Warth Line, Ltd. v. Merinda Marine Co., Ltd.

778 F. Supp. 158, 1992 A.M.C. 1406, 1991 U.S. Dist. LEXIS 16406, 1991 WL 242945
CourtDistrict Court, S.D. New York
DecidedNovember 12, 1991
Docket91 Civ. 4916 (SWK)
StatusPublished
Cited by2 cases

This text of 778 F. Supp. 158 (Warth Line, Ltd. v. Merinda Marine Co., Ltd.) is published on Counsel Stack Legal Research, covering District Court, S.D. New York primary law. Counsel Stack provides free access to over 12 million legal documents including statutes, case law, regulations, and constitutions.

Bluebook
Warth Line, Ltd. v. Merinda Marine Co., Ltd., 778 F. Supp. 158, 1992 A.M.C. 1406, 1991 U.S. Dist. LEXIS 16406, 1991 WL 242945 (S.D.N.Y. 1991).

Opinion

MEMORANDUM OPINION AND ORDER

KRAM, District Judge.

Petitioner Warth Line, Ltd. (the “Charterer”), moves to vacate an arbitration *159 award dated April 15, 1991 (the “Decision and Award”), pursuant to the United States Arbitration Act, 9 U.S.C. § 10(a)(4), on the grounds that the arbitrators “exceeded their powers, or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.” Respondent Merinda Marine Co., Ltd. (the “Owner”), opposes the petition to vacate and seeks confirmation of the Award.

BACKGROUND

In March of 1987, the Owner and Charterer entered into a Time Charter Party contract for the vessel M/V LEONIDAS GLORY, at $1,950 per day (the “Charter Party”). The Charter Party called for the vessel to load granite blocks at Mangalore, India, during April and May, 1987. These granite blocks were to be discharged at Santander, Spain, St. Malo, France and Antwerp, Belgium. On route to Santander, the vessel encountered heavy weather which the Owner claimed caused delays in arriving at the designated ports of discharge.

Consequently, the Charterer claimed damages for underperformance in the amount of $39,622.00, based upon a delay of 11.34 days as compared to a routine voyage. The Charterer asserted its claim for underperformance in the Court of Commerce in Antwerp, under Belgian law. At the Charterer’s request, the Court of Commerce issued a Detention Order which prevented the LEONIDAS GLORY from sailing from the court’s jurisdiction, and appointed a neutral Nautical Surveyor to investigate the vessel’s records in order to determine and report the causes of the alleged delay.

The Charterer informed the Owner that in lieu of arresting the vessel it would accept a letter of guarantee in the amount of $45,000, as security for any liability due to the vessel’s underperformance. Although the Owner had made arrangements to drydock the vessel for a Class Survey in a Netherlands shipyard the day after discharge, May 27, 1987, and an arrest would prevent the Owner from going on drydock as scheduled, the Owner refused to post the security. As a result, the Charterer applied to the Belgian Court and obtained an order of arrest for the LEONIDAS GLORY. Under Belgian law, 1 the Owner was permitted to contest the arrest but failed to do so, even though it was represented in Antwerp. 2

The vessel was subsequently arrested on May 26,1987, after completion of discharge at Antwerp. After the arrest, the Owner posted adequate security, the arrest was lifted and the vessel was allowed to sail from Antwerp. However, due to the arrest the vessel was delayed in Antwerp for two days.

During the vessel’s detention, the Nautical Surveyor determined that the LEONIDAS GLORY had indeed underperformed for a total of 118 hours, or 4 days and 22 hours (as opposed to the 11.34 days claimed *160 by the Charterer) on the voyage from Man-galore to Antwerp. The Surveyor also found that the Charterer should be compensated in the amount of $17,709.89.

After this determination, the Owner invoked the arbitration clause of the Charter Party contract, 3 and sought arbitration of the various claims and cross-claims at New York. The claims and cross-claims were as follows: (1) The Charterer claimed the $17,-708.89 to which the Nautical Surveyor determined it was entitled as a result of underperformance; (2) The Owner claimed damages for unpaid freight, repairs necessitated by stevedores, fees and expenses incurred at Antwerp due to the arrest, expenses incurred due to the postponement of scheduled drydocking while the vessel was under arrest at Antwerp, including the costs of arranging drydocking in Greece, the cost of the extra drydocking, the costs of the arbitration proceeding and the cost of the letter of guarantee posted in Antwerp. Pre-hearing submissions were presented to a Panel of three arbitrators (the “Panel”), which was formed in accordance with Clause 17, and a hearing was held on March 29, 1990.

On April 15, 1991, the Panel issued a Decision and Award in which it denied the Charterer’s claims. Contrary to the Nautical Surveyor, the Panel concluded that the weather conditions during the voyage and the Captain’s concern for safety were serious enough to justify the Captain’s decision to seek shelter at Crete and reduce the speed of the vessel. Thus, the delay was justified, and the Charterer was not entitled to recover for underperformance. The Panel further concluded that the arrest of the vessel was

wrongful and unjustified under the circumstances because Charterers could have started their investigation of alleged speed loss at the first two discharge ports instead of waiting till [sic] two hours before completion of discharge. Owners would then have had plenty of time to grant Charterers Letter of Undertaking without the vessel being delayed two days.

Decision and Award, Exhibit “A” to DeOrchis Aff., at 15.

Based upon these findings, the Panel awarded the Owner $75,068.28. According to the Charterer, $49,013 of this award was intended to reimburse the Owner for expenses relating to what the arbitrators deemed the “wrongful and unjustified” arrest. 4 The Charterer moves to vacate only this portion of the award. 5 The Charterer *161 alleges that in awarding the Owner $49,013 for expenses incurred in connection with the Belgian arrest, the “arbitrators exceeded their powers, or so imperfectly executed them that a mutual, final and definite award upon the subject matter submitted was not made.” 9 U.S.C. § 10(a)(4).

DISCUSSION

The United States Arbitration Act, 9 U.S.C. § 10(a), provides that either party to an arbitration may move to vacate the arbitration award. The grounds for vacating an arbitration award, however, are extremely limited. See Sweeney v. Morganroth, 451 F.Supp. 367, 369 (S.D.N.Y.1978) (court’s review of an arbitrator’s award is necessarily “severely limited,” being confined to the grounds specified in 9 U.S.C. § 10). They are as follows:

(1) Where the award was procured by corruption, fraud, or undue influence.
(2) Where there was evident partiality or corruption in the arbitrators, or either of them.
(3) Where the arbitrators were guilty of misconduct in refusing to postpone the hearing, upon sufficient cause shown, or in refusing to hear evidence pertinent and material to the controversy; or of any other misbehavior by which the rights of any party have been prejudiced.

Free access — add to your briefcase to read the full text and ask questions with AI

Related

May Ship Repair Contracting Corp. v. Barge Columbia New York
160 F. Supp. 2d 594 (S.D. New York, 2001)
Siegel v. Prudential Ins. Co. of America
79 Cal. Rptr. 2d 726 (California Court of Appeal, 1998)

Cite This Page — Counsel Stack

Bluebook (online)
778 F. Supp. 158, 1992 A.M.C. 1406, 1991 U.S. Dist. LEXIS 16406, 1991 WL 242945, Counsel Stack Legal Research, https://law.counselstack.com/opinion/warth-line-ltd-v-merinda-marine-co-ltd-nysd-1991.