Washington Service Contractors Coalition v. District Of Columbia

54 F.3d 811
Procedural entryThis page is a short order in Washington Service Contractors Coalition v. District Of Columbia. Read the opinion of the Court — 54 F.3d 811
Court of Appeals for the D.C. Circuit·Decided August 9, 1995·No. 94-7143·Published

Opinion

54 F.3d 811

149 L.R.R.M. (BNA) 2271, 311 U.S.App.D.C.
407, 63 USLW 2712,
130 Lab.Cas. P 57,918

WASHINGTON SERVICE CONTRACTORS COALITION, et al., Appellees,
v.
DISTRICT OF COLUMBIA, et al., and Service Employees
International Union and Service Employees
International Union, Local 82, Appellants.

Nos. 94-7143, 94-7144.

United States Court of Appeals,
District of Columbia Circuit.

Argued March 27, 1995.
Decided May 12, 1995.
Rehearing and Suggestion for Rehearing In Banc Denied Aug.
9, 1995.*

Marsha S. Berzon, Ithaca, NY, argued the cause, for appellants. With her on the briefs were Garland Pinkston, Acting Corp. Counsel, Charles L. Reischel, Deputy Corp. Counsel, Orrin Baird and Carol R. Golubock, Washington, DC.

Anita Barondes, Washington, DC, argued the cause, for appellees. With her on the brief were Peter Chatilovicz and Ronald A. Lindsay, Washington, DC.

Before WALD, SENTELLE and ROGERS, Circuit Judges.

Opinion for the Court filed by Circuit Judge WALD.

Dissenting opinion filed by Circuit Judge SENTELLE.

WALD, Circuit Judge:

The District of Columbia Displaced Workers Protection Act of 1994, 41 D.C.Reg. 1011 (to be codified at D.C.Code Ann. Secs. 36-1501 to 1503) ("DWPA" or "Act"), requires that contractors who take over contracts for the provision of certain services must hire their predecessors' employees for a period of 90 days. Appellees, a coalition of service contractors and eight individual companies (collectively "the contractors"), brought suit in the district court alleging that the DWPA is preempted by the National Labor Relations Act, 29 U.S.C. Secs. 151-69 (1988) ("NLRA"), and violates the mandate of the Contracts Clause. U.S. CONST. art. I, Sec. 10, cl. 1. The district court agreed that the NLRA preempts the DWPA and enjoined the Act's enforcement without addressing the Contracts Clause issue. The District of Columbia and its mayor ("the District") and the Service Employees International Union and its local branch ("SEIU") appeal. Because we hold that the DWPA is neither preempted by the NLRA nor invalid under the Contracts Clause, we vacate the district court's decision and remand for proceedings consistent with this opinion.

I. BACKGROUND

A. The DWPA

The DWPA was enacted by the Council of the District of Columbia and approved by Mayor Sharon Pratt Kelly on February 17, 1994. Following a period of congressional review, it became law on April 26, 1994. According to the District, the DWPA represents "an effort ... to provide a measure of employment security to certain low wage service workers who are frequently displaced from their employment when their employers lose contracts," and to "reduc[e][ ] the number of unemployed D.C. residents currently collecting unemployment benefits." Appellants' Brief at 2-4.

The Act applies to contractors who employ 25 or more persons and perform food, janitorial, maintenance, or nonprofessional health care services. DWPA Sec. 2(a), (b). Such contractors must "retain, for a 90-day transition period, covered employees1 who have been employed by the previous contractor for the preceding 8 months or longer at the site or sites covered by the contract." Id. at Sec. 3(b). During the transition period, the new contractor may dismiss "retained" employees--beginning with the least senior--in excess of the number that it "determines ... are required to perform the new contract," id. at Sec. 3(c); other covered employees, however, may be terminated only for "cause." Id. at Sec. 3(e). The DWPA also requires that the new contractor "shall [at the end of the transition period] perform a written performance evaluation for each employee retained pursuant to this act"; if the employee's performance is found to be satisfactory, the contractor "shall offer the employee continued employment under the terms and conditions established by the new contractor." Id. at Sec. 3(f). The DWPA provides employees discharged in violation of the Act a cause of action for back pay, costs, and attorney's fees in the Superior Court of the District of Columbia. Id. at Sec. 4.

B. Procedural Background

On May 24, 1994, appellees filed a three-count complaint for declaratory and injunctive relief in the district court.2 Appellees advanced three primary theories for the proposition that the DWPA was preempted by federal law, as well as a claim of unconstitutionality under the Contracts Clause.

First, appellees argued that the DWPA is preempted by Sec. 14(a) of the NLRA. The district court agreed. Specifically, it found that the DWPA "conflicts with Sec. 14(a) by ... infring[ing] upon contractors' abilities to ensure the loyalty of their supervisors." Washington Service Contractors Coalition v. District of Columbia, 858 F.Supp. 1219, 1225 (D.D.C.1994). The court held that "the DWPA's application to supervisors must [accordingly] be enjoined." Id. at 1227.

Appellees also argued that the DWPA is preempted by federal law because it could transform some non-union contractors who "retain" union employees into "successor" employers under the NLRB's jurisprudence, and so oblige the new contractors to bargain with the union that represented their predecessors' employees. This, appellees claimed, represents an impermissible state incursion into the collective bargaining processes regulated by federal law. The district court again agreed. It held that "the DWPA's effect ... on collective bargaining so significantly alters the balance of power between labor and management that this Court must find that the DWPA is preempted by the NLRA." Id. at 1229. The court therefore "enter[ed] a declaratory judgment ... permanently enjoin[ing]" the Act's enforcement. Id. at 1230.

Appellees contended as well that the NLRA preempts the DWPA because it "improperly regulates [contractors'] right to hire whomever they wish." Id. at 1227. The district court wrote that "it is not clear whether this inhibition on free enterprise alone would be adequate to justify NLRA preemption," id. at 1229, but found it unnecessary to resolve the question in light of its other rulings in the case. The court also did not reach appellees' Contracts Clause claim.

The District and SEIU opted not to appeal the district court's ruling that Sec. 14(a) of the NLRA preempts application of the DWPA to supervisors. Appellees argue that this appeal is therefore moot on the theory that the district court's unchallenged Sec. 14(a) ruling, standing alone, is sufficient to justify the whole of its injunction on the application of the DWPA. In addition, appellees continue to maintain that the DWPA is preempted because of its potential interference with federal successorship doctrine and employers' hiring decisions, and that it is invalid under the Contracts Clause.

II. ANALYSIS

A. Preemption Principles

Under the Supremacy Clause, U.S. CONST. art. VI, cl.

Free access — add to your briefcase to read the full text and ask questions with AI

Washington Service Contractors Coalition v. District Of Columbia, 54 F.3d 811 (D.C. Cir. 1995).

54 F.3d 811 (Washington Service Contractors Coalition v. District Of Columbia) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related

Hines v. Davidowitz
312 U.S. 52 (Supreme Court, 1941)
Rice v. Santa Fe Elevator Corp.
331 U.S. 218 (Supreme Court, 1947)
International Union of United Automobile v. O'Brien
339 U.S. 454 (Supreme Court, 1950)
San Diego Building Trades Council v. Garmon
359 U.S. 236 (Supreme Court, 1959)
John Wiley & Sons, Inc. v. Livingston
376 U.S. 543 (Supreme Court, 1964)
Jones v. Rath Packing Co.
430 U.S. 519 (Supreme Court, 1977)
Allied Structural Steel Co. v. Spannaus
438 U.S. 234 (Supreme Court, 1978)
Metropolitan Life Insurance v. Massachusetts
471 U.S. 724 (Supreme Court, 1985)
General Motors Corp. v. Romein
503 U.S. 181 (Supreme Court, 1992)
Washington Service Contractors Coalition v. District of Columbia