Watts Bros. Builders, Inc. v. Altex Ready Mix Concrete Corp.

349 So. 2d 1304, 1977 La. App. LEXIS 4339
CourtLouisiana Court of Appeal
DecidedJune 13, 1977
DocketNos. 11335, 11336
StatusPublished
Cited by3 cases

This text of 349 So. 2d 1304 (Watts Bros. Builders, Inc. v. Altex Ready Mix Concrete Corp.) is published on Counsel Stack Legal Research, covering Louisiana Court of Appeal primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Watts Bros. Builders, Inc. v. Altex Ready Mix Concrete Corp., 349 So. 2d 1304, 1977 La. App. LEXIS 4339 (La. Ct. App. 1977).

Opinion

LANDRY, Judge.

In these consolidated actions, appeals have been taken by Altex Ready Mix Concrete Corporation (Altex), and Anderson Dunham, Inc. (Dunham), from judgments rejecting their demands for recognition of their alleged materialmen’s liens and privileges against Watts Brothers Builders, Inc. (Watts), owners and developers of a subdivision, and Hanover Insurance Company (Hanover), surety on the performance bond provided by John P. Cryer Construction Company (Cryer), who contracted to perform the construction work on Watts’ subdivision. We affirm in part, reverse in part and render judgment in favor of Altex and Dunham against Hanover.

The issues presented are: (1) The alleged applicability of LSA-R.S. 9:4816(A), pertaining to the filing of liens against con[1307]*1307struction of two or more buildings or works by a single general contractor under a single building contract when buildings or works are situated on adjacent lots or parcels of land of a single owner; (2) Were the liens of Altex and Dunham timely filed so as to create a privilege against Watts’ land and improvements; and, (3) Did Altex and Dunham timely file direct actions against Hanover.

There is virtually no dispute as to the operative facts. On April 6, 1973, Watts purchased a tract of land for development into a residential subdivision. For purely economic and business reasons, Watts elected to divide the land into two subdivisions, designated as Woodland Ridge Sixth Filing and Woodland Ridge Seventh Filing, for purposes of development. Watts also elected to first construct the streets, sewers and sidewalks for the Sixth Filing and subsequently build the streets, sewers and sidewalks for Seventh Filing, dovetailing the latter work into the former. In furtherance of the plan, Watts entered into two written contracts with Cryer on April 12, 1973, one to construct the sewer system in Sixth Filing for $20,443.10, and the other for streets, drainage and sidewalks in Sixth Filing for $93,717.00. Performance bonds for both contracts were written by Hanover, through its alleged agent, Virgil Seale, in the stated contract amounts. Both contracts and bonds were timely recorded. Certificates of substantial completion of the sewer contract and the streets, drainage and sidewalk contracts were recorded by Watts January 28, 1974, and January 29, 1974, respectively. As a further precaution, Watts recorded an additional acceptance of both Sixth Filing contracts on May 8, 1974. On June 24, 1974, Watts was issued a clear lien certificate by the Clerk of Court.

The sale of lots in the Sixth Filing development exceeded Watts’ expectations to such extent that prior to completion of said work, Watts signed a contract with Cryer, on July 18, 1973, for construction of the sewer system, streets, drainage and sidewalks on the Seventh Filing for the sum of $63,780.00. Hanover bonded this contract for Cryer at the contract price, which contract and bond were duly recorded. A certificate of acceptance was filed on July 18, 1974, for the Seventh Filing work and a clear lien certificate with respect thereto was issued by the Clerk of Court on September 9, 1975.

On October 11,1974, Dunham liened both the Sixth and Seventh Filing work in the sum of $37,186.09, for concrete and pipe furnished the projects, which claim was judicially reduced to $32,334.43. Altex liened both projects, for concrete furnished, on October 22, 1974, in the amount of $30,-545.01.

Watts obtained bonds to secure the Dun-ham and Altex liens and filed suit to cancel the liens. Alternatively, Watts prayed for reduction of his bonds to the amount allegedly due Dunham and Altex, should their claims be held valid. Dunham and Altex reconvened in Watts’ cancellation suit, urging recognition of their liens and alleging their unawareness of two construction contracts. They also alleged that work on both constructions was continuous and that the subdivision was not substantially complete upon recordation of the acceptances filed. Both Dunham and Altex third partied Cryer and Hanover, in solido, for the amount of their respective claims.

On June 4, 1975, Watts filed an amended and supplemental petition, making both Cryer and Hanover defendants in the main demand.

On July 24, 1975, Hanover answered Watts’ original and supplemental petitions, alleging Watts still held some monies owed Cryer on the contracts. Hanover also urged the invalidity of the bond issued by their alleged agent, Virgil L. Seale, Jr., because Seale’s agency had been previously revoked. Additionally, Hanover filed a peremptory exception of no cause of action against Altex, predicated on Altex having asserted a third party demand against Hanover, independent of Watts’ main demand, [1308]*1308and therefore in contravention of LSA-C. C.P. Article 1111.

On October 8, 1975, Dunham filed suit Number 11,336 against Watts, Cryer and Hanover, based on the same claims asserted in Dunham’s third party demand in Watts’ action to cancel the liens.

Both suits were consolidated for trial, following which the trial court found the January 28 and 29,1974, acceptances of the Sixth Piling were premature, but that the work on the Sixth Piling was substantially complete for the use for which it was intended, as of the May 8, 1974, acceptance. He also found that the liens filed by Altex and Dunham on October 11 and 22, 1974, against the Sixth Filing work, were untimely and did not preserve a lien against the Sixth Piling work.

As to the Seventh Filing work, the trial court held the July 18, 1974, filing of acceptance was premature, and that said work was complete as of August 26, 1974. On this basis, the trial court held the liens filed against the Seventh Filing on October 11 and 22, 1974, were untimely, and did not meet the requirements of LSA-R.S. 9:4802.

As regards Hanover’s bonds, the trial court held them valid because he found Seale was acting as Hanover’s agent with apparent authority. The trial court also held the third party demands of Altex and Dunham against Hanover to be proper but nevertheless dismissed them as being moot. Dunham’s direct action against Hanover was dismissed on the ground that said cause of action prescribed because Dunham did not bring that suit until October 8, 1975. Altex and Dunham were given judgment by default against Cryer. A retainage of $13,430.38, held by Watts, was equally divided between Altex and Dunham.

Altex and Dunham have appealed. No other party has appealed or answered the appeals of Altex and Dunham.

EFFICACY OF THE ALTEX AND DUNHAM LIENS

Altex and Dunham maintain the trial court erred in not finding the Sixth and Seventh Filings to be one continuous phase of the subdivision development such that the lien filing period should date from completion or acceptance of the Seventh Filing, as provided for by LSA-R.S. 9:4816(A), which recites:

“Any person furnishing service or material or performing any labor for the contemporaneous and continuous construction or improvements of two or more buildings or works by a single general contractor under a single construction contract which buildings or works are situated on adjacent lots or parcels of land of a single owner, may file a single privilege upon all said buildings or works upon the lands on which they are situated. Such a privilege shall secure the payment in principal and interest of the entire amount due for all service, material or labor, furnished and performed, and the costs for recording said privilege.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Southmark Corp. v. Ellis Millwork, Inc.
535 So. 2d 507 (Louisiana Court of Appeal, 1988)
Lake Forest, Inc. v. Cirlot Co.
466 So. 2d 61 (Louisiana Court of Appeal, 1985)
Watts Bro. Builders, Inc. v. Altex Ready Mix Concrete Corp.
352 So. 2d 1032 (Supreme Court of Louisiana, 1977)

Cite This Page — Counsel Stack

Bluebook (online)
349 So. 2d 1304, 1977 La. App. LEXIS 4339, Counsel Stack Legal Research, https://law.counselstack.com/opinion/watts-bros-builders-inc-v-altex-ready-mix-concrete-corp-lactapp-1977.