Washington Cty. Job Family v. Binegar, Unpublished Decision (5-30-2003)

CourtOhio Court of Appeals
DecidedMay 30, 2003
DocketNo. 02CA42.
StatusUnpublished

This text of Washington Cty. Job Family v. Binegar, Unpublished Decision (5-30-2003) (Washington Cty. Job Family v. Binegar, Unpublished Decision (5-30-2003)) is published on Counsel Stack Legal Research, covering Ohio Court of Appeals primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Washington Cty. Job Family v. Binegar, Unpublished Decision (5-30-2003), (Ohio Ct. App. 2003).

Opinion

DECISION AND JUDGMENT ENTRY
{¶ 1} This is an appeal from a Marietta Municipal Court judgment in favor of the Washington County Department of Job and Family Services, plaintiff below and appellee herein. The trial court found that Edward Binegar, individually and dba Binegar's Painting, defendant below and appellant herein, had breached the contract into which he entered with appellee and awarded appellee $8,500.

{¶ 2} Appellant raises the following assignments of error:

FIRST ASSIGNMENT OF ERROR:

"The trial court erred in finding for plaintiff in that there was no evidence offered at trial to show damages."

SECOND ASSIGNMENT OF ERROR:

"The trial court erred in finding for plaintiff in that the weight of the evidence clearly shows a lack of failure of consideration on the part of the defendant."

THIRD ASSIGNMENT OF ERROR:

"The court erred in not finding on behalf of defendant/appellant."

{¶ 3} On December 26, 2000, appellant and appellee entered into a written contract. The contract required appellant to paint the interior of appellee's office building for the amount of $12,500.

{¶ 4} On January 12, 2001, appellee paid appellant one-half of the contract amount, $6,250. On March 14, 2001, appellee exercised its right to terminate the contract. Appellee opted to terminate appellant's services because it believed that appellant had not satisfactorily performed the work.

{¶ 5} On May 7, 2001, appellee filed a complaint against appellant for breach of contract. Appellee asserted that appellant (1) failed to perform the work in a workmanlike manner; (2) failed to employ, hire, and use only qualified painters to perform the contract work; (3) failed to protect adjacent surfaces; (4) failed to clean paint from surfaces not intended to be painted; (5) failed to properly prepare surfaces to be painted; (6) used materials other than those specified in the contract; (7) altered materials prior to application; and (8) employed subcontractors.

{¶ 6} On April 23, 2002, the parties tried the case to the court. At the trial, appellee presented evidence that: (1) appellant used watered-down paint to paint the interior of the building, which resulted in an uneven application; (2) appellant had not spackled or otherwise filled holes or dents prior to painting; (3) appellant had not properly prepared the walls before painting; (4) appellant left paint marks on surfaces, such as door knobs and ceiling tiles, that were not intended to be painted; (5) fibers from the paint rollers that appellant used stuck to some of the surfaces that appellant painted; (6) appellant failed to move filing cabinets so that he could paint behind the cabinets; and (7) appellee was not satisfied with appellant's performance. Appellee also presented evidence that as a result of appellant's poor performance, it had to employ another painter to re-paint the areas that appellant had painted and to paint the portion of the building that appellant had not completed. Appellee presented testimony that the cost of employing the other painter to re-do appellant's work, and to complete the painting project, was $14,750.

{¶ 7} Appellant testified that he performed the work as called for in the contract. Appellant denied watering-down the paint, except to perform touch-up painting. Appellant claimed that he used a good quality paint and that he applied three coats of paint on each surface. Appellant further claimed that he properly prepared the surfaces before he began painting and denied that he failed to spackle or fill holes and dents before painting.

{¶ 8} On June 14, 2002, the trial court entered judgment in appellee's favor. The trial court found that appellant failed to perform the contract work in workmanlike manner by: (1) failing to move filing cabinets so that he could paint behind them; and (2) using paint rollers that allowed the fibers from the rollers to stick to the wall. The trial court further found that: (1) the paint rubbed off of the wall; (2) appellant had not caulked the windows; (3) the paint coverage not uniform, with some areas being lighter than others; (4) appellant hired subcontractors to perform some of the painting and the contract forbade the use of subcontractors; (5) appellant failed to protect adjacent surfaces; (6) appellant did not properly prepare surfaces prior to painting; and (7) appellant altered the paint by adding water to it, thus voiding paint warranty.

{¶ 9} The trial court determined that "the quality of the work performed by [appellant] was so poor that [appellant] was justified in seeking a contractor who would repaint all the surfaces that [appellee] had already painted, to complete the contract as originally contemplated by the parties." The court thus concluded that appellee was entitled to "restitution of the moneys paid and the additional moneys expended to correct the defective work."

{¶ 10} In calculating the amount of damages to award appellee, the trial court found as follows: (1) the value of contract was $12,500; (3) appellee paid appellant $6,250 as partial payment; (3) appellee had to hire another contractor to completely repaint the areas that appellant had painted and to finish the painting project; and (4) appellee paid the other contractor $14,750 to do the work that appellee had agreed to perform for $12,500. The trial court found that appellee paid $2,250 more than it would have paid appellant had appellant properly performed the job. The court thus entered judgment in appellee's favor in the amount of $8,500. Appellant filed a timely notice of appeal.

{¶ 11} Because appellant's three assignments of error all raise the related issue of whether the record supports the trial court's decision to award appellee $8,500 in damages, we will address the three assignments of error together.1

{¶ 12} In his three assignments of error, appellant argues that the trial court erred by entering judgment in appellee's favor. Appellant asserts that appellee did not present any evidence at trial to support the trial court's damage award of $8,500. We disagree with appellant.

{¶ 13} "It is well-settled law that `[j]udgments supported by some competent, credible evidence going to all the essential elements of the case will not be reversed by a reviewing court as being against the manifest weight of the evidence.'" Sharp v. Norfolk W. Ry. Co. (1995), 72 Ohio St.3d 307, 313, 649 N.E.2d 1219 (quoting C.E. Morris Co.v. Foley Constr. Co. (1978), 54 Ohio St.2d 279, 376 N.E.2d 578, syllabus); see, also, Shemo v. Mayfield Hts. (2000), 88 Ohio St.3d 7,10, 722 N.E.2d 1018. When reviewing a claim that a trial court's judgment is against the manifest weight of the evidence, a reviewing court must employ "an extremely deferential standard of review." State ex rel. Pizzav. Strope (1990), 54 Ohio St.3d 41, 45-46

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Barkley v. Barkley
694 N.E.2d 989 (Ohio Court of Appeals, 1997)
Ohio Valley Bank v. Copley
699 N.E.2d 540 (Ohio Court of Appeals, 1997)
Hansel v. Creative Concrete & Masonry Construction Co.
772 N.E.2d 138 (Ohio Court of Appeals, 2002)
Rasnick v. Tubbs
710 N.E.2d 750 (Ohio Court of Appeals, 1998)
Barton v. Ellis
518 N.E.2d 18 (Ohio Court of Appeals, 1986)
Stewart v. B.F. Goodrich Co.
623 N.E.2d 591 (Ohio Court of Appeals, 1993)
Rogers v. Hill
706 N.E.2d 438 (Ohio Court of Appeals, 1998)
McCray v. Clinton County Home Improvement
708 N.E.2d 1075 (Ohio Court of Appeals, 1998)
Allied Erecting & Dismantling Co. v. City of Youngstown
783 N.E.2d 523 (Ohio Court of Appeals, 2002)
Sites v. Moore
607 N.E.2d 1114 (Ohio Court of Appeals, 1992)
F. Enterprises, Inc. v. Kentucky Fried Chicken Corp.
351 N.E.2d 121 (Ohio Supreme Court, 1976)
C. E. Morris Co. v. Foley Construction Co.
376 N.E.2d 578 (Ohio Supreme Court, 1978)
Seasons Coal Co. v. City of Cleveland
461 N.E.2d 1273 (Ohio Supreme Court, 1984)
State ex rel. Pizza v. Strope
560 N.E.2d 765 (Ohio Supreme Court, 1990)
Sharp v. Norfolk & Western Railway Co.
649 N.E.2d 1219 (Ohio Supreme Court, 1995)
Shemo v. Mayfield Heights
722 N.E.2d 1018 (Ohio Supreme Court, 2000)

Cite This Page — Counsel Stack

Bluebook (online)
Washington Cty. Job Family v. Binegar, Unpublished Decision (5-30-2003), Counsel Stack Legal Research, https://law.counselstack.com/opinion/washington-cty-job-family-v-binegar-unpublished-decision-5-30-2003-ohioctapp-2003.