Washtenaw Co Parks & Recreation Commn v. Vortex Aquatic Structures

CourtMichigan Court of Appeals
DecidedMarch 10, 2022
Docket355889
StatusUnpublished

This text of Washtenaw Co Parks & Recreation Commn v. Vortex Aquatic Structures (Washtenaw Co Parks & Recreation Commn v. Vortex Aquatic Structures) is published on Counsel Stack Legal Research, covering Michigan Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washtenaw Co Parks & Recreation Commn v. Vortex Aquatic Structures, (Mich. Ct. App. 2022).

Opinion

If this opinion indicates that it is “FOR PUBLICATION,” it is subject to revision until final publication in the Michigan Appeals Reports.

STATE OF MICHIGAN

COURT OF APPEALS

WASHTENAW COUNTY PARKS AND UNPUBLISHED RECREATION COMMISSION, March 10, 2022

Plaintiff-Appellee,

V No. 355889 Washtenaw Circuit Court VORTEX AQUATIC STRUCTURES LC No. 20-000498-CB INTERNATIONAL, INC., doing business as VORTEX USA, INC.,

Defendant-Appellant.

Before: REDFORD, P.J., and SAWYER and MURRAY, JJ.

PER CURIAM.

In this interlocutory appeal, defendant appeals by leave granted1 the circuit court’s denial of defendant’s motion for summary disposition on the ground that plaintiff’s indemnification claims were not barred by the durational term provided in the parties’ contract. We reverse and remand for entry of an order granting summary disposition in favor of defendant.

I. FACTUAL BACKGROUND

In April 2012 the parties contracted for defendant to design and construct the Blue Heron Bay Splash Pad at Independence Lake Park for plaintiff’s payment of an amount not to exceed $212,000 (subject to authorized change orders) upon completion and acceptance of defendant’s services. Article IV defined the temporal duration of the parties’ contract:

1 Washtenaw Co Parks & Recreation Comm v Vortex Aquatic Structures, Inc, unpublished order of the Court of Appeals, entered March 26, 2021 (Docket No. 355889).

-1- This contract begins on April 10, 2012 and ends on November 15, 2012 according to the project schedule and as modified through authorized change orders.

Article VI required defendant to indemnify plaintiff as follows: The contractor will protect, defend and indemnify Washtenaw County, its officers, agents, servants, volunteers and employees from any and all liabilities, claims, liens, fines, demands and costs, including legal fees, of whatsoever kind and nature which may result in injury or death to any persons, including the Contractor’s own employees, and for loss or damage to any property, including property owned or in the care, custody, or control of Washtenaw County in connection with or in any way incident to or arising out of the occupancy, use, service, operations, performance or non-performance of work in connection with this contract resulting in whole or in part from negligent acts or omissions of contractor, any sub-contractor, or any employee, agent or representative of the contractor or any sub-contractor.

The splash pad opened to the public on May 25, 2013. From 2015 to 2019, several of the splash pad’s features were turned off because of leaks and water pressure issues. Plaintiff had an inspection performed in November 2019 which revealed several structural defects and function issues. Plaintiff apparently waited until March 2020 to send two letters to defendant regarding the problems. In each letter plaintiff requested that defendant indemnify it for the costs it incurred and expenses anticipated for correction of the problems. Defendant did not respond to the letters. In June 2020, plaintiff filed its complaint alleging that the splash pad had various defects for which defendant bore responsibility. Plaintiff requested that the trial court declare that the indemnity provision applied and required defendant to indemnify plaintiff for costs and damages incurred because of defendant’s negligent performance of the construction. Plaintiff also alleged that defendant breached the contract’s indemnity provision by refusing to indemnify plaintiff.

In lieu of answering, defendant moved for summary disposition of plaintiff’s indemnity claim under MCR 2.116(C)(8) (failure to state a claim), and argued, in pertinent part, that the claim was untimely because defendant’s duty to indemnify ended when the contract ended, on November 15, 2012, pursuant to the duration term of the contract.2 Plaintiff opposed the motion by arguing that the contract’s durational term did not apply to the indemnification provision which it contended was a separate and independent obligation subject to no durational limit beyond the applicable statute of limitations. The trial court agreed with plaintiff and denied defendant’s motion.

2 Defendant also moved for summary disposition under MCR 2.116(C)(7) on the ground that the statute of repose, MCL 600.5839, barred the action. The trial court also denied that portion of defendant’s motion. This appeal concerns only the trial court’s denial of its MCR 2.116(C)(8) motion.

-2- II. STANDARDS OF REVIEW

We review de novo a trial court’s decision on a motion for summary disposition. Zaher v Miotke, 300 Mich App 132, 139; 832 NW2d 266 (2013). “A motion under MCR 2.116(C)(8) tests the legal sufficiency of the complaint on the basis of the pleadings alone to determine if the opposing party has stated a claim for which relief can be granted.” Id. (quotation marks and citation omitted). A trial court considering such a motion “must accept all well-pleaded allegations as true and construe them in the light most favorable to the nonmoving party.” Id. “A motion under MCR 2.116(C)(8) may only be granted when a claim is so clearly unenforceable that no factual development could possibly justify recovery.” El-Khalil v Oakwood Healthcare, Inc, 504 Mich 152, 160; 934 NW2d 665 (2019). Because the instant cause of action is based on a written instrument, the parties’ contract is considered part of the pleadings for purposes of the motion. See MCR 2.113(C)(1); Laurel Woods Apartments v Roumayah, 274 Mich App 631, 635; 734 NW2d 217 (2007). We review de novo questions of contract interpretation. Burkhardt v Bailey, 260 Mich App 636, 646; 680 NW2d 453 (2004).

III. ANALYSIS

Defendant argues that the trial court erred by ruling that the contract’s durational term did not apply to the indemnification provision. We agree.

“The cardinal rule in the interpretation of contracts is to ascertain the intention of the parties; to this rule all others are subordinate.” Highfield Beach v Sanderson, 331 Mich App 636, 654; 954 NW2d 231 (2020) (quotation marks, alterations, and citation omitted). “In ascertaining the meaning of a contract, we give the words used in the contract their plain and ordinary meaning that would be apparent to a reader of the instrument.” Id. (quotation marks and citation omitted). Courts must “give effect to every word, phrase, and clause in a contract and avoid an interpretation that would render any part of the contract surplusage or nugatory.” Klapp v United Ins Group Agency, Inc, 468 Mich 459, 468; 663 NW2d 447 (2003). “[U]nless a contract provision violates law or one of the traditional defenses to the enforceability of a contract applies, a court must construe and apply unambiguous contract provisions as written.” Rory v Continental Ins Co, 473 Mich 457, 461; 703 NW2d 23 (2005). The legal principle that “ ‘unambiguous contracts are not open to judicial construction and must be enforced as written’ ” is “grounded in the rationale that the judiciary ought not interfere with the right of individuals to ‘arrange their affairs via contract.’ ” VHS Huron Valley Sinai Hosp v Sentinel Ins Co, 322 Mich App 707, 716; 916 NW2d 218 (2018), quoting Rory, 473 Mich at 468.

Indemnity contracts are construed in accordance with general contract interpretation rules. Triple E Produce Corp v Mastronardi Produce Ltd, 209 Mich App 165, 172; 530 NW2d 772 (1995). Indemnity contracts should be strictly construed against the party who drafted the contract and the party designated the indemnitee. Id. “Under ordinary contract principles, if contractual language is clear, construction of the contract is a question of law for the court.” Meagher v Wayne State Univ, 222 Mich App 700, 721; 565 NW2d 401 (1997).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rory v. Continental Insurance
703 N.W.2d 23 (Michigan Supreme Court, 2005)
Klapp v. United Insurance Group Agency, Inc
663 N.W.2d 447 (Michigan Supreme Court, 2003)
Triple E Produce Corp. v. Mastronardi Produce, Ltd.
530 N.W.2d 772 (Michigan Court of Appeals, 1995)
DaimlerChrysler Corp. v. Wesco Distribution, Inc.
760 N.W.2d 828 (Michigan Court of Appeals, 2008)
In Re Rudell Estate
780 N.W.2d 884 (Michigan Court of Appeals, 2009)
Old Kent Bank v. Sobczak
620 N.W.2d 663 (Michigan Court of Appeals, 2000)
Meagher v. Wayne State University
565 N.W.2d 401 (Michigan Court of Appeals, 1997)
Laurel Woods Apartments v. Roumayah
734 N.W.2d 217 (Michigan Court of Appeals, 2007)
Burkhardt v. Bailey
680 N.W.2d 453 (Michigan Court of Appeals, 2004)
Sherman v. Sea Ray Boats, Inc
649 N.W.2d 783 (Michigan Court of Appeals, 2002)
Miller-Davis Co. v. Ahrens Construction, Inc.
848 N.W.2d 95 (Michigan Supreme Court, 2014)
Title Guaranty & Surety Co. v. Roehm
184 N.W. 414 (Michigan Supreme Court, 1921)
Moore v. Capital National Bank
264 N.W. 288 (Michigan Supreme Court, 1936)
Vhs Huron Valley Sinai Hospital v. Sentinel Insurance Company
916 N.W.2d 218 (Michigan Court of Appeals, 2018)
Rita Kendzierski v. County of MacOmb
931 N.W.2d 604 (Michigan Supreme Court, 2019)
Grand Trunk Western Railroad v. Auto Warehousing Co.
686 N.W.2d 756 (Michigan Court of Appeals, 2004)
Zaher v. Miotke
832 N.W.2d 266 (Michigan Court of Appeals, 2013)

Cite This Page — Counsel Stack

Bluebook (online)
Washtenaw Co Parks & Recreation Commn v. Vortex Aquatic Structures, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washtenaw-co-parks-recreation-commn-v-vortex-aquatic-structures-michctapp-2022.