Wasatch County v. Utility Facility Review Board

2018 UT App 191, 437 P.3d 406
CourtCourt of Appeals of Utah
DecidedOctober 4, 2018
Docket20160523-CA
StatusPublished
Cited by3 cases

This text of 2018 UT App 191 (Wasatch County v. Utility Facility Review Board) is published on Counsel Stack Legal Research, covering Court of Appeals of Utah primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Wasatch County v. Utility Facility Review Board, 2018 UT App 191, 437 P.3d 406 (Utah Ct. App. 2018).

Opinion

MORTENSEN, Judge:

¶1 Rocky Mountain Power (Rocky Mountain) sought a conditional use permit from Wasatch County in order to erect transmission towers and lines, but Wasatch County denied the permit. 1 The Utility Facility Review Board (the Board) thereafter ordered Wasatch County to issue the permit. Wasatch County sought a stay from the Board, which was denied. Wasatch County then issued the conditional use permit and the power transmission towers were constructed. Wasatch County did not seek a stay from this court, nor did it delay issuance of the permit or otherwise seek to stop the construction. Under the circumstances of this case, we conclude that this proceeding for judicial review has been rendered moot and, therefore, we dismiss it.

BACKGROUND

¶2 Rocky Mountain obtained an easement over property (the Property) owned by Promontory Investments LLC (Promontory). The Property sits in both Summit and Wasatch counties. Prior to the events giving rise to this case, Rocky Mountain's transmission line ran through a portion of the Property located entirely within Summit County.

¶3 Rocky Mountain supplies power to one of the fastest-growing regions of Utah, of which Summit and Wasatch counties are part. Based on projected growth of the region, Rocky Mountain has undertaken an ongoing project to increase transmission capacity and create alternative transmission pathways (the Project). Part of the Project requires building a sixty-seven-mile transmission line. Only 0.26 miles of the proposed line would sit in Wasatch County, on Promontory's land.

¶4 The changed location-from the previous transmission line location in Summit County to the new location in Wasatch County-resulted from a request by Promontory after Rocky Mountain approached it about upgrading the current transmission line to a higher capacity one. Promontory asked Rocky Mountain "to consider alternative siting locations on" the Property. It is Rocky Mountain's practice to accommodate such a request from landowners, provided the landowner pays the cost of relocation and the new location is acceptable to Rocky Mountain. Accordingly, Rocky Mountain and Promontory considered five alternative locations for the transmission line. Promontory agreed to grant a new easement and pay additional costs associated with constructing the new line in Promontory's preferred location along the south and east perimeters of the Property-including the 0.26 miles of Wasatch County land. The agreement between Promontory and Rocky Mountain included a provision stating that if Rocky Mountain were unable to obtain necessary permits, it could terminate the agreement and leave the transmission line in its then-current location.

¶5 In its quest to obtain authorization for the construction of the transmission line segment located in Wasatch County (the Segment), Rocky Mountain was in frequent contact with Wasatch County officials, planning staff, and nearby property owners. Wasatch County consistently expressed concern about the Segment's compliance with existing ordinances aimed at limiting structures that protrude above the visual ridgeline. In its application for a conditional use permit, 2 Rocky Mountain "included four options for the proposed alignment of the transmission line in Wasatch County." The Wasatch County Planning Commission (the Planning Commission) denied the permit, concluding that none of the four options were acceptable, as "there was no way to mitigate the impacts of [the Segment] on neighboring properties."

¶6 Rocky Mountain appealed the denial of the permit to the Wasatch County Board of Adjustment (the Board of Adjustment), which agreed with the Planning Commission. The Board of Adjustment concluded that the proposed transmission upgrade violated Wasatch County's ridgeline ordinance and likewise denied the permit.

¶7 Rocky Mountain then appealed to the Board, which determined that the Segment was "needed to provide safe, reliable, adequate, and efficient service" to Rocky Mountain customers and ordered Wasatch County to issue the permit within sixty days.

¶8 Wasatch County asked the Board for a stay of its order. After the Board denied the request, Wasatch County issued the conditional use permit to Rocky Mountain. 3 Wasatch County then sought judicial review of the Board's order in this court, but did not ask this court for a stay of that order pending the outcome of judicial review. 4 After briefing and oral argument before this court, we issued a decision and the Board filed a petition for rehearing. In the briefing associated with the petition for rehearing, the parties informed this court-for the first time-that while the proceeding for judicial review had been pending, the conditional use permit had been issued, the new transmission lines had been constructed on the Segment, and the lines were now in use. This court then ordered supplemental briefing.

¶9 The supplemental briefing makes clear that the remedy Wasatch County seeks is a determination that the conditional use permit be rescinded and that the transmission towers be dismantled and moved.

ANALYSIS

¶10 In our view, Wasatch County's requested remedy is no longer available, and therefore the dispute has been rendered moot.

I. Mootness

¶11 "A case may be mooted on appeal if the relief requested is rendered impossible or of no legal effect." Transportation All. Bank v. International Confections Co., LLC , 2017 UT 55 , ¶ 15, 423 P.3d 1171 (cleaned up). In Transportation Alliance , our supreme court held that an appeal was moot because a debtor failed to seek a stay of an order approving a receivership sale. Id. ¶¶ 16-17. The bank filed a complaint alleging breach of a loan agreement and sought appointment of a receiver. Id. ¶ 2. Several creditors of one of the defendants, International Confections, intervened. Id. ¶ 3. The district court appointed a receiver, with power to sell the assets of International Confections. Id. ¶ 4.

¶12 The bank settled its claims against International Confections, and the district court dismissed the claims between the bank and International Confections, but ordered that the receiver stay in place. Id. ¶¶ 5-6. The receiver then accepted an offer to buy International Confections' assets. Id. ¶ 7. The district court held an expedited hearing and approved the order of sale. Id. ¶ 8. The buyer paid the agreed-upon price and began using the assets. Id. ¶ 9. International Confections then filed a motion under rule 60 of the Utah Rules of Civil Procedure to "reactivate" the case and allow it to file an objection to the order approving the sale. Id. ¶ 11 ; see Utah R. Civ. P. 60(b). The district court denied the motion and International Confections appealed. Id. ¶ 11.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Boyle v. Baumhaus
Court of Appeals of Utah, 2026
Harman v. 105 Partners
2024 UT App 109 (Court of Appeals of Utah, 2024)
Brigham City v. Bywater
2024 UT App 53 (Court of Appeals of Utah, 2024)
Ferre v. Salt Lake City
2019 UT App 94 (Court of Appeals of Utah, 2019)

Cite This Page — Counsel Stack

Bluebook (online)
2018 UT App 191, 437 P.3d 406, Counsel Stack Legal Research, https://law.counselstack.com/opinion/wasatch-county-v-utility-facility-review-board-utahctapp-2018.