Wärtsilä NSD North America, Inc. v. Hill International, Inc.

342 F. Supp. 2d 267, 2004 U.S. Dist. LEXIS 21856
District Court, D. New Jersey·Decided October 29, 2004·No. Civil Action 99-4565(SSB)·Published·Cited by 6 cases

Opinion

OPINION REGARDING DEFENDANT HILL INTERNATIONAL’S MOTION FOR SUMMARY JUDGMENT

BROTMAN, District Judge.

Defendant Hill International Incorporated (“Hill”) is a construction consulting firm in the business of providing expert advice and project management for major construction projects. Plaintiff Wártsilá NSD North America, Inc (“Wártsilá”) is an engineering and construction company. Presently before the Court is Hill’s motion seeking summary judgment as to the remaining claims in the Amended Complaint: negligence, fraud, and breach of contract. This litigation arises out of a business relationship between Wártsilá Diesel, an engineering and construction company and the predecessor to Plaintiff, and Hill. Richard LeFebvre (“LeFebvre”), one of Hill’s “expert” employees, was assigned to the Wártsilá project, first as a Hill employee but later as an independent contractor on Wártsilá’s payroll. The parties later discovered that LeFebvre lacked the credentials claimed in his resume, as he did not hold either the engineering degrees or the professional certifications represented. Wártsilá’s Complaint alleges that the late discovery of these defects in LeFebvre’s resume ultimately caused Wártsilá to lose millions of dollars in arbitration claims and related litigation. The Court held oral argument on October 20, 2004. 1

I. FACTUAL AND PROCEDURAL BACKGROUND

In July 1994, Wártsilá entered into a contract with Coastal Salvadorian Ltd. (“Coastal”) wherein Wártsilá agreed to design, engineer, procure, construct, start up and test a diesel engine power plant in Nejapa, El Salvador (“the Project”). Wártsilá’s business had focused primarily on the sale and maintenance of diesel engines, so it subcontracted much of the plant’s construction to a variety of other entities, including Black & Veatch International (“BVI”). Within months, the Project fell behind schedule, resulting in numerous contractual disputes between Wártsilá, BVI, and Coastal. (PI. First Am. Compl. ¶ 6.) In an effort to get the project back on track, Wártsilá sought the services of the Defendant, Hill International. (Id. ¶¶ 10, 34.)

According to Wártsilá’s First Amended Complaint, Hill submitted a proposal for the consulting position on January 18, 1995. (Id. ¶ 31.) In its proposal, Hill recommended that Richard LeFebvre (“LeFebvre”), one of the firm’s senior consultants, be assigned to the Project to “collect, organize and evaluate ... factual information and report ... his findings as to the best way to proceed with the completion of the project.” (Id. ¶ 33.) LeFebvre’s responsibilities would include gathering information and materials related to the construction project, visiting the project site “to evaluate the adequacy of the plans and specifications,” and comparing the actual performance of the construction work to Wártsilá’s obligations under its contract with Coastal. (Id.) Hill attached a copy of LeFebvre’s professional resume to the proposal which represented that he had: (a) received a B.S. in electrical engineering from Penn State in 1966; (b) earned a B.A. in business administration from Du-quesne University in 1969; (c) taken courses in business law at the University of North Florida in 1983; and (d) registered and was licensed as a professional engineer in Pennsylvania, New York, and Massachusetts. (Id. ¶ 32.)

*271 On January 24, 1995, Wartsila and Hill entered into a written consulting agreement (the “agreement”) that incorporated by reference the January 18 proposal. (Id. ¶ 34.) Pursuant to the terms of the agreement, Hill assigned Richard Le-Febvre to work as a senior consultant on the Project. (Id. ¶ 35.) As part of his responsibilities, LeFebvre analyzed issues bearing on potential claims and defenses in contractual disputes between Wartsila and BVI. (Id. ¶¶ 38, 39.) LeFebvre was quickly promoted by Wartsila to the position of Project Manager and continued to work on the Project as a Hill employee until May 25, 1995. (Id. ¶¶ 37, 40.)

On June 1, 1995, with Hill’s approval, Wartsila hired LeFebvre “as an independent contractor to provide assistance with construction and claims management on the Project.” (Id. ¶ 41.) Relying on Le-Febvre’s analysis and recommendations, Wartsila decided in May 1996 to pursue claims against BVI before the American Arbitration Association and retained the Louisiana law firm of Chaffe, McCall, Phillips, Toler & Sarpy, L.L.P., and two of its attorneys, John H. Clegg, Esq., and Daphne McNutt, Esq., to initiate arbitration proceedings against BVI in Charlotte, North Carolina. (Id. ¶ 43; Third Party Compl. ¶ 11.) Due to his intimate and extensive knowledge of the facts underlying the dispute as well as his participation in drafting various “claim support” documents LeFebvre was considered a “key witness” in the proceedings. (Pl.’s First Am. Compl. ¶¶ 43-44.)

At the arbitration proceedings in September 1997, LeFebvre offered testimony regarding the academic and professional credentials listed on his resume. (Id. ¶ 47.) On September 8, 1997, counsel for BVI, toward the end of LeFebvre’s direct testimony, requested that LeFebvre execute a release for his background academic information. (Id. ¶ 48.) Wartsila became aware, “for the first time,” that there were questions concerning LeFebvre’s educational and professional credentials. (Id.) Later that day, after the proceedings had been adjourned, LeFebvre admitted to Wartsila’s attorneys that the statement on his resume concerning the business degree from Duquesne University was not accurate. (Id. ¶ 49.) He allegedly told Wartsi-la that Hill had asked him to overstate the extent of his training at Duquesne. (Id.)

The next morning, LeFebvre requested and received from Hill a revised resume. This one omitted any reference to a business degree from Duquesne or business law courses at North Florida and modified the date on which he claimed to have received an electrical engineering degree from Penn State.. (Id. ¶ 50.) When the proceedings resumed later that day, BVI’s attorneys subjected LeFebvre to a idgorous cross-examination, forcing him to acknowledge the obvious inconsistencies between the two resumes. LeFebvre nevertheless insisted that the revised resume was entirely accurate and truthful. (Id. ¶ 50(b).) However, by the conclusion of the day’s proceedings, Wartsila’s attorneys were forced to concede that a hasty investigation into LeFebvre’s academic credentials had uncovered no evidence that he had ever received an engineering degree from Penn State or attended any of the other schools listed on his resume. (Id. ¶ 51.) Wartsila also found no evidence that LeFebvre had ever been licensed as a professional engineer in either New York, Pennsylvania, or Massachusetts. (Id.)

In light of this development, Wartsila’s counsel withdrew LeFebvre’s testimony and the arbitration panel 'granted Wartsila a short recess to restructure its case based on new witnesses. (Id. ¶ 53.) During that time, Wartsila re-examined materials pre *272

Free access — add to your briefcase to read the full text and ask questions with AI

Wärtsilä NSD North America, Inc. v. Hill International, Inc., 342 F. Supp. 2d 267, 2004 U.S. Dist. LEXIS 21856 (D.N.J. 2004).

342 F. Supp. 2d 267 (Wärtsilä NSD North America, Inc. v. Hill International, Inc.) — published by Counsel Stack Legal Research, free access to 12M+ legal documents.

Related