Wayne Sewer & Drain Co. v. Ward-Cowan Construction Co.

143 N.E. 290, 195 Ind. 75, 1924 Ind. LEXIS 110
CourtIndiana Supreme Court
DecidedApril 2, 1924
DocketNo. 24,035.
StatusPublished
Cited by1 cases

This text of 143 N.E. 290 (Wayne Sewer & Drain Co. v. Ward-Cowan Construction Co.) is published on Counsel Stack Legal Research, covering Indiana Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wayne Sewer & Drain Co. v. Ward-Cowan Construction Co., 143 N.E. 290, 195 Ind. 75, 1924 Ind. LEXIS 110 (Ind. 1924).

Opinion

Gause, J.

This action was brought by appellee against appellants to recover damages for the alleged breach of a contract. From a judgment for appellee in the sum of $25,267.58 appellants appeal.

The alleged error which appellants discuss relate to the action of the court in overruling the motion for a new trial.

Appellants say in their reply brief that, “The decision of this case depends entirely on the construction to be placed on the contract entered into between the Wayne Sewer & Drain Company as owner and the Ward-Cowan Construction Company as the contractor.”

The question that is decisive of this case arises upon *78 certain instructions given by the court and certain ones requested by appellants and refused.

. By a written contract dated January 11, 1917, the appellee, as contractor, agreed to construct a certain sewer for appellant, The Wayne Sewer and Drain Company, herein referred to as the owner, for the sum of $7.50 per lineal foot. The appellant Speedway Realty Company guaranteed the performance of said contract on behalf of said owner. The contractor was to furnish the material and labor for such work, except that the owner was to manufacture the cement tile with which the sewer was to be constructed, the material for such tile, however, to be furnished by the contractor. The contractor deposited with the owner the sum of $10,000 in cash, which was to be held by the owner as security for the faithful performance of such contract and the payment of all labor and material claims. The dispute arises over the construction to be given to item 13 of said contract relating to the manner of payments on said work.

Said section 13 is as follows: “13. The Owner shall make payment in full to the material men and laborers, for material, labor appliances and construction of the drain and sewer specified in this contract, in the construction thereof, upon the approval of the claims by the Contractor, within five (5) days after the 1st and 15th days of each month, which shall be deducted from eighty-five (85%) per cent, of the work done, on the basis of seven and fifty hundredths ($7.50) dollars per lineal foot, and eighty-five per cent, of the contract price likewise' paid the Contractor, less the previous payments, except that the cement for which the Owner shall pay in full as it is delivered on the ground, and payments for the cement deducted from the semi-monthly statements.

“Provided, always, that the Contractor shall pay for *79 the services of a time-keeper, or some one to keep the accounts, in order that the Owner may have the data for the material, labor and work done, upon which to base the payments to be made hereunder, such expense not to exceed the sum of five hundred ($500.00) dollars on the entire job.

“Provided further, that the Owner shall not be required to pay the expense, or any part of it, in placing the machinery on the ground, or setting it up ready for operation, and payment in full shall be made within fifteen (15) days after the completion and acceptance of the work, and the ten thousand ($10,000.00) dollars security returned to the Contractor, provided there shall then exist no claims for labor or material, or damages, or liability, for damages, as herein provided, in which, or either of said events, said ten thousand ($10,000.00) dollars shall be held- by the Owner until the same are paid, or the liability discharged, as provided in the eleventh clause of this contract, but payments on the work as it progresses, shall not be held or treated as an acknowledgment of the performance or completing the work in accordance with the terms of the contract, if the work shall not have been done and completed according to the contract.

“Provided further, that payment shall only be made for work done, and amounts due, upon the certificate of the engineer in charge of the work, as to the amounts then due less the fifteen (15%) per cent, retained, and the previous payments for material and labor.”

Said contract also contained the following provision: “18. The time of payments to be made by the owner to the contractor is hereby made the essence of this contract and in the event of the failure of the owner to make payments to the contractor as hereinabove set forth, then the contractor shall have the right to forthwith terminate this contract, and have the right to the *80 payment of the amounts then due it, and to the recovery of such damages as it may be legally entitled to for breach of this contract by the owner.”

The contractor stopped work and refused to complete the contract when the sewer was only partially completed, claiming that the owner had breached its agreement by refusing to make certain payments to the contractor, and also to materialmen and laborers. At the time the contractor stopped work the owner was claiming that it was only required to pay out for labor and material, including cement, eighty-five per cent, of the value of the work that was completed, and it had refused to pay for labor or material, including cement, furnished in excess of eighty-five per cent, of the value of such completed work.

The contractor contended that under the contract the owner was to pay the laborers and materialmen in full, including payment in full for the cement, and that the eighty-five per cent, limitation only applied to the payments that were to be made to the contractor, except that prior payments for labor and material were to be credited before anything was to be paid the contractor. If the contractor is correct in the above contention, then the owner was in default and the contractor had the right to abandon the contract and recover for the work done and damages.

We think that under said contract the owner was to pay in full to the laborers and materialmen for the labor and material, said payments to be made semi-monthly, and was to pay in full for the cement when delivered; that the contractor was to receive eighty-five per cent, of the value of the work done, also payable semi-monthly, but that the 'payments to the contractor were to be reduced by the amounts paid to laborers and materialmen. If the amount paid out for labor and material equalled or exceeded eighty- *81 five per cent, of the value of work done, then nothing was to be paid the contractor at such times.

The provision that the materialmen and laborers were to be paid in full is clear and means just what it says, namely, that they were to be paid in full, not that eighty-five per cent, of the work done was to be distributed among them. The effect of this provision is not limited by the provision that what is paid to them shall be deducted from eighty-five per cent, of the work done, but this latter provision regulates the amount to be paid to the contractor. The contractor can receive nothing until eighty-five per cent, of the work done is sufficient to pay the laborers and materialmen, and then if such eighty-five per cent, exceeds the amount necessary for that purpose, the contractor is entitled to the balance of said eighty-five per cent. If the amount paid out for labor and materials equals or exceeds eighty-five per cent, of the work done, then the contractor would not be entitled to any payments so long as that condition existed, until the contract was completed.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Couch v. Southern Railway Co.
14 N.E.2d 266 (Appellate Court of Illinois, 1938)

Cite This Page — Counsel Stack

Bluebook (online)
143 N.E. 290, 195 Ind. 75, 1924 Ind. LEXIS 110, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wayne-sewer-drain-co-v-ward-cowan-construction-co-ind-1924.