whatever sum the plaintiff actually earned, or might have earned by the use of reasonable diligence. Sutherland v. Wyer, 67 Me. 64.

/“ Such would seem to be the rule in Pennsylvania. See King v. Steiren, 44 Pa. 99; Chamberlin v. Morgan, 68 Pa. 168. And the defendant concedes that such is the rule in England. We do not go into an exhaustive consideration of the decisions upon the question, as we consider it to have been settled in favor of the ruling given at the trial by our decisions. Dennis v. Maxwell, 10 Allen (Mass.), 138; Blair v. Laflin, 127 Mass. 522; Jewett v. Brooks, 134 Mass. 505; Paige v. Barrett, 151 Mass. 67. See, also, Warner v. Bacon, 8 Gray (Mass.), 397, 408; Amos v. Oakley, 131 Mass. 413; Parker v. Russell, 133 Mass. 74; Drummond v. Crane, 159 Mass. 577, 581 (23 L. R. A. 707).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Reinardy v. Bruzzese
118 N.W.2d 952 (Michigan Supreme Court, 1962)
Dixie Glass Co. v. Pollak
341 S.W.2d 530 (Court of Appeals of Texas, 1960)
Goesaert v. Cleary
74 F. Supp. 735 (E.D. Michigan, 1947)
Arnold v. Masonic Country Club
256 N.W. 472 (Michigan Supreme Court, 1934)
Gallino v. Boland
191 N.W. 222 (Michigan Supreme Court, 1922)
Granow v. Adler
206 P. 590 (Arizona Supreme Court, 1922)
Lamar v. Hildreth
209 S.W. 167 (Court of Appeals of Texas, 1919)
Helfferich v. Sherman
134 N.W. 815 (South Dakota Supreme Court, 1912)
Elkhart Rubber Works v. Neff
92 N.E. 553 (Indiana Court of Appeals, 1910)

Cite This Page — Counsel Stack

Bluebook (online)
116 N.W. 560, 152 Mich. 698, 1908 Mich. LEXIS 917, Counsel Stack Legal Research, https://law.counselstack.com/opinion/webb-v-depew-mich-1908.