Wayne H. Coloney Co. v. US Dept. of Air Force

35 Cont. Cas. Fed. 75,543, 89 B.R. 924, 1988 Bankr. LEXIS 1271
CourtUnited States Bankruptcy Court, N.D. Florida
DecidedAugust 8, 1988
Docket19-40052
StatusPublished
Cited by5 cases

This text of 35 Cont. Cas. Fed. 75,543 (Wayne H. Coloney Co. v. US Dept. of Air Force) is published on Counsel Stack Legal Research, covering United States Bankruptcy Court, N.D. Florida primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wayne H. Coloney Co. v. US Dept. of Air Force, 35 Cont. Cas. Fed. 75,543, 89 B.R. 924, 1988 Bankr. LEXIS 1271 (Fla. 1988).

Opinion

FINDINGS OF FACT AND CONCLUSIONS OF LAW

LEWIS M. KILLIAN, Jr., Bankruptcy Judge.

On March 12, 1986, Wayne H. Coloney Company, Inc. (“Coloney”) filed a complaint to (1) determine the dischargeability of a debt asserted against Coloney by the United States of America, Department of the Air Force (the “Air Force”) and (2) obtain a declaratory judgment and other equitable relief. Coloney filed a petition under Chapter 11 of the Bankruptcy Code on August 13, 1982, a plan of reorganization was thereafter confirmed on May 23, 1983, and the case was closed by a Final Decree entered by this Court on April 24, 1985. The case was reopened on December 2, 1985, to allow the filing of this action.

Prior to the filing of its Chapter 11 case, a substantial portion of Coloney’s income had been derived from work performed pursuant to contracts with the United States government and in particular with the Air Force. On July 10, 1985, the Air Force informed Coloney that, in accordance with the price redetermination provisions of one such contract, the Defense Contract Audit Agency (DCAA) had issued its Advisory Report to Establish a Final Price on Fixed Price Incentive Contract F33657-77-C-0451 (the “Final Advisory Report”) wherein it had concluded that the Air Force had over paid Coloney the sum of $1,520,-534.00 (the “Air Force Claim”). Coloney asserts that the AF Claim is based upon a contract that was completed pre-petition, that the contract was not executory and was not assumed by Coloney in its plan of reorganization, and that any debt to the Air Force based upon that contract was discharged by confirmation of its plan pursuant to 11 U.S.C. § 1141. The Air Force, on the other hand, asserts that the debt was not a claim against the estate and thus not subject to discharge. The Air Force further maintains that, even if a claim did exist prior to confirmation, the contract was executory and was assumed in Colo-ney’s plan; therefore, Coloney remains bound by all of its terms including those dealing with redetermination of the contract price.

This is a proceeding arising under Title 11, and the Court has determined that it has jurisdiction over this matter under 28 U.S.C. § 1334(b). The issues raised in this case involve Title 11 questions of law; therefore, pursuant to 28 U.S.C. § 157(b)(3), the Court has determined that this is a core proceeding under 28 U.S.C. § 157(b)(2). Having considered the evidence and argument of counsel, the Court makes the following findings of fact and conclusions of law:

On October 18,1977, Coloney and the Air Force entered into a contract, designated by Procurement Instrument Identification Number (PUN) F33657-77-C-0451 and referred to as the “0451 Incentive Price Contract,” by which Coloney was to design, manufacture and deliver to the Air Force: *926 (1) 48 ammunition loaders, (2) 36 auxiliary power units to be used in connection with the ammunition loaders, (3) ammunition containers, (4) spare parts from the date of delivery until 120 days after final delivery of the ammunition loaders, and (5) engineering and technical data to assist the Air Force in using the ammunition loaders. The Air Force subsequently exercised its options under the 0451 Incentive Price Contract to take delivery of an additional 48 ammunition loaders. The price terms of the contract called for payment of Colo-ney’s cost plus a profit. 1 Pursuant to the terms of the contract, the final amount paid to Coloney was subject to redetermination upon completion of the contract.

Upon completion of its obligations under the 0451 Incentive Price Contract, Coloney was required to submit a report to the Air Force setting forth all costs incurred by Coloney in performing its obligations under the contract (the “Price Redetermination Proposal”) and to deliver to the Air Force all government inventory remaining in Coloney’s possession relating to the contract. Coloney made its last delivery under the 0451 Incentive Price Contract on April 22, 1982, submitted its Price Redetermination Proposal, and returned the government inventory to the Air Force. On June 6, 1982, two months prior to the filing of Coloney’s Chapter 11 petition, the Air Force made its final payment on the 0451 Incentive Price Contract bringing the total price actually paid by the Air Force to Coloney to $25,-131,711. On May 19, 1983, four (4) days prior to confirmation of Coloney’s plan, the DCAA issued the Final Advisory Report to the Air Force, in which the DCAA concluded that the Air Force should not have reimbursed Coloney for $1,520,534 of the costs incurred under the 0451 Incentive Price Contract. The Final Advisory Report was the result of the DCAA’s audit of the costs incurred under the 0451 Incentive Price Contract, which audit began in April, 1980 (pre-petition), and was completed in March, 1983 (pre-confirmation). Both the Air Force contracting officers and several employees at Coloney were aware before the audit was complete that there may be questions concerning some of the cost items; however, Coloney was not informed of the existence of the Final Advisory Report or its contents until a meeting held on July 10, 1985, at Coloney’s offices.

The Air Force filed two proofs of claim during the pendency of the Coloney case. The first, claim number 200 filed on October 27, 1982, in the amount of $4,702,-165.10, was for unliquidated progress payments made to Coloney on various contracts which Coloney claimed it was continuing to perform. Claim 200 listed an amount due of $763,127.93 based on unliq-uidated progress payments associated generally with the 0451 Contract including all of its related changes, modifications, and supplemental agreements. That claim was eventually disallowed by order of this Court on June 28, 1983. The second claim, claim number 332 in the amount of $457,-056.36, was filed on September 19, 1984, one year and four months after issuance of the DCAA Final Advisory Report and confirmation of Coloney’s plan. It too was based upon unliquidated progress payments, $454,251.06 of which were attributable to the 0451 Contract and its related changes, modifications, and supplemental agreements. Neither claim made any reference to or asserted any part of the $1,520,534 Air Force Claim which is the subject of this case.

On September 27, 1979, Coloney entered into another contract with the Air Force, designated by the PUN F33657-79-C-0806-PZ0001 and referred to as the “0806 Fixed Price Contract”, by which Coloney was to (1) manufacture an additional 112 ammunition loaders, and (2) deliver engineering and technical data to assist the Air *927 Force in using the ammunition loaders. The ammunition loaders produced under this contract were substantially similar to those produced under the 0451 Incentive Price Contract.

During the term of the 0451 Incentive Price Contract and subsequent to its completion, Coloney and the Air Force entered into various “supplemental agreements” or “contract modifications” to the 0451 Incentive Price Contract. The following five such agreements are material to this adversary proceeding:

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Missouri Breaks, LLC v. Burns
2010 ND 221 (North Dakota Supreme Court, 2010)
In Re Wilbur
237 B.R. 203 (M.D. Florida, 1999)
In Re Royster Co.
137 B.R. 530 (M.D. Florida, 1992)

Cite This Page — Counsel Stack

Bluebook (online)
35 Cont. Cas. Fed. 75,543, 89 B.R. 924, 1988 Bankr. LEXIS 1271, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wayne-h-coloney-co-v-us-dept-of-air-force-flnb-1988.