Waterview Site Service, Inc. v. Pay Day, Inc.

11 A.3d 692, 125 Conn. App. 561, 2010 Conn. App. LEXIS 565
CourtConnecticut Appellate Court
DecidedDecember 21, 2010
DocketAC 30982
StatusPublished
Cited by7 cases

This text of 11 A.3d 692 (Waterview Site Service, Inc. v. Pay Day, Inc.) is published on Counsel Stack Legal Research, covering Connecticut Appellate Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Waterview Site Service, Inc. v. Pay Day, Inc., 11 A.3d 692, 125 Conn. App. 561, 2010 Conn. App. LEXIS 565 (Colo. Ct. App. 2010).

Opinion

Opinion

ALVORD, J.

This appeal arises from a business disagreement between the plaintiff, Waterview Site Services, Inc., and the defendant, Pay Day, Inc. On appeal, the defendant claims that the court improperly found that (1) the defendant consented to the work that the plaintiff performed, (2) the mechanic’s lien was filed in a timely manner and (3) the defendant was unjustly enriched in the amount of $224,959.24. The plaintiff filed a cross appeal challenging the court’s decision that, in calculating the unjust enrichment award, it would credit the defendant for an amount equal to the fair rental value owed by the plaintiff for occupying the land. We disagree with the claims raised by both parties and, accordingly, affirm the judgment of the trial court.

The following facts and procedural history are relevant to our resolution of the issues on appeal. James R. DeVito, a general contractor, is a partial owner of the plaintiff. Salvatore DiNardo is a real estate investor who serves as an officer and owner of numerous companies, including his partial ownership interest in the defendant. DeVito and DiNardo have a lengthy history of doing business with each other, often through their respective corporations.1

In 2001, the defendant purchased 575 Asylum Street, Bridgeport, a vacant lot in an industrial area (property). [564]*564The property was overgrown and had been unoccupied for a number of years. Subsequently, DeVito and DiNardo entered into an oral agreement allowing the plaintiffs use and occupancy of the property. The individuals offered conflicting testimony as to the terms of this agreement. The plaintiff argues that both parties expected the performance of extensive site improvements, the cost of which would be shared equally. The plaintiff also claims that, after it completed the site work, the property was going to be used for a rock crushing and processing operation and that title to the property was to be transferred to a company owned equally by DiNardo and DeVito. The defendant contends that the corporations entered a straightforward lease agreement that permitted the plaintiff to use the property as a contractor’s yard or construction yard and that any site work done by the plaintiff was to be credited against rent.

The plaintiff spent a significant amount of time and effort preparing the property for a processing operation. Subsequently, the relationship between the parties soured, and the defendant initiated summary process proceedings. In turn, the plaintiff provided invoices to the defendant, citing expenditures of $269,868.79.2 The plaintiff filed a certificate of mechanic’s lien on October 7, 2004, in the same amount. Thereafter, the plaintiff filed a two count complaint on January 6, 2005, seeking (1) foreclosure of the mechanic’s lien and (2) damages for urijust enrichment. The defendant denied the plaintiffs claims. It filed a counterclaim and two special defenses, requesting compensation or a setoff against any recovery for valuable natural resources removed by the plaintiff without permission.3

[565]*565The court ruled in favor of the plaintiff on both counts of the complaint, stating that the plaintiff expended “substantial sums in time and money” improving the property. It rendered judgment of foreclosure on the mechanic’s lien, and continued the matter for further proceedings to make other findings consistent with that judgment.4 The court also found in favor of the plaintiff on the unjust enrichment claim, in the total amount of $224,959.24, which represented the total adjusted amount pleaded by the plaintiff as reflected in the invoices, after subtraction of $36,000 for the fair rental value of the property dming the time that the plaintiff occupied the property. The court rendered judgment in favor of the plaintiff on the counterclaim. This appeal followed.

I

The defendant first contends that the court erred in finding that it consented to the site work performed by the plaintiff. It argues that consent for the purpose of the mechanic’s lien statute requires that the defendant not only knew that the work was being performed but also agreed that it may be liable for the materials or labor. We agree with the court’s finding that the required consent was present for the proposes of foreclosing the mechanic’s lien.

As an initial matter, we dismiss the defendant’s argument that because the court found no “meeting of the [566]*566minds” in respect to the contract claims that DeVito filed, individually; see footnote 3 of this opinion; it could not in turn enforce the mechanic’s hen under the theory of an implied contract. The trial court’s finding that there was no meeting of the minds on the contract governing the overall agreement, which controlled use of the property, site work, future dealings and purchase of machinery, among other things, does not preclude a finding of limited consent for the purposes of the mechanic’s hen.

General Statutes § 49-33, which governs mechanic’s hens, provides in relevant part: “(a) If any person has a claim for more than ten dollars for materials furnished or services rendered ... in the improvement of any lot or in the site development or subdivision of any plot of land, and the claim is by virtue of an agreement with or by consent of the owner of the land . . . then the plot of land, is subject to the payment of the [mechanic’s hen], . . .”

“Under ... § 49-33 (a), the consent required from the owner ... is more than the mere granting of permission for work to be conducted on one’s property ... or the mere knowledge that work was being performed on one’s land. . . . The consent meant by the statute must be a consent that indicates an agreement that the owner of at least the land shall be, or may be, hable for the materials or labor.” (Citations omitted; internal quotation marks omitted.) St. Catherine’s Church Corp. v. Technical Planning Associates, Inc., 9 Conn. App. 682, 684, 520 A.2d 1298 (1987).

Whether the plaintiff consented to the performance of the defendant’s work is a question of fact. Id., 685. Our review of the trial court’s factual findings is limited to the question of whether the findings are clearly erroneous. Id. “A finding of fact is clearly erroneous when there is no evidence in the record to support it . . . [567]*567or when although there is evidence to support it, the reviewing court on the entire evidence is left with the definite and firm conviction that a mistake has been committed.” (Internal quotation marks omitted.) New Hartford v. Connecticut Resources Recovery Authority, 291 Conn. 433, 487, 970 A.2d 592 (2009).

Because there was no written contract between the parties, the court’s conclusion that there was consent for the purposes of foreclosure of the mechanic’s lien rested primarily on its assessment of the weight and credibility to be accorded to the witness’ testimony. In reviewing the record, we conclude that there is sufficient evidence to support the court’s findings. DeVito testified to his belief that there was an agreement that the defendant would be responsible for the cost of site work.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Levinson v. Lawrence
Connecticut Appellate Court, 2016
Leftridge v. Wiggins
44 A.3d 217 (Connecticut Appellate Court, 2012)
McKeon v. Lennon
27 A.3d 436 (Connecticut Appellate Court, 2011)
Thomas v. Collins
21 A.3d 518 (Connecticut Appellate Court, 2011)
McRae v. McRae
20 A.3d 1255 (Connecticut Appellate Court, 2011)
Waterview Site Services, Inc. v. Pay Day, Inc.
12 A.3d 1005 (Supreme Court of Connecticut, 2011)

Cite This Page — Counsel Stack

Bluebook (online)
11 A.3d 692, 125 Conn. App. 561, 2010 Conn. App. LEXIS 565, Counsel Stack Legal Research, https://law.counselstack.com/opinion/waterview-site-service-inc-v-pay-day-inc-connappct-2010.