Washington Gas Light Company v. Prince George's County Council

711 F.3d 412, 2013 WL 1189296, 2013 U.S. App. LEXIS 5884
CourtCourt of Appeals for the Fourth Circuit
DecidedMarch 25, 2013
Docket12-1443
StatusPublished
Cited by23 cases

This text of 711 F.3d 412 (Washington Gas Light Company v. Prince George's County Council) is published on Counsel Stack Legal Research, covering Court of Appeals for the Fourth Circuit primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Gas Light Company v. Prince George's County Council, 711 F.3d 412, 2013 WL 1189296, 2013 U.S. App. LEXIS 5884 (4th Cir. 2013).

Opinion

Affirmed by published opinion. Judge THACKER wrote the opinion, in which Chief Judge TRAXLER and Judge FLOYD joined.

OPINION

THACKER, Circuit Judge:

Appellant Washington Gas Light Company (“Washington Gas”) operates a natural gas substation on Chillum Road in Prince George’s County, Maryland (“Chil-lum Site”). Beginning in 2004, Washing *414 ton Gas sought to expand that substation with the addition of a liquefied natural gas (“LNG”) storage tank. Washington Gas initially requested approval for this proposed expansion from Prince George’s County (“County”), which denied the request based on recently enacted county zoning plans (“County Zoning Plans”).

Thereafter, Washington Gas filed a federal action seeking: (1) a declaration that the County erroneously denied Washington Gas permission to proceed under 28 Md.Code Ann. § 7-112 (the “mandatory referral statute”); (2) a declaration that the Natural Gas Pipeline Safety Act (“PSA”), Natural Gas Act (“NGA”), and state law preempt the County Zoning Plans; and (3) an injunction prohibiting the County from enforcing the allegedly preempted County Zoning Plans.

The district court initially dismissed the mandatory referral claim for failure to state a claim upon which relief could be granted and, in the alternative, on Burford abstention grounds. In a subsequent order, the district court granted summary judgment in favor of the County on the state and federal preemption claims, thus denying Washington Gas’s request for declaratory and injunctive relief.

Washington Gas appeals the district court’s order, dated February 9, 2009, dismissing the mandatory referral claim and the district court’s subsequent order, dated March 9, 2012, granting summary judgment on the federal preemption claims. 1 We conclude (1) the district court did not abuse its discretion in dismissing the mandatory referral claim pursuant to Bwrford; (2) the PSA does not preempt the County Zoning Plans because the PSA only preempts safety regulations and the County Zoning Plans are not safety regulations; and (3) the NGA does not preempt the County Zoning Plans because Washington Gas is a local distributor of natural gas and, therefore, is not subject to the NGA.

Therefore, the district court’s judgment, as set forth in its February 9, 2009 and March 9, 2012 orders, is affirmed.

I.

A.

Washington Gas distributes natural gas to retail customers in the Washington, D.C. area, including portions of Maryland and Virginia. Currently, Washington Gas operates a natural gas substation at the Chillum Site. The Chillum Site was initially approved for natural gas storage and compression in 1933. The scope of Washington Gas’s operations at the Chillum Site has expanded, with County permission, on several occasions since that time. Specifically, in 1955, the County granted Washington Gas permission to construct a branch headquarters at the Chillum Site. Then, in 1975 and again in 1982, the County permitted Washington Gas to construct additional office and storage space there.

B.

Washington Gas began seeking approval to add LNG storage tanks to the Chillum Site in 2004. In pursuit of this proposed expansion, Washington Gas initially sought to invoke the mandatory referral statute, Md.Code Ann., Land Use §§ 20-301-20-307 (Lexis 2012). 2 This statute, sets forth a method through which certain public or *415 ganizations may obtain approval for a project without having to go through local zoning review. See Pan Am. Health Org. v. Montgomery County, 338 Md. 214, 657 A.2d 1163, 1168 (1995) (“PAHO ”). However, the County determined that the mandatory referral statute was inapplicable in this case. Thus, Washington Gas ultimately sought to obtain zoning approval rather than to proceed through mandatory referral. Accordingly, the County held several hearings on this zoning request.

However, on March 23, 2006, during the pendency of the zoning proceedings, the County adopted the County Zoning Plans. The County Zoning Plans, known as the West Hyattsville District Overlay Zone (‘WHDOZ”) and the Transit District Development Plan (“TDDP”), were aimed at maximizing “transit-oriented development” in the area around the West Hyattsville Metro Center. The County Zoning Plans prohibited all industrial usage in that area, which included the Chillum Site. Based on this enactment, the County denied Washington Gas zoning approval on August 24, 2006.

Thereafter, Washington Gas appealed to the County Council, which denied the appeal. Washington Gas then appealed the denial to the Circuit Court for Prince George’s County, Maryland, which dismissed the appeal on ripeness and exhaustion grounds.

C.

As the state and county proceedings were ongoing, Washington Gas also appeared before the Maryland Public Service Commission (“MDPSC”) in two separate matters relevant to the proposed expansion. First, in November 2005, Washington Gas wrote a letter to the MDPSC requesting regulatory approval for the proposed expansion. In particular, Washington Gas requested the MDPSC to certify that the proposed expansion complied with Maryland’s regulations governing thermal radiation and vapor exclusion zones. 3 By letter dated March 20, 2007, the MDPSC’s engineering staff determined that Washington Gas’s proposal was consistent with the pertinent safety regulations. Notably, the letter was expressly limited to safety considerations, indicating, “this opinion refers to analyses discussed herein and it does not state [the] Technical Staffs position on any other matter pertaining to the proposed Chillum facility....” J.A. 744. 4

Second, in November 2008, Washington Gas initiated MDPSC review of its annual Gas Portfolio Plan, a required annual presentation in which a public utility details how it intends to meet customer demand over the next five years. This review is conducted pursuant to the MDPSC’s rate regulation authority as set forth in Md. Code Ann., Pub. Util. § 4-402 (2012). As the district court noted, these annual reviews are limited to rate regulation and, therefore, “[t]hey are not general reviews of all aspects of public utilities in Maryland and do not include thorough reviews of a public utility’s conformity with local land use plans.” J.A. 1041. The proposed expansion was discussed during that review. However, because the proposed expansion, even if authorized by the County, would *416 not have been completed within the next five years, the MDPSC did not express any opinion on the propriety of the proposal.

D.

Following completion of the zoning proceedings and the ensuing state appeal, Washington Gas brought this federal action on April 16, 2008 in United States District Court for the District of Maryland. The initial complaint was amended on July 18, 2008 (the “first amended complaint”).

Free access — add to your briefcase to read the full text and ask questions with AI

Related

AbbVie Inc. v. Morrisey
S.D. West Virginia, 2024
Teaf v. Lee
D. Maryland, 2020
Little v. Haddaway-Riccio
D. Maryland, 2019
Mountain Valley Pipeline, LLC v. Wender
337 F. Supp. 3d 656 (U.S. District Court, 2018)
Portland Pipe Line Corp. v. City of S. Portland
288 F. Supp. 3d 321 (D. Maine, 2017)

Cite This Page — Counsel Stack

Bluebook (online)
711 F.3d 412, 2013 WL 1189296, 2013 U.S. App. LEXIS 5884, Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-gas-light-company-v-prince-georges-county-council-ca4-2013.