Warwick Township Water & Sewer Authority v. Boucher & James, Inc.

851 A.2d 953, 2004 Pa. Super. 201, 2004 Pa. Super. LEXIS 1308
CourtSuperior Court of Pennsylvania
DecidedJune 2, 2004
StatusPublished
Cited by18 cases

This text of 851 A.2d 953 (Warwick Township Water & Sewer Authority v. Boucher & James, Inc.) is published on Counsel Stack Legal Research, covering Superior Court of Pennsylvania primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warwick Township Water & Sewer Authority v. Boucher & James, Inc., 851 A.2d 953, 2004 Pa. Super. 201, 2004 Pa. Super. LEXIS 1308 (Pa. Ct. App. 2004).

Opinion

DEL SOLE, P.J.

¶ 1 This is an appeal from a trial court order overruling Appellant’s preliminary objections which sought to have the trial court stay the proceedings and compel arbitration alleging that the parties had an agreement to arbitrate the matter at issue. Upon review we conclude Appellant’s preliminary objections should have been granted, and we reverse and remand.

¶ 2 Appellee, Warwick Township Water & Sewer Authority (the Authority) filed a complaint against T.J. Sharp, Inc. (Appellant), Boucher & James Inc. (Boucher) and Adams Associates (Adams). The Authority had contracted with Boucher as an engineer to design and oversee the construction of an expansion project for a wastewater treatment plant. Boucher in turn contracted with Adams to prepare design plans and specifications. Appellant, a contractor, was the successful bidder on the project and became party to the contract documents. Tanks were designed for the project and built to completion, after which the Authority issued final payment to Appellant, who in turn signed *955 a “Contractor’s Release.” The Authority alleged that the tanks had structural problems resulting in cracking which required significant repair and remediation. The Authority thus sought recovery for breach of contract, breach of implied warranties, and negligence against Appellant. Appellant responded with the filing of preliminary objections alleging that the complaint was improperly filed with the Court of Common Pleas of Bucks County because the contract dictated that the parties agreed to submit all disputes arising under the contract to arbitration before the American Arbitration Association. The trial court ultimately overruled Appellant’s preliminary objections, and this appeal followed. 1

¶ 3 Where a party to a civil action seeks to compel arbitration the trial court must first determine if a valid agreement to arbitrate exists between the parties. If the trial court determines that such an agreement does exist, it must then determine if the dispute involved is within the scope of the arbitration provision. “The scope of arbitration is determined by the intention of the parties as ascertained in accordance with the rules governing contracts generally.” Keystone Tech. Group, Inc. v. Kerr Group, Inc., 824 A.2d 1223, 1227 (Pa.Super.2003). If it appears that a dispute relates to a contract’s subject matter and the parties agreed to arbitrate, all issues of interpretation and procedure are for the arbitrators to resolve. Theodore C. Wills Co. v. Sch. Dish, 837 A.2d 1186, 1189 (Pa.Super.2003). The existence of an agreement and whether a dispute is within the scope of the agreement are questions of law and our review is plenary. Keystone, 824 A.2d at 1227.

¶ 4 At issue in this case are the provisions of the contract and the Contractor’s Release. Appellant asserts that the following contract language is applicable and requires arbitration:

16.1 All claims, disputes and other matters in question between [the Authority] and [Appellant] arising out of or relating to the Contract documents or the breach thereof (except for claims which have been waived by the making or acceptance of final payment as provided in paragraph 14.15) will be decided by arbitration in accordance with the Construction Industry Rules of the American Arbitration Association then obtaining ...

In reviewing this language the trial court ultimately concluded that it applied only for disputes arising during construction, not after the completion of construction and final payment. It found support for this in paragraph 9.11 of the contract which provides:

Claims, disputes and other matters relating to the acceptability of the Work or the interpretation of the requirements of the contract documents .. .will be referred initially to ENGINEER in writing with a request for a formal decision. ... ENGINEER’S written decision on such claim, dispute or other matter will be final and binding upon OWNER and CONTRACTOR unless (1) an appeal from the ENGINEER’S decision is taken within the time limits and in accordance with the procedures set forth in [the]... “Dispute Resolution Agreement” entered into between OWNER and CONTRACTOR pursuant to Article 16.

*956 The trial court concluded that this language indicates that the arbitration clause was intended to apply only to claims made during construction and that an ENGINEER’S decision is a condition precedent to submission to arbitration. We do not read paragraph 9.11 of the contract as applicable to the instant situation. Admittedly it sets forth the procedure for disputes which concern the acceptability of work or the interpretation of contract documents, which will presumably occur during construction and which ultimately may lead to arbitration. However the matter at issue concerns the ultimate work product and its performance. It is governed by the terms of the dispute resolution agreement entered into between the Authority and Appellant and specifically paragraph 16.1 as cited by Appellant.

¶ 5 The trial court further found that this particular dispute is outside the arbitration provision because paragraph 16.1 makes an exception “for claims which have been waived by making or acceptance of final payment.” Agreement ¶ 16.1; Trial Court Opinion, 6/11/03, at 4-5. The agreement, however, goes on to provide that the exception shall apply to those claims waived “as provided by paragraph 14.15.” Id. Paragraph 14.15 sets forth which claims are extinguished upon final payment. It provides:

14.15 The making and acceptance of final payment will constitute:
14.15.1. a waiver of all claims by OWNER against CONTRACTOR, except claims arising from unsettled Liens, from defective work appearing after final inspection pursuant to paragraph 14.11, from failure to comply with the Contract documents or the terms of any special guarantees specified therein, or from CONTRACTOR’S continuing obligations under the contract documents; and
14.15.2. a waiver of all claims by CONTRACTOR against OWNER other than those previously made in writing and still unsettled.

(emphasis in original). The language in this paragraph, read in conjunction with paragraph 16.11 directs that the instant dispute be decided by arbitration. This is a dispute of a- claim which has not been waived as a result of final payment. It concerns the Authority’s allegation that Appellant performed defective work which became' apparent after final payment. The Complaint alleges at paragraph 39:

Not until [the Authority’s] receipt of Carroll’s February 2001, assessment of the Project did [the Authority] determine that the defective conditions present in the Project were the result of serious structural design and construction deficiencies that compromised the structural integrity of the Project.

Complaint, ¶ 39.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

Rannard, S. v. Wexford Health Services, Inc.
Superior Court of Pennsylvania, 2026
Dynamic Healthcare v. Philips Medical Capital
Superior Court of Pennsylvania, 2025
Pierce, N. v. Floatme Corp.
Superior Court of Pennsylvania, 2025
Doe, J. v. The Cheesecake Factory
2023 Pa. Super. 153 (Superior Court of Pennsylvania, 2023)
Carvell, K. v. Edward D. Jones and Co., L.P.
Superior Court of Pennsylvania, 2023
Fineman, Krekstein, & Harris, P.C. v. Perr, R.
2022 Pa. Super. 117 (Superior Court of Pennsylvania, 2022)
Braccia, N. v. Braccia/Vistel, LLC
Superior Court of Pennsylvania, 2022
Selectdecks, LLC v. Pittsburgh Stone
Superior Court of Pennsylvania, 2021
In Re:Est. of Atkinson, J., Appeal of: Wells Fargo
2020 Pa. Super. 87 (Superior Court of Pennsylvania, 2020)
Main Street Business Funding v. Goldner, M.
Superior Court of Pennsylvania, 2018
Saltzman v. Thomas Jefferson University Hospitals, Inc.
166 A.3d 465 (Superior Court of Pennsylvania, 2017)
Highmark Inc. v. UPMC
Superior Court of Pennsylvania, 2016
Provenzano, D. v. Ohio Valley General Hosp.
121 A.3d 1085 (Superior Court of Pennsylvania, 2015)
Chighizola v. Beverly Enterprises Inc.
79 Pa. D. & C.4th 416 (Monroe County Court of Common Pleas, 2006)

Cite This Page — Counsel Stack

Bluebook (online)
851 A.2d 953, 2004 Pa. Super. 201, 2004 Pa. Super. LEXIS 1308, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warwick-township-water-sewer-authority-v-boucher-james-inc-pasuperct-2004.