Wassilie v. Alaska Village Electric Cooperative, Inc.

816 P.2d 158, 1991 Alas. LEXIS 85
CourtAlaska Supreme Court
DecidedAugust 9, 1991
DocketNo. S-3932
StatusPublished
Cited by1 cases

This text of 816 P.2d 158 (Wassilie v. Alaska Village Electric Cooperative, Inc.) is published on Counsel Stack Legal Research, covering Alaska Supreme Court primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wassilie v. Alaska Village Electric Cooperative, Inc., 816 P.2d 158, 1991 Alas. LEXIS 85 (Ala. 1991).

Opinion

OPINION

Before RABINOWITZ, C.J., MATTHEWS, COMPTON and MOORE, JJ.

MOORE, Justice.

Michael Wassilie appeals a judgment notwithstanding the verdict in a negligence action brought against Alaska Village Electric Cooperative, Inc. (AVEC). Wassilie received injuries from a severe electrical shock incurred when his citizens’ band (CB) antenna toppled near AVEC’s newly installed overhead electrical transmission wire system in the village of Eek. The trial court issued a partial summary judgment, finding as a matter of law that Wassilie had been comparatively negligent for failing to ground his CB radio and CB antenna; this decision was not appealed. At trial, the jury found in favor of Wassilie in a special verdict but allocated 40% of the negligence to Wassilie and 60% to AVEC.

AVEC moved for judgment notwithstanding the verdict, or alternatively, a new trial, or alternatively, remittitur. The superior court granted judgment n.o.v., ruling that the possibility that Wassilie’s CB antenna would fall near the overhead lines was unforeseeable and therefore, AVEC did not have a duty to specifically warn Wassilie of the possibility that electricity from the lines could be conducted by his antenna and furthermore, even if such a duty existed, Wassilie failed to demonstrate that additional warnings would have changed his behavior. The court did not decide the motion for a new trial or remit-titur. Although there is considerable evidence to the contrary, we are nonetheless persuaded that the jury could reasonably have concluded that the overhead lines created a risk of foreseeable harm to Wassilie. We therefore reverse the grant of judgment n.o.v. and remand for consideration of the motions for a new trial and remittitur.1

I. BACKGROUND

At the request of the Eek village council, AVEC installed an overhead electrical power system in Eek. Previously, the village had been served by a ground-level system of insulated wires enclosed in wooden utila-dors. AVEC began construction of the overhead system in November 1984. Construction was completed in late March or early April 1985, and the system energized some three to four months later.

Michael Wassilie’s CB antenna was mounted on a forty foot wooden mast which was located about eighteen feet from AVEC’s power lines. Contrary to explicit directions provided with the antenna and CB unit, neither the antenna nor the CB [160]*160unit was grounded. The antenna was originally in an upright position, but sometime between February 1984 and the time construction began in November 1984, it blew over and was leaned at a forty-five degree angle against Wassilie’s house.

According to Wassilie, the antenna was righted to a vertical position during the period between completion of construction and the energizing of the system. AVEC disputed the timing, contending that the antenna was placed in a vertical position after the system was energized.2 The parties also disagreed as to whether the antenna was relocated when it was placed upright. Wassilie maintains that the antenna was merely righted and its base not moved.

On October 9, 1985, Eek experienced a storm with winds estimated at fifty miles per hour. Unbeknownst to Wassilie, his CB antenna blew over from its vertical position and landed dangerously close to AVEC’s overhead transmission lines. The proximity of the antenna to the wires permitted electricity to arc to the antenna through which it was conducted to the CB unit. When Wassilie attempted to pick up the CB, he received a severe shock and was knocked to the floor unconscious. His daughter ran to their neighbor Charles Allen’s home for assistance. Allen came to Wassilie’s home and was also mildly shocked when he went to pick up the CB unit from the floor where Wassilie had dropped it. Allen then went outside the home and saw the antenna leaning toward the wires with electricity arcing between it and the wires. Allen contacted the village power plant operator who shut down the power system; Allen then moved the antenna away from the wires and secured it to Wassilie’s house with a rope.

Wassilie was airlifted to a hospital in Bethel and ultimately to Anchorage where he was hospitalized from October 9 through 23. Wassilie suffered third degree burns on his forearm, palm, and chest. He was unable to resume normal activities for the remainder of the winter.3

At trial, Wassilie’s expert witness, John Talbott, testified that AVEC could have prevented the accident had it: (1) moved the power lines horizontally three feet further away, out of the antenna’s fall zone; (2) raised the conductors four feet in height; or (3) insulated the conductors for “15 feet centered on the nearest point to the antenna.” AVEC’s expert testified as to the impracticality of insulating the line, stating that the greater weight would have required additional support poles. He also established that the antenna’s proximity to the power line did not violate the National Electrical Safety Code.4

In the memorandum decision granting judgment n.o.v., the trial court, focusing on the issue of foreseeability, found that AVEC did not have a duty to specifically warn Wassilie of the danger posed by the uninsulated lines adjacent to his home because it could not have foreseen that Was-silie would create the dangerous condition by moving the antenna closer to the overhead lines. Furthermore, the court found Wassilie had received generalized warnings about the danger of the overhead power lines and CB antennas but ignored these warnings. Therefore, the court concluded that even assuming that AVEC did have a duty to warn, Wassilie could not demonstrate that his actions would have been different if he had received an adequate warning and thus had failed to establish that breaching this duty was the proximate cause of his injuries. For these reasons, the trial court overturned the jury verdict and granted judgment for AVEC.

II. STANDARD OF REVIEW

“[T]he proper role of this court, on review of motions ... for judgment notwithstanding the verdict, is not to weigh con[161]*161flicting evidence or judge of the credibility of the witnesses, but ... rather to determine whether the evidence, when viewed in the light most favorable to the nonmoving party, is such that reasonable men could not differ in their judgment.” Holiday Inns of America, Inc. v. Peck, 520 P.2d 87, 92 (Alaska 1974) (footnote omitted).

In reviewing judgments n.o.v. in negligence cases, this court has focused on whether, in the exercise of reasonable judgment, there was room for diversity of opinion among fair minded persons. Nat’l Bank of Alaska v. McHugh, 416 P.2d 239, 242 (Alaska 1966); McCoy v. Alaska Brick Co., 389 P.2d 1009, 1010 (Alaska 1964); Snipes v. March, 378 P.2d 827, 828-29 (Alaska 1963).

III. FORESEEABILITY

The trial court reasoned that AVEC could not have foreseen that Wassilie would move his antenna from a safe position against the house and “place it ... ungrounded and improperly moored” in a position close to the lines.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Cite This Page — Counsel Stack

Bluebook (online)
816 P.2d 158, 1991 Alas. LEXIS 85, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wassilie-v-alaska-village-electric-cooperative-inc-alaska-1991.